← Back
STATEN ISLAND
73 HEMLOCK STREET
STATEN ISLAND · BIN 5175378
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction1p · 1 filing · 10 docs
Floor 2Under Construction14p · 2 filings · 20 docs
Floor 1Under Construction14p · 2 filings · 20 docs
Basement12p · 1 filing · 20 docs
1 job · most recent 07/11/2023
Gas Storm Water/Sanitary
FiledStatusContractorScope
07/11/2023Signed-offCAPITAL CONTR P&H CORPGas, Storm, Water/Sanitary
1 job · most recent 06/26/2023
General Wiring
FiledStatusContractorScope
06/26/2023CompleteTRUE ELECTRIC CORP.General Wiring
1 job · most recent 07/11/2023
Concrete Wood
FiledStatusContractorScope
07/11/2023Signed-offBLUE STAR GROUP LLCConcrete, Wood
1 job · most recent 07/11/2023
Fence
FiledStatusContractorScope
07/11/2023Signed-offBLUE STAR GROUP LLCFence
1 job · most recent 07/11/2023
Earthwork
FiledStatusContractorScope
07/11/2023Signed-offBLUE STAR GROUP LLCEarthwork
Building Lifecycle
All (66)Filed (9)Permit Issued (9)Signed Off (3)Violation (1)Inspection (10)Objection (4)Special Inspection (30)
08/11/2026
Permit issued — General Construction
S01412179-I1-GC
07/27/2026
Objection resolved — Addressed
07/01/2026
Special inspection requirement — Air barrier - visual inspection
anthony santoro
07/01/2026
Special inspection requirement — Air barrier — testing
anthony santoro
07/01/2026
Special inspection requirement — Insulation placement and R values
anthony santoro
07/01/2026
Special inspection requirement — Interior lighting power
anthony santoro
07/01/2026
Special inspection requirement — Fenestration air leakage
anthony santoro
07/01/2026
Special inspection requirement — Air barrier continuity plan testing
anthony santoro
07/01/2026
Special inspection requirement — Fenestration areas
anthony santoro
07/01/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
anthony santoro
07/01/2026
Special inspection requirement — Duct leakage testing, insulation and design
anthony santoro
06/24/2026
Objection raised — Scope
06/04/2026
Filed — Alteration
THE SCOPE OF WORK IS LIMITED TO EXISTING OPEN TO BELOW SPAVE BEING CONVERTED TO A NEW BEDROOM ON THE SECOND FLOOR. A PORTION OF THE SECOND FLOOR FRONT BALCONY IS ALSO BEING CONVERTED TO A NEW BEDROOM. NEW PORTION OF ROOF TO BE INSTALLED ABOVE NEW BEDROOM.
S01412179-I1
06/04/2026
Violation issued (ECB, open)
Construction
06/04/2026
Special inspection requirement — Fire-Resistance Rated Construction
anthony santoro
06/04/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
anthony santoro
06/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
anthony santoro
06/04/2026
Special inspection requirement — Energy Code Compliance Inspections
anthony santoro
08/14/2023
Signed off — New Building
PROPOSED INSTALLATION OF 18' WIDE CURB CUT FOR NEW DETACHED TWO FAMILY DWELLING.
S00729062-S1
08/11/2023
Signed off — New Building
PROPOSED INSTALLATION OF 18' WIDE CURB CUT FOR NEW DETACHED TWO FAMILY DWELLING.
S00729062-S2
07/24/2023
Special inspection requirement — Footing and Foundation
anthony santoro
07/24/2023
Special inspection requirement — Lighting in dwelling units
anthony santoro
07/24/2023
Special inspection requirement — Subgrade Inspections
anthony santoro
07/24/2023
Special inspection requirement — Protection of exposed foundation insulation
anthony santoro
07/24/2023
Special inspection requirement — HVAC-R and service water heating equipment
anthony santoro
07/24/2023
Special inspection requirement — Structural Wood Frame
anthony santoro
07/24/2023
Special inspection requirement — Mechanical Systems
anthony santoro
07/24/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
anthony santoro
07/24/2023
Special inspection requirement — Interior lighting power
anthony santoro
07/24/2023
Special inspection requirement — Electric vehicle service equipment requirements
anthony santoro
07/24/2023
Special inspection requirement — Duct leakage testing, insulation and design
anthony santoro
07/24/2023
Special inspection requirement — Fenestration air leakage
anthony santoro
07/24/2023
Special inspection requirement — Permanent certificate
anthony santoro
07/24/2023
Special inspection requirement — Insulation placement and R values
anthony santoro
07/24/2023
Special inspection requirement — HVAC-R and service water heating system controls
anthony santoro
07/24/2023
Special inspection requirement — Fenestration areas
anthony santoro
07/24/2023
Special inspection requirement — Ventilation and air distribution system
anthony santoro
07/12/2023
Signed off — New Building
PROPOSED INSTALLATION OF 18' WIDE CURB CUT FOR NEW DETACHED TWO FAMILY DWELLING.
