Locations of Work
ArchitectureElectrical
Roof2p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC109/20/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272109/20/2024
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
12/18/2025
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01107673-I1
09/30/2024
Permit issued — Solar
S01107673-I1-SL
09/20/2024
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01107673-I1
09/06/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
09/06/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
09/06/2024
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
09/06/2024
Special inspection requirement — Final
Walid Abdulla
09/06/2024
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC09/30/2024
1 project · most recent 09/20/2024
General Wiring
FiledStatusContractorScope
09/20/2024CompleteSUNRUN SOLAR ELECTL CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
09/06/2024Fire-Resistant Penetrations and JointsWalid Abdullaspecial
09/06/2024Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
09/06/2024Energy Code Compliance InspectionsWalid Abdullaprogress
09/06/2024FinalWalid Abdullaprogress
09/06/2024Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 19 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026S01107673-I1Request digital key ↗
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
10/07/2025520369903Open ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature3
08/29/2026S01107673-I1Open ↗
08/29/2026S01107673-I1Open ↗
08/29/2026S01107673-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/29/2026S01107673-I1Open ↗
08/29/2026S01107673-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
01/16/2019520369903Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
01/16/2019520369903Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01107673-I1Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
01/16/2019520369903Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
01/16/2019520369903Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
01/16/2019520369903Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01107673-I1Open ↗
▸Approvals, Objections & Sign-offs3
▸BISSCHEDULE A - OCCUPANCY / USE1
01/16/2019520369903Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
01/16/2019520369903Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01107673-I1Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
01/16/2019520369903Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1