← Back
BuildNYC
Two stories - detached, small or mid-size
732 EAST 216TH STREET
BRONX · BIN 2057904
💬 Discuss this project
1910Year Built
2.5Stories
A1Building Class
R7AZoning
1,500 sfGross Floor Area
1Units
2 Active Violations ▸
Two stories - detached, small or mid-size · 3,300 sf lot · 0.45 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofUnder Construction75p · 1 filing · 20 docs
PenthouseUnder Construction79p · 1 filing · 20 docs
Floor 4Under Construction72p · 1 filing · 20 docs
Floor 3Under Construction85p · 1 filing · 20 docs
Floor 2Under Construction80p · 1 filing · 20 docs
Floor 1Under Construction81p · 1 filing · 20 docs
CellarUnder Construction71p · 1 filing · 20 docs
Site & exteriorUnder Construction98p · 2 filings · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/03/2024$700K—Private party → Private party$467/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Badaly Architects906/23/2026
Badaly Engineering302/24/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Badaly Architects303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Kiri ConstructionGeneral Contractor407/08/2026
Kiri ConstructionScaffold407/08/2026
Infiniti Esc PlumbingPlumbing109/23/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Badaly Architect7137602/24/2026
Building Lifecycle
All (103)Filed (12)Permit Issued (8)Signed Off (1)Violation (3)Objection (46)Special Inspection (30)Tax Incentive (3)
10/01/2026
485-x construction completed
09/22/2026
Permit issued — Plumbing
X01130512-S3-PL
08/11/2026
Violation issued (ECB, open)
Construction
08/11/2026
Violation issued (ECB, open)
Construction
07/07/2026
Special inspection requirement — Interior lighting power
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Maintenance information
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Air barrier - visual inspection
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Metering
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Insulation placement and R values
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Footing and Foundation
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Fenestration areas
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Fenestration air leakage
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Lighting in dwelling units
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Exterior lighting power
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Energy Code Compliance Inspections
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Structural Steel - High Strength Bolting
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Subgrade Inspections
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Structural Steel - Welding
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Fire-Resistance Rated Construction
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Electrical motors and elevators
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Lighting controls
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Concrete - Cast-In-Place
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Air barrier — testing
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Structural Cold-Formed Steel
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Structural Steel - Details
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Final
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
SOORJBALLY HARILALL
07/07/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MOHAMMAD BADALY
07/07/2026
Special inspection requirement — Masonry
MOHAMMAD BADALY
06/25/2026
485-x registration filed
06/24/2026
Special inspection requirement — HVAC-R and service water heating system controls
06/23/2026
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-P5
06/23/2026
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-P4
06/23/2026
Objection resolved — Resolved
06/01/2026
Permit issued — General Construction
X01130512-I1-GC-CX
05/29/2026
Permit issued — Construction Fence
X01130512-S4-FN
04/23/2026
485-x construction commenced
02/26/2026
Objection raised — Other
02/24/2026
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-P2
02/24/2026
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-P3
01/16/2026
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-P1
12/11/2025
Permit issued — Support of Excavation
X01130512-S1-SE
10/03/2025
Permit issued — Foundation
X01130512-I1-GC-CX
09/18/2025
Permit issued — Construction Fence
X01130512-S4-FN
08/13/2025
Objection resolved — Addressed
08/12/2025
Objection raised — Other
07/30/2025
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-S1
07/28/2025
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-S4
05/28/2025
Objection resolved — Addressed
05/15/2025
Objection resolved — Addressed
05/15/2025
Objection resolved — Addressed
04/28/2025
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-S3
04/28/2025
Filed — New Building
Provide new sprinkler and plumbing system in conjunction with NB X01130512
X01130512-S2
04/23/2025
Objection resolved — Addressed
04/16/2025
Objection resolved — Addressed
04/16/2025
Objection resolved — Addressed
Latest 60 of 103 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedInfiniti Esc Plumbing09/22/2026
DOB NOWGeneral ConstructionPermit IssuedKiri Construction06/01/2026
DOB NOWConstruction FencePermit IssuedKiri Construction05/29/2026
DOB NOWSupport of ExcavationPermit IssuedKiri Construction12/11/2025
DOB NOWFoundationPermit IssuedKiri Construction10/03/2025
DOB NOWConstruction FencePermit IssuedKiri Construction09/18/2025
DOB NOWConstruction FenceSigned-offKiri Construction12/17/2024