S00729062-S3
07/11/2023
Filed — New Building
PROPOSED INSTALLATION OF 18' WIDE CURB CUT FOR NEW DETACHED TWO FAMILY DWELLING.
S00729062-P4
07/10/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/10/2023
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
07/10/2023
Inspection — Pass-Final Fence Non-Directive 14
Pass
View inspection ↗
07/05/2023
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/25/2023
Filed — New Building
PROPOSED INSTALLATION OF 18' WIDE CURB CUT FOR NEW DETACHED TWO FAMILY DWELLING.
S00729062-P3
05/17/2023
Permit issued — Curb Cut
S00729062-S3-CC
05/11/2023
Filed — New Building
PROPOSED INSTALLATION OF 18' WIDE CURB CUT FOR NEW DETACHED TWO FAMILY DWELLING.
S00729062-S3
04/13/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/12/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
01/12/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
01/11/2023
Filed — New Building
PROPOSED INSTALLATION OF 18' WIDE CURB CUT FOR NEW DETACHED TWO FAMILY DWELLING.
S00729062-P2
11/17/2022
Permit issued — Foundation
S00729062-I1-GC-CX
11/17/2022
Permit issued — Construction Fence
S00729062-S1-FN
11/16/2022
Filed — New Building
PROPOSED INSTALLATION OF 18' WIDE CURB CUT FOR NEW DETACHED TWO FAMILY DWELLING.
S00729062-P1
11/03/2022
Permit issued — Construction Fence
S00729062-S1-FN
11/01/2022
Permit issued — General Construction
S00729062-I1-GC-CX
10/26/2022
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
10/25/2022
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
10/20/2022
Permit issued — Plumbing
S89403840-S2-PL
07/29/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/18/2022
Permit issued — Plumbing
S00729062-S2-PL
Latest 60 of 66 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BLUE STAR GROUP409/02/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JOSEPH M. MORACE, A.I.A., ARCHITECT906/04/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BLUE STAR HOLDING1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BLUE STAR GROUP LLCGeneral Contractor1008/12/2026
CAPITAL CONTR P&H CORPPlumbing107/08/2026
R&M PIPING & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
A TECH ENGINEERING NYC, P6738406/04/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedBLUE STAR GROUP LLC08/11/2026
DOB NOWCurb CutSigned-offBLUE STAR GROUP LLC05/17/2023
DOB NOWFoundationPermit IssuedBLUE STAR GROUP LLC11/17/2022
DOB NOWConstruction FenceSigned-offBLUE STAR GROUP LLC11/17/2022
DOB NOWConstruction FenceSigned-offBLUE STAR GROUP LLC11/03/2022
DOB NOWGeneral ConstructionPermit IssuedBLUE STAR GROUP LLC11/01/2022
DOB NOWPlumbingSigned-offR&M PIPING & HTG INC10/20/2022
DOB NOWPlumbingSigned-offCAPITAL CONTR P&H CORP07/18/2022
DOB NOWGeneral ConstructionPermit IssuedBLUE STAR GROUP LLC06/24/2022
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
07/10/2023Pass-Final CND-Occupancy InspectionPassView ↗
07/10/2023Pass-Final Curb Cut Non-Directive 14PassView ↗
07/10/2023Pass-Final Fence Non-Directive 14PassView ↗
07/05/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/13/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/12/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
01/12/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/26/2022Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
10/25/2022Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
07/29/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 100
DateRequirementInspectorRole
07/01/2026Fenestration air leakageanthony santoroenergy_progress
07/01/2026Air barrier - visual inspectionanthony santoroenergy_progress
07/01/2026Interior lighting poweranthony santoroenergy_progress
07/01/2026Air barrier — testing anthony santoroenergy_progress
07/01/2026Duct leakage testing, insulation and designanthony santoroenergy_progress
07/01/2026Insulation placement and R valuesanthony santoroenergy_progress
07/01/2026Fenestration and door U-factor and product ratingsanthony santoroenergy_progress
07/01/2026Air barrier continuity plan testinganthony santoroenergy_progress
07/01/2026Fenestration areasanthony santoroenergy_progress
06/04/2026Structural Stability – Alterations of existing buildingsanthony santorospecial
06/04/2026Fire-Resistance Rated Constructionanthony santoroprogress
06/04/2026Energy Code Compliance Inspectionsanthony santoroprogress
06/04/2026Fire-Resistant Penetrations and Jointsanthony santorospecial
07/24/2023Lighting in dwelling unitsanthony santoroenergy_progress
07/24/2023Fenestration areasanthony santoroenergy_progress
07/24/2023Fireplacesanthony santoroenergy_progress
07/24/2023HVAC-R and service water piping design and insulationanthony santoroenergy_progress
07/24/2023Air barrier - visual inspectionanthony santoroenergy_progress
07/24/2023Maintenance informationanthony santoroenergy_progress
07/24/2023Air barrier continuity plan testinganthony santoroenergy_progress
07/24/2023Air barrier — testing anthony santoroenergy_progress
07/24/2023Interior lighting poweranthony santoroenergy_progress
07/24/2023Fenestration and door U-factor and product ratingsanthony santoroenergy_progress
07/24/2023Electric vehicle service equipment requirementsanthony santoroenergy_progress
07/24/2023Duct leakage testing, insulation and designanthony santoroenergy_progress
Latest 25 of 100.
