← Back
Two family frame
73 MONTAUK AVENUE
BROOKLYN · East New York (North) · BIN 3088439
💬 Discuss this project
1910Year Built
2Stories
B2Building Class
R5BZoning
1,900 sfGross Floor Area
2Units
13 Open Violations 4 unresolved · 9 paperwork only ▸FDNY Report ↗
Two family frame · 2,117 sf lot · 0.9 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralPlumbing
Cellar4p · 1 filing · 16 docs
Site & exterior1p · 1 filing · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FEDERAL NATIONAL MORTGAGE203/22/2026
MONROE 719103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
08/04/2023$950K—Private party → Private party$500/sf building
10/23/2014$550K—MONROE 719 LLC → Private party$289/sf building
02/28/2014$233K—FANNIE MAE AKA FEDERAL NATIONAL MORTGAGE ASSOC → MONROE 719 LLC$123/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ABEJA ENGINEERING PLLC212/31/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
COMMERCIAL CAPITAL USA403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DESIGN PROCURE BUILD LLCGeneral Contractor203/21/2026
GLENNS PLUMBING SVCS INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ABEJA ENGINEERING PLLC7269212/31/2023
Building Lifecycle
All (79)Filed (2)Permit Issued (2)Violation (57)Inspection (10)Special Inspection (8)
05/06/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/02/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/29/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/01/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/26/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/13/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/12/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/22/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
02/22/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/22/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
01/23/2024
Permit issued — Plumbing
B00948166-S1-PL
01/02/2024
Permit issued — Structural
B00948166-I1-GC-CX
12/31/2023
Filed — Alteration
B00948166-S1
12/01/2023
Filed — Alteration
B00948166-I1
10/14/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
JOHANN VELEZ
10/14/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
JOHANN VELEZ
10/14/2023
Special inspection requirement — Masonry
JOHANN VELEZ
10/14/2023
Special inspection requirement — Final
JOHANN VELEZ
10/14/2023
Special inspection requirement — Footing and Foundation
JOHANN VELEZ
10/14/2023
Special inspection requirement — Energy Code Compliance Inspections
JOHANN VELEZ
10/14/2023
Special inspection requirement — Fire-Resistance Rated Construction
JOHANN VELEZ
10/14/2023
Special inspection requirement — Interior lighting power
JOHANN VELEZ
11/24/2015
Violation issued (ECB, open)
Construction
11/06/2015
Violation issued (ECB, closed)
Construction
11/06/2015
Violation issued (ECB, open)
Construction
04/02/2015
Violation issued (ECB, open)
Construction
04/02/2015
Violation issued (HPD, open)
B
11/17/2014
Violation issued (ECB, closed)
Construction
02/09/2011
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/02/2010
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/12/2010
Violation issued (ECB, open)
Construction
09/09/2010
Violation issued (ECB, open)
Construction
08/05/2010
Violation issued (HPD, closed)
C
08/05/2010
Violation issued (HPD, closed)
B
08/05/2010
Violation issued (HPD, closed)
B
05/18/2010
Violation issued (ECB, open)
Construction
03/31/2010
Violation issued (HPD, closed)
B
03/31/2010
Violation issued (HPD, closed)
B
03/31/2010
Violation issued (HPD, closed)
B
03/31/2010
Violation issued (HPD, closed)
B
03/19/2010
Violation issued (HPD, closed)
C
03/19/2010
Violation issued (HPD, closed)
B
03/19/2010
Violation issued (HPD, closed)
C
03/19/2010
Violation issued (HPD, closed)
C
01/24/2010
Violation issued (HPD, closed)
B
01/24/2010
Violation issued (HPD, closed)
B
01/24/2010
Violation issued (HPD, closed)
B
01/24/2010
Violation issued (HPD, closed)
B
01/24/2010
Violation issued (HPD, closed)
B
01/14/2010
Violation issued (ECB, open)
Construction
12/15/2009
Violation issued (HPD, closed)
A
12/15/2009
Violation issued (HPD, closed)
B
11/06/2009
Violation issued (ECB, open)
Construction
09/11/2009
Violation issued (ECB, open)
Construction
08/16/2009
Violation issued (HPD, closed)
B
08/16/2009
Violation issued (HPD, closed)
B
08/16/2009
Violation issued (HPD, closed)
B
07/17/2009
Violation issued (HPD, closed)
B
07/09/2009
Violation issued (HPD, closed)
A
07/06/2009
Violation issued (HPD, closed)
C
Latest 60 of 79 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedGLENNS PLUMBING SVCS INC01/23/2024
