| Owner | Filings | Most Recent |
|---|---|---|
| 73 FIFTH AVENUE CONDOMINIUM | 28 | 09/19/2026 |
| CFA MANAGEMENT | 33 | 07/08/2026 |
| 73- 5TH AVE ASSOC. | 1 | 03/22/2026 |
| 73 5 AVE CONDOMINIUM ASSO | 1 | 03/22/2026 |
| THE OWNER OF | 1 | 03/22/2026 |
| CHARTER COMMUNICATIONS | 1 | 03/22/2026 |
| ACE ATLAS CORP | 1 | 03/21/2026 |
| 73 STORE | 32 | 03/21/2026 |
| 73 5TH AVE CONDOMINIUM | 10 | 03/21/2026 |
| COLGATE ENTERPRISE | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PETER V STOREY | 2 | 06/11/2026 |
| DAVID TURNER ARCHITECT PC | 8 | 02/19/2026 |
| EN-POWER GROUP | 1 | 08/14/2025 |
| PAUL PERDEK, PROF. ENG. PLLC | 2 | 10/09/2024 |
| ASHRAF CORP | 1 | 11/01/2023 |
| THOMAS A FENNIMAN ARCHITECT | 1 | 05/04/2023 |
| BLUE SKY DESIGN, INC. | 3 | 03/06/2023 |
| KLH PROFESSIONAL ENGINEERS, PSC P.C | 4 | 01/19/2023 |
| LALIRE MARCH ARCHITECTS LLP | 2 | 11/17/2022 |
| CES ENGINEERING LLC | 7 | 11/11/2022 |
| SIGLER HENDERSON STUDIO LLC | 2 | 11/18/2021 |
| ANDREW B.BALLARD,AIA ARCHITECT,PLLC | 1 | 07/21/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 24 | 03/21/2026 |
| JAM CONSULTANTS, INC. | 34 | 03/21/2026 |
| J A EXPEDITING | 2 | 03/21/2026 |
| CODE | 4 | 03/21/2026 |
| KD DESIGNS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRESERV BLD RESTOR MGT IN | General Contractor | 11 | 07/08/2026 |
| REAZ MOHAMMED | Electrical | 8 | 03/21/2026 |
| SCORDIO CONSTRUCTION INC | General Contractor | 8 | 07/08/2026 |
| HUDSON BLACK INC | General Contractor | 4 | 07/08/2026 |
| ARSENAL SCAFFOLD INC | General Contractor | 3 | 04/09/2026 |
| EFFICIENT CLIMATE SOLUTIO | General Contractor | 2 | 07/30/2026 |
| LITUEV, ANDREI | Electrical | 2 | 03/21/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| ALL BOROUGH GROUP SVC INC | General Contractor | 2 | 07/08/2026 |
| SYED-NAQVI ALTAF | Electrical | 1 | 03/21/2026 |
| SYED-NAQVI, ALTAF | Electrical | 1 | 03/21/2026 |
| ALLSTATE SPRINKLER LLC | Fire Protection | 1 | 07/08/2026 |
| DYNAMIC PLBNG & SPRKR COR | Fire Protection | 1 | 06/28/2026 |
| FULL CAPACITY FIRE CORP | Fire Protection | 1 | 07/08/2026 |
| PACIFIC PLBG. & HTG. CORP | Fire Protection | 1 | 09/19/2026 |
| MELE CONTRACTING, INC | General Contractor | 1 | 04/09/2026 |
| NEW YORK GENERAL CONST* | General Contractor | 1 | 06/28/2026 |
| QHF CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| COPPER PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| DYNAMIC PLBG & SPRKLR COR | Plumbing | 1 | 06/28/2026 |
| GREGG NY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| ABE HIMELFARB | Electrical | 1 | 03/21/2026 |
| THOMAS F. CASH & SONS INC | Plumbing | 1 | 09/18/2026 |
| CHARLES, ANDELL | Electrical | 1 | 03/21/2026 |
| DOROWSKY, HARRY | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| O'ROURKE ENGINEERING, LLC | 5873 | 1 | 06/11/2026 |
| DAVID TURNER ARCHITECT PC | 3829 | 2 | 02/19/2026 |
| JOSEPH BOTTA, PE, PC | 1139 | 2 | 02/19/2026 |
| SWL ENGINEERING INSPECTIO | 6912 | 2 | 08/14/2025 |
| GROUP-S LLC | 5216 | 1 | 08/14/2025 |
| LEO Y LEE ASSOCIATES | 2481 | 1 | 12/04/2023 |
| THOMAS A. FENNIMAN ARCHIT | 260 | 1 | 05/04/2023 |
| BLUE SKY DESIGN, INC. | 1908 | 3 | 03/06/2023 |
| SOCOTEC ENGINEERING | 4983 | 5 | 01/19/2023 |
| CATALPA SPECIAL INSPECTIO | 2004 | 8 | 11/11/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | PACIFIC PLBG. & HTG. CORP | 09/18/2026 |
| DOB NOW | Plumbing | Permit Issued | THOMAS F. CASH & SONS INC | 09/17/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | EFFICIENT CLIMATE SOLUTIO | 07/29/2026 |
