| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/11/2018 | $475K | — | — → — | $132/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ANTHONY SOMEFUN | 6 | 11/12/2024 |
| COLOMBO ARCHITECTURAL STUDIO PC | 4 | 08/08/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| PCA DESIGN CONSULTANTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KODRA CONSTRUCTION CORP | General Contractor | 3 | 07/08/2026 |
| WEBB DEVELOPMENT SVC CORP | General Contractor | 3 | 07/28/2026 |
| JUNIOR CARTER MECH. CORP | Plumbing | 3 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BADALY ARCHITECT PLLC | 7137 | 1 | 02/16/2023 |
| COLOMBO ARCHITECTURAL STU | 4930 | 4 | 08/08/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | WEBB DEVELOPMENT SVC CORP | 07/27/2026 |
| DOB NOW | Construction Fence | Permit Issued | WEBB DEVELOPMENT SVC CORP | 04/27/2026 |
| DOB NOW | Construction Fence | Permit Issued | WEBB DEVELOPMENT SVC CORP | 09/25/2025 |
| DOB NOW | Full Demolition | Signed-off | KODRA CONSTRUCTION CORP | 01/30/2025 |
| DOB NOW | Construction Fence | Permit Issued | KODRA CONSTRUCTION CORP | 01/03/2025 |
| DOB NOW | Construction Fence | Permit Issued | KODRA CONSTRUCTION CORP | 11/25/2024 |
| DOB NOW | Plumbing | Signed-off | JUNIOR CARTER MECH. CORP | 07/06/2022 |
| DOB NOW | Plumbing | Signed-off | JUNIOR CARTER MECH. CORP | 12/23/2020 |
| DOB NOW | Plumbing | Signed-off | JUNIOR CARTER MECH. CORP | 09/10/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/08/2022 | Signed-off | JUNIOR CARTER MECH. CORP | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/12/2024 | Permit Issued | WEBB DEVELOPMENT SVC CORP | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2024 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 08/20/2024 | Air barrier - visual inspection | — | energy_progress |
| 08/20/2024 | Permanent certificate | — | energy_progress |
| 08/20/2024 | Insulation placement and R values | — | energy_progress |
| 08/20/2024 | Fenestration areas | — | energy_progress |
| 08/20/2024 | Fenestration air leakage | — | energy_progress |
| 08/20/2024 | Air barrier — testing | — | energy_progress |
| 08/08/2024 | Permanent certificate | — | energy_progress |
| 08/08/2024 | Duct leakage testing, insulation and design | — | energy_progress |
| 07/02/2024 | Ventilation and air distribution system | — | energy_progress |
| 12/11/2023 | Air barrier — testing | — | energy_progress |
| 11/29/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 11/29/2023 | Permanent certificate | — | energy_progress |
| 11/29/2023 | Fenestration areas | — | energy_progress |
| 11/29/2023 | Metering | — | energy_progress |
| 11/29/2023 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 11/29/2023 | Electric vehicle service equipment requirements | — | energy_progress |
| 11/29/2023 | Fenestration air leakage | — | energy_progress |
| 11/29/2023 | Maintenance information | — | energy_progress |
| 11/29/2023 | Air barrier - visual inspection | — | energy_progress |
| 11/29/2023 | Interior lighting power | — | energy_progress |
| 11/29/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 11/29/2023 | Masonry | — | special |
| 11/29/2023 | Post-installed Anchors | — | special |
| 11/29/2023 | Seismic Isolation Systems | — | special |