DOB NOWStructuralPermit IssuedDESIGN PROCURE BUILD01/02/2024
BISOTISSUEDCENTURION SOLAR ENERGY09/21/2022
1 project · most recent 12/31/2023
Gas Water/Sanitary
FiledStatusContractorScope
12/31/2023Permit IssuedGLENNS PLUMBING SVCS INCGas, Water/Sanitary
2 projects · most recent 12/19/2022
FiledStatusContractorScope
12/19/2022CompleteBERGER QUALITY ELEC'L CON2 meters
10/02/2022CompleteBERGER QUALITY ELEC'L CON—
1 project · most recent 12/31/2023
FiledStatusContractorScope
12/31/2023Permit IssuedGLENNS PLUMBING SVCS INC1 scope_items
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
05/06/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/02/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/29/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/01/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/26/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/13/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/12/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/22/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
02/22/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/22/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
10/14/2023Structural Stability – Alterations of existing buildingsJOHANN VELEZspecial
10/14/2023Fire-Resistant Penetrations and JointsJOHANN VELEZspecial
10/14/2023MasonryJOHANN VELEZspecial
10/14/2023FinalJOHANN VELEZprogress
10/14/2023Footing and FoundationJOHANN VELEZprogress
10/14/2023Energy Code Compliance InspectionsJOHANN VELEZprogress
10/14/2023Fire-Resistance Rated ConstructionJOHANN VELEZprogress
10/14/2023Interior lighting powerJOHANN VELEZenergy_progress
▾Documents — 71 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/26/2026B00948166-I1Request digital key ↗
08/26/2026B00948166-S1Request digital key ↗
▸Applications & Permits6
▸BISPLAN / WORK APPROVAL APPLICATION4
01/16/2024340863934Open ↗
08/15/2022340863934Open ↗
06/08/2022340856737Open ↗
Showing 3 of 4 on file for this type
▸BISWORK PERMIT APPLICATION2
09/21/2022340863934Open ↗
08/22/2022340863934Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWRestrictive Declaration/Easement 12
08/13/2026B00948166-I1Open ↗
08/13/2026B00948166-S1Open ↗
▸Seals & Professional Certifications13
▸DOB NOWProgress Inspector Seal & Signature5
09/05/2026B00948166-I1Open ↗
09/05/2026B00948166-I1Open ↗
09/05/2026B00948166-I1Open ↗
Showing 3 of 5 on file for this type
▸BISAPPLICANT OWNER SIGNATURE3
08/15/2022340863934Open ↗
06/08/2022340856737Open ↗
05/02/2022340842949Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
09/05/2026B00948166-I1Open ↗
09/05/2026B00948166-I1Open ↗
09/05/2026B00948166-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/26/2026B00948166-I1Open ↗
08/26/2026B00948166-S1Open ↗
▸Safety & Tenant Protection3
▸BISTPP1: TENANT PROTECTION PLAN3
08/15/2022340863934Open ↗
06/08/2022340856737Open ↗
05/02/2022340842949Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
08/15/2022340863934Open ↗
06/08/2022340856737Open ↗
05/02/2022340842949Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/26/2026B00948166-S1Open ↗
08/26/2026B00948166-I1Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY7
02/26/2025340863934Open ↗
08/15/2022340863934Open ↗
08/15/2022340863934Open ↗
Showing 3 of 7 on file for this type
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)3
08/15/2022340863934Open ↗
06/08/2022340856737Open ↗
05/02/2022340842949Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
02/26/2025340863934Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/26/2025340863934Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: RESPONSIBILITY11
02/26/2025340863934Open ↗
02/26/2025340863934Open ↗
08/15/2022340863934Open ↗
Showing 3 of 11 on file for this type
▸Approvals, Objections & Sign-offs1
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
02/27/2025340863934Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT4
02/26/2025340863934Open ↗
08/15/2022340863934Open ↗
06/08/2022340856737Open ↗
Showing 3 of 4 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
05/02/2022340842949Open ↗
▸Filing & Intake Forms7
▸BISADDITIONAL INFORMATION4
11/20/2024340863934Open ↗
09/19/2022340856737Open ↗
09/13/2022340856737Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
08/15/2022340863934Open ↗
06/08/2022340856737Open ↗
05/02/2022340842949Open ↗
▸Other Documents4
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION3
08/15/2022340863934Open ↗
06/08/2022340856737Open ↗
05/02/2022340842949Open ↗
▸BISTax Abatement Miscellaneous1
02/27/2025340863934Open ↗