| DOB NOW | General Construction | Permit Issued | NEW YORK GENERAL CONST* | 06/26/2026 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PRESERV BLD RESTOR MGT IN | 05/13/2026 |
| DOB NOW | General Construction | Permit Issued | ALL BOROUGH GROUP SVC INC | 05/11/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRESERV BUILDING RESTORAT | 01/28/2026 |
| DOB NOW | General Construction | Signed-off | PRESERV BLD RESTOR MGT IN | 12/30/2025 |
| DOB NOW | General Construction | Signed-off | PRESERV BLD RESTOR MGT IN | 11/21/2025 |
| DOB NOW | General Construction | Permit Issued | QHF CONSTRUCTION INC | 08/20/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | EFFICIENT CLIMATE SOLUTIO | 07/28/2025 |
| DOB NOW | Sprinklers | Permit Issued | CITYWIDE PLBG, HTG &SPRKL | 06/16/2025 |
| DOB NOW | Plumbing | Permit Issued | CITYWIDE PLBG HTG & SPKLS | 05/22/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PRESERV BLD RESTOR MGT IN | 05/12/2025 |
| DOB NOW | General Construction | Permit Issued | ALL BOROUGH GROUP SVC INC | 05/02/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRESERV BUILDING RESTORAT | 02/06/2025 |
| DOB NOW | General Construction | Signed-off | PRESERV BLD RESTOR MGT IN | 11/26/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 10/29/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PRESERV BLD RESTOR MGT IN | 10/11/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRESERV BUILDING RESTORAT | 08/02/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRESERV BUILDING RESTORAT | 07/02/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRESERV BUILDING RESTORAT | 05/31/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PRESERV BLD RESTOR MGT IN | 05/03/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRESERV BUILDING RESTORAT | 02/07/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRESERV BUILDING RESTORAT | 01/26/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | PRESERV BUILDING RESTORAT | 12/27/2023 |
| DOB NOW | General Construction | Signed-off | PRESERV BLD RESTOR MGT IN | 12/05/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 11/02/2023 |
| DOB NOW | General Construction | Signed-off | SCORDIO CONSTRUCTION INC | 09/29/2023 |
| DOB NOW | Structural | Signed-off | SCORDIO CONSTRUCTION INC | 08/04/2023 |
| DOB NOW | Sprinklers | Signed-off | FULL CAPACITY FIRE CORP | 09/14/2022 |
| DOB NOW | Mechanical Systems | Signed-off | HUDSON BLACK INC | 09/09/2022 |
| DOB NOW | Plumbing | Signed-off | COPPER MECHANICAL INC | 09/03/2022 |
| DOB NOW | General Construction | Signed-off | HUDSON BLACK INC | 08/30/2022 |
| DOB NOW | Plumbing | Signed-off | ORBIT PLBG & HTG INC | 08/16/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SCORDIO CONSTRUCTION INC | 04/11/2022 |
| DOB NOW | General Construction | Signed-off | SCORDIO CONSTRUCTION INC | 04/08/2022 |
| DOB NOW | General Construction | Signed-off | MELE CONTRACTING, INC | 03/29/2022 |
| DOB NOW | Plumbing | Signed-off | GREGG NY PLUMBING, INC | 03/11/2022 |
| DOB NOW | Sprinklers | Signed-off | ALLSTATE SPRINKLER LLC | 11/16/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/11/2026 | — | — | Water/Sanitary |
| 06/20/2025 | Permit Issued | THOMAS F. CASH & SONS INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/08/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 08/28/2026 | Permit Issued | KWONG MING ELECTRIC INC | General Wiring |
| 06/03/2026 | Permit Issued | S & D ELECTRIC NY CORP | General Wiring |
