One story - permanent living quarter
73-46 196 PLACE
QUEENS · BIN 4154403
💬 Discuss this project
1950Year Built
1Stories
A2Building Class
R2AZoning
1,357 sfGross Floor Area
1Units
One story - permanent living quarter · 6,000 sf lot · 0.23 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GREEN RIVER ENVIRONMENTAL ENGINEERI112/14/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY State Solar LLC103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYSS LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREEN RIVER ENVIRONMENTAL7841112/14/2023
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
08/12/2024
Signed off — Alteration
Installation of solar photovoltaic array per plans
Q00975787-I1
02/08/2024
Permit issued — Solar
Q00975787-I1-SL
12/14/2023
Filed — Alteration
Installation of solar photovoltaic array per plans
Q00975787-I1
12/12/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
12/12/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
ROBERT MASONE
12/12/2023
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
12/12/2023
Special inspection requirement — Final
ROBERT MASONE
12/12/2023
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYSS LLC02/08/2024
1 project · most recent 12/06/2023
FiledStatusContractorScope
12/06/2023CompleteNY SOLAR ELECTRICAL LLC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
12/12/2023Fire-Resistant Penetrations and JointsROBERT MASONEspecial
12/12/2023Structural Stability – Alterations of existing buildingsROBERT MASONEspecial
12/12/2023Energy Code Compliance InspectionsROBERT MASONEprogress
12/12/2023FinalROBERT MASONEprogress
12/12/2023Air barrier - visual inspectionROBERT MASONEenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/23/2026Q00975787-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
09/02/2026Q00975787-I1Open ↗
09/02/2026Q00975787-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/23/2026Q00975787-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/02/2026Q00975787-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/23/2026Q00975787-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00975787-I1Open ↗