▾Documents — 92 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/23/2026S00729062-S1Request digital key ↗
08/23/2026S00729062-S2Request digital key ↗
08/23/2026S00729062-P4Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits4
▸BISBPP-5 - Authorization to the Department of Transportation2
06/28/2023540211466Open ↗
03/14/2022540211466Open ↗
▸BISPARKS DEPARTMENT PERMIT FOR REMOVING TREES1
06/28/2023540211466Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
05/22/2023540211466Open ↗
▸Zoning, Tax Lot & Property Records10
▸DOB NOWZD1: DOB Zoning Diagram4
08/23/2026S00729062-P3Open ↗
08/15/2026S00729062-I1Open ↗
08/14/2026S01412179-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWZoning Exhibit form (1-5)4
08/23/2026S00729062-P3Open ↗
08/15/2026S00729062-I1Open ↗
08/14/2026S01412179-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTAX LOT: FINAL LOT NUMBER ISSUED1
03/14/2022540211466Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00729062-I1Open ↗
▸Seals & Professional Certifications29
▸DOB NOWProgress Inspector Seal & Signature11
09/01/2026S00729062-I1Open ↗
09/01/2026S00729062-I1Open ↗
09/01/2026S00729062-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/23/2026S00729062-I1Open ↗
08/23/2026S00729062-P3Open ↗
08/23/2026S00729062-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/01/2026S00729062-I1Open ↗
09/01/2026S00729062-I1Open ↗
08/28/2026S00729062-P4Open ↗
Showing 3 of 7 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
12/22/2021540211466Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
12/22/2021540211466Open ↗
▸Trade Schedules & Equipment3
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)3
08/23/2026S00729062-P3Open ↗
08/15/2026S00729062-I1Open ↗
08/13/2026S00729062-P4Open ↗
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist3
08/23/2026S00729062-P3Open ↗
08/15/2026S00729062-I1Open ↗
08/13/2026S00729062-P4Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026S00729062-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026S00729062-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026S00729062-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026S00729062-I1Open ↗
▸Inspections & Test Reports6
▸DOB NOWSOIL REPORT3
08/23/2026S00729062-P3Open ↗
08/15/2026S00729062-I1Open ↗
08/13/2026S00729062-P4Open ↗
▸BISBPP-9 - Request for Builders Pavement Field Inspection1
12/22/2021540211466Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026S00729062-I1Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026S00729062-I1Open ↗
▸Approvals, Objections & Sign-offs2
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff2
06/28/2023540211466Open ↗
03/14/2022540211466Open ↗
▸Filing & Intake Forms3
▸BISADDITIONAL INFORMATION2
06/28/2023540211466Open ↗
03/14/2022540211466Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
12/22/2021540211466Open ↗
▸Other Documents19
▸DOB NOWProperty Ownership Certification6
08/23/2026S00729062-S2Open ↗
08/23/2026S00729062-P3Open ↗
08/23/2026S00729062-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSite Survey: Initial4
08/23/2026S00729062-P3Open ↗
08/15/2026S00729062-I1Open ↗
08/14/2026S01412179-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
08/23/2026S00729062-P3Open ↗
08/15/2026S00729062-I1Open ↗
08/14/2026S01412179-I1Open ↗
Showing 3 of 4 on file for this type
▸BISBPP - SUPPORTING DOCUMENTATION2
03/14/2022540211466Open ↗
12/22/2021540211466Open ↗
▸BISBPP - DOT Builders Pavement Unit Waiver Request Form1
03/14/2022540211466Open ↗
▸DOB NOWPlot Diagram1
08/14/2026S01412179-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026S00729062-I1Open ↗