1948Year Built
2Stories
C6Building Class
R3-2Zoning
154,232 sfGross Floor Area
200Units
LL97 CoveredRent Stabilized6 Open Violations ▸
Walk-up cooperative · Owner of record: GLEN OAKS VILLAGE OWNERS INC · 417,750 sf lot · 0.37 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 21p · 1 filing · 18 docs
Floor 11p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ABDUS SALAM C. ENGINEERS307/03/2024
RAS PE CONSULTING ENGINEERS109/12/2022
EDWARD C. HICKS RA105/05/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ZONE PLUMBING HEATING C603/21/2026
KATARIA BUILDERS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ZONE PLUMBING & HEATING CPlumbing407/08/2026
MONTI UNITED CONSTRUCTIONGeneral Contractor203/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519407/03/2024
Building Lifecycle
All (24)Filed (5)Permit Issued (5)Signed Off (2)Objection (4)Special Inspection (8)
07/16/2024
Signed off — Alteration
INSTALLATION OF WASHER AND DRYER ON SECOND FLOOR
Q00435395-I1
07/03/2024
Filed — Alteration
INSTALLATION OF WASHER AND DRYER ON SECOND FLOOR
Q00435395-P3
07/03/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
04/05/2024
Filed — Alteration
INSTALLATION OF WASHER AND DRYER ON SECOND FLOOR
Q00435395-P2
03/29/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
12/18/2023
Permit issued — Plumbing
Q00435395-I1-PL
09/12/2022
Filed — Alteration
INSTALLATION OF WASHER AND DRYER ON SECOND FLOOR
Q00435395-P1
09/12/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
08/12/2022
Permit issued — Plumbing
Q00435395-I1-PL
11/16/2021
Signed off — Alteration
FILING HEREWITH PLANS AND APPLICATION FOR NEW ENTRY DOOR FOR THE SECOND FLOOR UNIT ON THE FIRST FLOOR MAIN ENTRANCE. NO CHANGE IN USE/EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00511672-I1
07/01/2021
Permit issued — Plumbing
Q00435395-I1-PL
05/22/2021
Permit issued — General Construction
Q00511672-I1-GC
05/12/2021
Objection raised — Scope
05/12/2021
Objection resolved — Addressed
05/12/2021
Objection raised — Scope
05/12/2021
Objection resolved — Addressed
05/05/2021
Filed — Alteration
FILING HEREWITH PLANS AND APPLICATION FOR NEW ENTRY DOOR FOR THE SECOND FLOOR UNIT ON THE FIRST FLOOR MAIN ENTRANCE. NO CHANGE IN USE/EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q00511672-I1
04/27/2021
Special inspection requirement — Energy Code Compliance Inspections
EDWARD HICKS
04/27/2021
Special inspection requirement — Fire-Resistance Rated Construction
EDWARD HICKS
04/27/2021
Special inspection requirement — Final
EDWARD HICKS
04/27/2021
Special inspection requirement — Fenestration areas
EDWARD HICKS
04/27/2021
Special inspection requirement — Air barrier - visual inspection
EDWARD HICKS
02/12/2021
Permit issued — Plumbing
Q00435395-I1-PL
12/16/2020
Filed — Alteration
INSTALLATION OF WASHER AND DRYER ON SECOND FLOOR
Q00435395-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offZONE PLUMBING & HEATING C12/18/2023
DOB NOWPlumbingSigned-offZONE PLUMBING & HEATING C08/12/2022
DOB NOWPlumbingSigned-offZONE PLUMBING & HEATING C07/01/2021
DOB NOWGeneral ConstructionSigned-offMONTI UNITED CONSTRUCTION05/22/2021
DOB NOWPlumbingSigned-offZONE PLUMBING & HEATING C02/12/2021
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
07/03/2024Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
03/29/2024Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
09/12/2022Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
04/27/2021Energy Code Compliance InspectionsEDWARD HICKSprogress
04/27/2021Fire-Resistance Rated ConstructionEDWARD HICKSprogress
04/27/2021FinalEDWARD HICKSprogress
04/27/2021Fenestration areasEDWARD HICKSenergy_progress
04/27/2021Air barrier - visual inspectionEDWARD HICKSenergy_progress
▾Documents — 24 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch - Plumbing4
08/25/2026Q00435395-P2Request digital key ↗
08/25/2026Q00435395-P1Request digital key ↗
08/25/2026Q00435395-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch1
08/14/2026Q00511672-I1Request digital key ↗
▸Seals & Professional Certifications13
▸DOB NOWProgress Inspector Seal & Signature5
08/25/2026Q00511672-I1Open ↗
08/25/2026Q00511672-I1Open ↗
08/25/2026Q00511672-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/27/2026Q00511672-I1Open ↗
08/25/2026Q00435395-P3Open ↗
08/25/2026Q00435395-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026Q00435395-I1Open ↗
08/31/2026Q00435395-P1Open ↗
08/22/2026Q00435395-P2Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/25/2026Q00435395-P2Open ↗
08/25/2026Q00435395-P1Open ↗
08/25/2026Q00435395-I1Open ↗
Showing 3 of 5 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00511672-I1Open ↗