← Back
Two family brick
737 EAST 88 STREET
BROOKLYN · Canarsie · BIN 3224623
💬 Discuss this project
1925Year Built
2Stories
B1Building Class
R4-1Zoning
3,360 sfGross Floor Area
2Units
5 Open Violations ▸FDNY Report ↗
Two family brick · 2,375 sf lot · 1.41 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JBA112/19/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
WILLIAM JAMES BUSHELL CORGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DOYUN KIM; RA7415112/19/2023
Building Lifecycle
All (12)Filed (1)Permit Issued (1)Violation (5)Special Inspection (5)
12/21/2023
Permit issued — Solar
B00974728-I1-SL
12/19/2023
Filed — Alteration
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF. NO CHANGE INUSE, OCCUPANCY OR EGRESS. NOCHANGE IN BULK
B00974728-I1
12/09/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
DOYUN KIM
12/09/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
DOYUN KIM
12/09/2023
Special inspection requirement — Energy Code Compliance Inspections
DOYUN KIM
12/09/2023
Special inspection requirement — Final
JEFFREY BELL
12/09/2023
Special inspection requirement — Air barrier - visual inspection
DOYUN KIM
01/07/2011
Violation issued (HPD, open)
C
06/16/2010
Violation issued (HPD, open)
C
06/16/2010
Violation issued (HPD, open)
C
06/16/2010
Violation issued (HPD, open)
C
06/16/2010
Violation issued (HPD, open)
C
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offWILLIAM JAMES BUSHELL COR12/21/2023
1 project · most recent 12/18/2023
FiledStatusContractorScope
12/18/2023CompleteD.R.P. ELEC'L CONTRG INC1 meters
1 project · most recent 12/19/2023
FiledStatusContractorScope
12/19/2023Signed-offWILLIAM JAMES BUSHELL COR6 panels, 3.3 kw, 1,133 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
12/09/2023Fire-Resistant Penetrations and JointsDOYUN KIMspecial
12/09/2023Structural Stability – Alterations of existing buildingsDOYUN KIMspecial
12/09/2023Energy Code Compliance InspectionsDOYUN KIMprogress
12/09/2023FinalJEFFREY BELLprogress
12/09/2023Air barrier - visual inspectionDOYUN KIMenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/26/2026B00974728-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026B00974728-I1Open ↗
08/28/2026B00974728-I1Open ↗
08/28/2026B00974728-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/28/2026B00974728-I1Open ↗
08/28/2026B00974728-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/26/2026B00974728-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/26/2026B00974728-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B00974728-I1Open ↗