| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/28/2026 | Signed-off | HIL GROUP LLC | Heating and Air Conditioning Systems, Heating Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Permit Issued | PLBG P & H INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/28/2026 | Permit Issued | BRUCHE MECHANICAL NY LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/18/2026 | Complete | HIVOLTS ELECTRICAL INC | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| 739 PENNSYLVANIA AVE LLC | 1 | 03/22/2026 |
| HILL GROUP LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/17/2025 | $1.1M | — | — → — | $222/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NY BUILDING ASSOCIATES INC | 3 | 07/28/2026 |
| VASILIOS ARTEMIOU PE | 4 | 03/10/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HIL GROUP LLC | General Contractor | 3 | 04/09/2026 |
| BRUCHE MECHANICAL NY LLC | Fire Protection | 1 | 07/08/2026 |
| PLBG P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RI CONSULTING SERVICES IN | 8904 | 4 | 03/10/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | HIL GROUP | 01/22/2026 |
| DOB NOW | General Construction | Permit Issued | HIL GROUP | 01/20/2026 |
| DOB NOW | Plumbing | Permit Issued | PLBG P & H INC | 12/05/2025 |
| DOB NOW | Plumbing | Permit Issued | BRUCHE MECHANICAL NY LLC | 12/05/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/14/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/08/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/03/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/08/2026 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 03/20/2026 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 02/25/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/04/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/18/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 12/16/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/16/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/16/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/05/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 11/04/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 08/05/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/06/2026 | Energy Code Compliance Inspections | Md Istiaque Hasan | progress |
| 08/06/2026 | Insulation placement and R values | Md Istiaque Hasan | energy_progress |
| 08/06/2026 | Maintenance information | Md Istiaque Hasan | energy_progress |
| 08/06/2026 | Permanent certificate | Md Istiaque Hasan | energy_progress |
| 08/06/2026 | Air barrier - visual inspection | Md Istiaque Hasan | energy_progress |
| 08/06/2026 | Interior lighting power | Md Istiaque Hasan | energy_progress |
| 08/06/2026 | Metering | Md Istiaque Hasan | energy_progress |
| 08/06/2026 | Fire-Resistance Rated Construction | Md Istiaque Hasan | progress |
| 07/28/2026 | Permanent certificate | Md Istiaque Hasan | energy_progress |
| 07/28/2026 | Energy Code Compliance Inspections | Md Istiaque Hasan | progress |
| 07/28/2026 | Fire-Resistance Rated Construction | Md Istiaque Hasan | progress |
| 07/28/2026 | Metering | Md Istiaque Hasan | energy_progress |
| 07/28/2026 | Maintenance information | Md Istiaque Hasan | energy_progress |
| 07/28/2026 | Interior lighting power | Md Istiaque Hasan | energy_progress |
| 07/28/2026 | Air barrier - visual inspection | Md Istiaque Hasan | energy_progress |
| 07/28/2026 | Insulation placement and R values | Md Istiaque Hasan | energy_progress |
| 04/23/2026 | Maintenance information | Md Istiaque Hasan | energy_progress |
| 04/23/2026 | HVAC-R and service water piping design and insulation | Md Istiaque Hasan | energy_progress |
| 04/23/2026 | HVAC-R and service water heating system controls | Md Istiaque Hasan | energy_progress |
| 04/23/2026 | Duct leakage testing, insulation and design | Md Istiaque Hasan | energy_progress |
| 04/23/2026 | Permanent certificate | Md Istiaque Hasan | energy_progress |
| 04/23/2026 | Mechanical Systems | Md Istiaque Hasan | special |
| 04/23/2026 | Post-installed Anchors | Md Istiaque Hasan | special |
| 04/23/2026 | Fire-Resistant Penetrations and Joints | Md Istiaque Hasan | special |
| 04/23/2026 | Final | Md Istiaque Hasan | progress |