| Owner | Filings | Most Recent |
|---|---|---|
| 1415 Wythe Housing Development Fund | 56 | 07/08/2026 |
| Neighborhood Renewal HDFC | 13 | 07/08/2026 |
| Tzur 187 St | 5 | 03/21/2026 |
| N Atzur 187 Street | 2 | 03/21/2026 |
| 1415 Wythe HDFC | 2 | 03/21/2026 |
| Four Suns Fuel Oil | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Inglese Architecture and Engineering | 16 | 01/14/2026 |
| Curtis + Ginsberg Architects | 9 | 07/08/2025 |
| Old Structures Engineering | 6 | 06/05/2024 |
| Joel Phagoo P.E | 5 | 06/05/2024 |
| Bernard Ocasio Architect | 2 | 01/05/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| William Vitacco Associates | 31 | 03/21/2026 |
| A1 Expediting Service | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Notias Construction | General Contractor | 21 | 07/08/2026 |
| Akm Construction NY | Scaffold | 6 | 07/08/2026 |
| American Standard P&H Cororp | Plumbing | 4 | 07/08/2026 |
| Notias Construction | Scaffold | 4 | 07/08/2026 |
| Queue Electrical Contractors | Electrical | 3 | 03/21/2026 |
| J-J Plumbing | Plumbing | 2 | 07/08/2026 |
| Shally Electrical Co | Electrical | 2 | 03/21/2026 |
| Alson Electrical Contracting | Electrical | 1 | 03/21/2026 |
| Syed-Naqvi Altaf | Electrical | 1 | 03/21/2026 |
| Queue Electrical Contractors | Electrical | 1 | 03/22/2026 |
| G. Poulakis Electrical Contracting | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Concrete Solutions Lab Co | 5344 | 25 | 07/09/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | Notias Construction | 04/17/2025 |
| DOB NOW | General Construction | Signed-off | Notias Construction | 04/16/2025 |
| DOB NOW | Structural | Signed-off | Notias Construction | 04/16/2025 |
| DOB NOW | General Construction | Signed-off | Notias Construction | 04/16/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Notias Construction | 04/16/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Notias Construction | 04/02/2025 |
| DOB NOW | Plumbing | Signed-off | American Standard P&H Cororp | 01/09/2025 |
| DOB NOW | Boiler Equipment | Signed-off | American Standard P&H Cororp | 05/01/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Notias Construction | 01/08/2024 |
| DOB NOW | Structural | Signed-off | Notias Construction | 01/08/2024 |
| DOB NOW | Structural | Signed-off | Notias Construction | 01/08/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Notias Construction | 01/08/2024 |
| DOB NOW | General Construction | Signed-off | Notias Construction | 01/08/2024 |
| DOB NOW | General Construction | Signed-off | Notias Construction | 01/08/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Akm Construction NY | 12/15/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | Notias Construction | 11/16/2023 |
| DOB NOW | Structural | Signed-off | Notias Construction | 11/15/2023 |
| DOB NOW | Supported Scaffold | Signed-off | Akm Construction NY | 11/02/2023 |
| DOB NOW | General Construction | Signed-off | Notias Construction | 10/16/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Notias Construction | 10/16/2023 |
| DOB NOW | Structural | Signed-off | Notias Construction | 10/16/2023 |
| DOB NOW | Plumbing | Signed-off | American Standard P&H Cororp | 09/25/2023 |
| DOB NOW | General Construction | Signed-off | Notias Construction | 09/14/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | Akm Construction NY | 08/22/2023 |
| DOB NOW | Boiler Equipment | Signed-off | J-J Plumbing | 05/22/2023 |
| DOB NOW | Structural | Signed-off | Notias Construction | 09/29/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | Akm Construction NY | 08/24/2022 |
| DOB NOW | Boiler Equipment | Signed-off | J-J Plumbing | 06/21/2022 |
| BIS | OT | ISSUED | Blue Square Construction | 02/11/2019 |
| BIS | EQ | ISSUED | Blue Square Construction | 04/07/2017 |
| BIS | FB | ISSUED | Court Oil Heating | 08/22/1994 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/14/2026 | Signed-off | American Standard P&H | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/05/2025 | Permit Issued | Queue Electrical Contractors | General Wiring |
| 12/05/2024 | Complete | Queue Electrical Contractors | General Wiring |
| 10/08/2024 | Permit Issued | G. Poulakis Electrical Contracting | Boiler Controls |
| 12/12/2023 | Complete | Queue Electrical Contractors | — |
| 08/01/2022 | Complete | High Quality Electric of | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/30/2024 | Permit Issued | Akm Construction NY | Sidewalk Shed |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/18/2025 | Lighting in dwelling units | MINA HANNA | energy_progress |
| 07/18/2025 | Fire-Resistance Rated Construction | MINA HANNA | progress |
| 07/18/2025 | Final | Mark Ginsberg | progress |
| 07/18/2025 | Fire-Resistant Penetrations and Joints | MINA HANNA | special |
| 07/18/2025 | Final | MINA HANNA | progress |
| 07/18/2025 | Mechanical Systems | MINA HANNA | special |
| 07/18/2025 | Lighting controls | MINA HANNA | energy_progress |
| 07/18/2025 | Insulation placement and R values | MINA HANNA | energy_progress |
| 07/18/2025 | Interior lighting power | MINA HANNA | energy_progress |
| 07/18/2025 | Air barrier - visual inspection | MINA HANNA | energy_progress |
| 07/18/2025 | Exterior lighting power | MINA HANNA | energy_progress |
| 05/19/2025 | Fire-Resistance Rated Construction | MINA HANNA | progress |
| 05/19/2025 | Final | Mark Ginsberg | progress |
| 05/19/2025 | Fire-Resistant Penetrations and Joints | MINA HANNA | special |
| 05/19/2025 | Interior lighting power | MINA HANNA | energy_progress |
| 05/19/2025 | Exterior lighting power | MINA HANNA | energy_progress |
| 05/19/2025 | Mechanical Systems | MINA HANNA | special |
| 05/19/2025 | Final | MINA HANNA | progress |
| 05/19/2025 | Lighting controls | MINA HANNA | energy_progress |
| 05/19/2025 | Lighting in dwelling units | MINA HANNA | energy_progress |
| 05/19/2025 | Air barrier - visual inspection | MINA HANNA | energy_progress |
| 05/19/2025 | Insulation placement and R values | MINA HANNA | energy_progress |
| 10/08/2024 | Heating Systems | MINA HANNA | special |
| 10/08/2024 | HVAC-R and service water heating system controls | MINA HANNA | energy_progress |
| 10/08/2024 | HVAC-R and service water piping design and insulation | MINA HANNA | energy_progress |