DOB NOWFull DemolitionSigned-offKiri Construction12/17/2024
1 project · most recent 06/23/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScope
06/23/2026Permit IssuedKiri ConstructionHeating and Air Conditioning Systems, Ventilation Systems
1 project · most recent 06/23/2026
Sprinkler System
FiledStatusContractorScope
06/23/2026——Sprinkler System
1 project · most recent 06/23/2026
Storm Water/Sanitary
FiledStatusContractorScope
06/23/2026Permit IssuedInfiniti Esc PlumbingStorm, Water/Sanitary
1 project · most recent 06/23/2026
Steel Concrete Masonry
FiledStatusContractorScope
06/23/2026Permit IssuedInfiniti Esc PlumbingSteel, Concrete, Masonry
2 projects · most recent 06/23/2026
Fence
FiledStatusContractorScope
06/23/2026Permit IssuedInfiniti Esc PlumbingFence
10/17/2024Signed-offKiri ConstructionFence
▾Special Inspection Requirements (DOB NOW) — 106
DateRequirementInspectorRole
07/07/2026Fenestration and door U-factor and product ratingsMOHAMMAD BADALYenergy_progress
07/07/2026Fire-Resistance Rated ConstructionMOHAMMAD BADALYprogress
07/07/2026Concrete - Cast-In-PlaceMOHAMMAD BADALYspecial
07/07/2026Structural Cold-Formed SteelMOHAMMAD BADALYspecial
07/07/2026Structural Steel - WeldingMOHAMMAD BADALYspecial
07/07/2026Structural Steel - High Strength BoltingMOHAMMAD BADALYspecial
07/07/2026Exterior Insulation and Finish Systems (EIFS)MOHAMMAD BADALYspecial
07/07/2026Subgrade InspectionsMOHAMMAD BADALYspecial
07/07/2026MasonryMOHAMMAD BADALYspecial
07/07/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationMOHAMMAD BADALYspecial
07/07/2026Fire-Resistant Penetrations and JointsMOHAMMAD BADALYspecial
07/07/2026Structural Steel - DetailsMOHAMMAD BADALYspecial
07/07/2026Excavations - Sheeting, Shoring, and BracingMOHAMMAD BADALYspecial
07/07/2026Subsurface Investigations (Borings/Test Pits)SOORJBALLY HARILALLspecial
07/07/2026Maintenance informationMOHAMMAD BADALYenergy_progress
07/07/2026Insulation placement and R valuesMOHAMMAD BADALYenergy_progress
07/07/2026Interior lighting powerMOHAMMAD BADALYenergy_progress
07/07/2026MeteringMOHAMMAD BADALYenergy_progress
07/07/2026Exterior lighting powerMOHAMMAD BADALYenergy_progress
07/07/2026Lighting in dwelling unitsMOHAMMAD BADALYenergy_progress
07/07/2026Air barrier — testing MOHAMMAD BADALYenergy_progress
07/07/2026Air barrier - visual inspectionMOHAMMAD BADALYenergy_progress
07/07/2026Fenestration air leakageMOHAMMAD BADALYenergy_progress
07/07/2026Lighting controlsMOHAMMAD BADALYenergy_progress
07/07/2026Electrical motors and elevatorsMOHAMMAD BADALYenergy_progress
Latest 25 of 106.
▾Documents — 85 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/20/2026X01128538-S1Request digital key ↗
08/20/2026X01128538-I1Request digital key ↗
08/17/2026X01130512-P1Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
09/08/2025240361853Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram3
08/15/2026X01130512-I1Open ↗
08/13/2026X01130512-P3Open ↗
08/13/2026X01130512-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026X01130512-I1Open ↗
08/13/2026X01130512-P3Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026X01130512-P3Open ↗
08/13/2026X01130512-I1Open ↗
▸Seals & Professional Certifications31
▸DOB NOWSpecial Inspector Seal & Signature13
10/03/2026X01130512-I1Open ↗
10/03/2026X01130512-I1Open ↗
10/03/2026X01130512-I1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature12
08/20/2026X01128538-S1Open ↗
08/20/2026X01128538-I1Open ↗
08/17/2026X01130512-P2Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
10/03/2026X01130512-I1Open ↗
10/03/2026X01130512-I1Open ↗
08/22/2026X01130512-P3Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
09/08/2025240361853Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/08/2025240361853Open ↗
▸Trade Schedules & Equipment6
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/13/2026X01130512-P3Open ↗
08/13/2026X01130512-I1Open ↗
▸DOB NOWGas Cut-Off1
08/13/2026X01128538-I1Open ↗
▸DOB NOWWater Cut-Off1
08/13/2026X01128538-I1Open ↗
▸DOB NOWElectric Cut-Off1
08/13/2026X01128538-I1Open ↗
▸DOB NOWSewer Cut-Off1
08/13/2026X01128538-I1Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/15/2026X01130512-I1Open ↗
08/14/2026X01130512-P3Open ↗
▸BISBPP: STREET TREES SITE PLAN1
09/08/2025240361853Open ↗
▸BISSTREET TREE CHECKLIST1
09/08/2025240361853Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X01130512-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/20/2026X01128538-I1Open ↗
▸DOB NOWRodent Control1
08/13/2026X01128538-I1Open ↗
▸Inspections & Test Reports7
▸DOB NOWSOIL REPORT5
08/13/2026X01130512-P3Open ↗
08/13/2026X01130512-S1Open ↗
08/13/2026X01130512-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram2
08/13/2026X01130512-I1Open ↗
08/13/2026X01130512-S1Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
09/08/2025240361853Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
09/08/2025240361853Open ↗
▸Other Documents12
▸DOB NOWProperty Ownership Certification3
08/20/2026X01128538-I1Open ↗
08/15/2026X01130512-I1Open ↗
08/14/2026X01130512-P3Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026X01130512-P3Open ↗
08/13/2026X01130512-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026X01130512-P3Open ↗
08/13/2026X01130512-I1Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
09/08/2025240361853Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/13/2026X01128538-I1Open ↗
▸DOB NOWStructure Photographs1
08/13/2026X01128538-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026X01130512-S1Open ↗
▸DOB NOWCommunity Board Notification1
08/13/2026X01128538-I1Open ↗