| 04/21/2026 | Permit Issued | EIS ELECTRIC CORP DBA | General Wiring |
| 04/05/2026 | Complete | BANNER ELECTRIC INC | General Wiring |
| 02/16/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 02/12/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 02/12/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 02/12/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 02/12/2026 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 02/12/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 02/12/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 02/12/2026 | Permit Issued | THE METRO GROUP ELECTRIC | General Wiring |
| 02/04/2026 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 11/19/2025 | Permit Issued | CEL SVCS INC DBA CEL ELEC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/04/2025 | Permit Issued | PRESERV BUILDING RESTORAT | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/08/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 08/14/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/17/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/10/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/16/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/13/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/08/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/28/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/26/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/21/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/18/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/18/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/16/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/01/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/04/2026 | Fire-Resistant Penetrations and Joints | BRIAN O'ROURKE | special |
| 06/03/2026 | Fire-Resistance Rated Construction | Peter Storey | progress |
| 06/03/2026 | Final | Peter Storey | progress |
| 03/10/2026 | Final | TARIQ SIDDIQUI | progress |
| 03/10/2026 | Energy Code Compliance Inspections | DAVID TURNER | progress |
| 03/10/2026 | Mechanical Systems | DAVID TURNER | special |
| 03/02/2026 | Sprinkler Systems | JOSEPH BOTTA | special |
| 02/16/2026 | Sprinkler Systems | JOSEPH BOTTA | special |
| 08/08/2025 | Fire-Resistant Penetrations and Joints | MICHAEL SCORRANO | special |
| 08/08/2025 | Fire-Resistance Rated Construction | MICHAEL SCORRANO | progress |
| 08/08/2025 | Final | MICHAEL SCORRANO | progress |
| 08/08/2025 | Tenant Protection Plan Compliance | JOSHUA LUCKRITZ | special |
| 05/13/2023 | Structural Stability – Alterations of existing buildings | ANDREW RENFROE | special |
| 05/13/2023 | Structural Steel - Welding | ANDREW RENFROE | special |
| 05/13/2023 | Structural Steel - Details | ANDREW RENFROE | special |
| 05/13/2023 | Final | ANDREW RENFROE | progress |
| 05/13/2023 | Structural Steel - High Strength Bolting | ANDREW RENFROE | special |
| 04/26/2023 | Structural Stability – Alterations of existing buildings | ANDREW RENFROE | special |
| 04/20/2023 | Tenant Protection Plan Compliance | JOSHUA LUCKRITZ | special |
| 04/19/2023 | Post-installed Anchors | Thomas Fenniman | special |
| 04/19/2023 | Masonry | Thomas Fenniman | special |
| 04/19/2023 | Structural Stability – Alterations of existing buildings | Thomas Fenniman | special |
| 04/18/2023 | Final | Thomas Fenniman | progress |
| 01/11/2023 | Structural Steel - High Strength Bolting | ANDREW RENFROE | special |
| 01/11/2023 | Final | ANDREW RENFROE | progress |