| Owner | Filings | Most Recent |
|---|---|---|
| WENQING PROPERTY | 14 | 04/09/2026 |
| JABBIE INDUSTRIES INCORP* | 4 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/16/2021 | $1.3M | — | — → — | $440/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BRIAN ILL DEVELOPMENT LLC | 3 | 10/03/2025 |
| BASIC GROUPS CORP | 4 | 08/26/2021 |
| KL INNOVATIVE DESIGN INC | 3 | 05/06/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| BASIC GROUPS | 8 | 03/21/2026 |
| AMERILAND BROOK LLC | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JABBIE INDUSTRIES INCORP* | General Contractor | 5 | 04/09/2026 |
| CUBE BUILDERS GROUP NY | General Contractor | 3 | 03/21/2026 |
| PIPESTYLISTS, INC | Plumbing | 2 | 07/08/2026 |
| FLINT MECHANICAL CORP | Fire Protection | 1 | 06/28/2026 |
| AMC PLBG, HTG & CLNG, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AMERILAND BROOK LLC | 1506 | 3 | 10/03/2025 |
| BRIAN ILL DEVELOPMENT LLC | 1402 | 3 | 10/03/2025 |
| KL INNOVATIVE DESIGN INC | 7225 | 4 | 08/26/2021 |
| NY ACOM ENGINEERING PLLC | 7061 | 3 | 08/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | JABBIE INDUSTRIES INCORP* | 01/30/2026 |
| DOB NOW | Sprinklers | Permit Issued | BLETSAS P&H CORP | 08/20/2025 |
| DOB NOW | Plumbing | Permit Issued | AMC PLBG, HTG & CLNG, INC | 08/07/2025 |
| DOB NOW | Foundation | Permit Issued | JABBIE INDUSTRIES INCORP* | 06/18/2025 |
| DOB NOW | Earth Work | Permit Issued | JABBIE INDUSTRIES INCORP* | 02/11/2025 |
| DOB NOW | General Construction | Signed-off | CUBE BUILDERS GROUP NY | 05/11/2021 |
| DOB NOW | Plumbing | Signed-off | T & T PLUMBING INC | 05/06/2021 |
| DOB NOW | Boiler Equipment | Signed-off | T & T PLUMBING INC | 05/06/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/03/2025 | Permit Issued | BLETSAS P&H CORP | 44 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/03/2025 | Permit Issued | AMC PLBG, HTG & CLNG, INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/09/2025 | Permit Issued | KWONG MING ELECTRIC INC | General Wiring |
| 04/15/2022 | Complete | KWONG MING ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/12/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/03/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 12/03/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/29/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/02/2021 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/02/2021 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 09/02/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/02/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/08/2025 | Sprinkler Systems | XIAOHONG ZHAO | special |
| 10/08/2025 | Energy Code Compliance Inspections | BRIAN ILL | progress |
| 10/08/2025 | Tenant Protection Plan Compliance | — | special |
| 10/08/2025 | Fire-Resistant Penetrations and Joints | BRIAN ILL | special |
| 10/08/2025 | Maintenance information | BRIAN ILL | energy_progress |
| 10/08/2025 | HVAC-R and service water heating system controls | BRIAN ILL | energy_progress |
| 10/08/2025 | HVAC-R and service water piping design and insulation | BRIAN ILL | energy_progress |
| 10/08/2025 | HVAC-R and service water heating equipment | BRIAN ILL | energy_progress |
| 10/02/2025 | Fire-Resistant Penetrations and Joints | BRIAN ILL | special |
| 10/02/2025 | Sprinkler Systems | XIAOHONG ZHAO | special |
| 10/02/2025 | Tenant Protection Plan Compliance | — | special |
| 10/02/2025 | Energy Code Compliance Inspections | BRIAN ILL | progress |
| 10/02/2025 | Maintenance information | BRIAN ILL | energy_progress |
| 10/02/2025 | HVAC-R and service water heating equipment | BRIAN ILL | energy_progress |
| 10/02/2025 | HVAC-R and service water heating system controls | BRIAN ILL | energy_progress |
| 10/02/2025 | HVAC-R and service water piping design and insulation | BRIAN ILL | energy_progress |
| 07/12/2022 | Fenestration areas | BRIAN ILL | energy_progress |
| 07/12/2022 | Ventilation and air distribution system | BRIAN ILL | energy_progress |
| 07/12/2022 | Insulation placement and R values | BRIAN ILL | energy_progress |
| 07/12/2022 | Concrete - Cast-In-Place | BRIAN ILL | special |
| 07/12/2022 | Excavations - Sheeting, Shoring, and Bracing | XIAOHONG ZHAO | special |
| 07/12/2022 | Fire-Resistant Penetrations and Joints | BRIAN ILL | special |
| 07/12/2022 | Masonry | BRIAN ILL | special |
| 07/12/2022 | Structural Steel - Details | BRIAN ILL | special |
| 07/12/2022 | Structural Steel - High Strength Bolting | XIAOHONG ZHAO | special |