Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Whole building & multi-floor projectsSprinkler system changes and installation1 filing
Sprinkler changes as per plans filed herewith (additional heads added to provide proper coverage to reach standards set by Local Law 26). No change in use, egress or occupancy.
On file for this project
8 documents
Roof1 filing · 2 docs
Structural
Issued Permit Scope
Structural
REPLACEMENT OF EXISTING SIGN (LIGHT BOXES) WITH NEW DIGITAL DISPLAYS
On file for this project
2 documents
Floor 34Morgan StanleyUnder Construction12p · 8 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing Sprinkler System: Relocate (1) head and install (1) new head on the 4th Floor; Relocate (3) heads and install (1) new on the 34th Floor as per plans (Morgan Stanley - ADA Restroom.) No change to use, egress or occupancy.
On file for this project
8 documents
Modifications to the existing HVAC System: Install new ductwork. Connect to existing toilet exhaust ductwork and installation of a new toilet exhaust fan inline with existing ductwork on the 4th & 34th Floors as per plans (Morgan Stanley ADA Restroom.)
On file for this project
12 documents
Install new plumbing fixtures: (1) FD, (1) WC, (1) lavatory and (1) Janitor Sink on the 4th Floor and (1) FD, (1) WC, (1) lavatory on the 34th Floor and associated CW/sanitary piping on both as per plans (Morgan Stanley - ADA/ Gender Neutral Restroom.)
On file for this project
7 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 33Morgan Stanley4p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove (1) head, (2) new heads and (13) relocated on 29; Remove (1) head, (2) new and (9) relocated on 31; Remove (4), (3) new and (11) relocated on 32; Rem(4) head , (2) new and (8) relocated on 33; Rem (1), (5) new and (9) relocated on 34 as per plans.
On file for this project
8 documents · 1 drawing sheet
Removal of one (1) Drinking Fountain and associated piping on 29, 31-34th Floors each; Install one (1) new drinking fountain and associated piping each on floors 29, 31-34 as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing HVAC System: Installation of new AC Unit and associated ductwork and piping on the 29, 31-34th Floors as per plans (Morgan Stanley - RISK Floors.) No change to use, egress or occupancy.
On file for this project
13 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 32Morgan Stanley3p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove (1) head, (2) new heads and (13) relocated on 29; Remove (1) head, (2) new and (9) relocated on 31; Remove (4), (3) new and (11) relocated on 32; Rem(4) head , (2) new and (8) relocated on 33; Rem (1), (5) new and (9) relocated on 34 as per plans.
On file for this project
8 documents · 2 drawing sheets
Removal of one (1) Drinking Fountain and associated piping on 29, 31-34th Floors each; Install one (1) new drinking fountain and associated piping each on floors 29, 31-34 as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents
Modifications to the existing HVAC System: Installation of new AC Unit and associated ductwork and piping on the 29, 31-34th Floors as per plans (Morgan Stanley - RISK Floors.) No change to use, egress or occupancy.
On file for this project
13 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 31Morgan Stanley2p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove (1) head, (2) new heads and (13) relocated on 29; Remove (1) head, (2) new and (9) relocated on 31; Remove (4), (3) new and (11) relocated on 32; Rem(4) head , (2) new and (8) relocated on 33; Rem (1), (5) new and (9) relocated on 34 as per plans.
On file for this project
8 documents · 2 drawing sheets
Removal of one (1) Drinking Fountain and associated piping on 29, 31-34th Floors each; Install one (1) new drinking fountain and associated piping each on floors 29, 31-34 as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents
Modifications to the existing HVAC System: Installation of new AC Unit and associated ductwork and piping on the 29, 31-34th Floors as per plans (Morgan Stanley - RISK Floors.) No change to use, egress or occupancy.
On file for this project
13 documents
Latest 3 of 4 filings on this floor.
Floor 30
Floor 29Morgan Stanley1p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove (1) head, (2) new heads and (13) relocated on 29; Remove (1) head, (2) new and (9) relocated on 31; Remove (4), (3) new and (11) relocated on 32; Rem(4) head , (2) new and (8) relocated on 33; Rem (1), (5) new and (9) relocated on 34 as per plans.
On file for this project
8 documents · 1 drawing sheet
Removal of one (1) Drinking Fountain and associated piping on 29, 31-34th Floors each; Install one (1) new drinking fountain and associated piping each on floors 29, 31-34 as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents
Modifications to the existing HVAC System: Installation of new AC Unit and associated ductwork and piping on the 29, 31-34th Floors as per plans (Morgan Stanley - RISK Floors.) No change to use, egress or occupancy.
On file for this project
13 documents
Latest 3 of 4 filings on this floor.
Floor 28Bath & Body Works, FosterLane8p · 9 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Install new plumbing fixtures: (3) sinks, (1) hot water heater, (1) funnel drain and associated CW/sanitary piping on the 28th Floor as per plans (Bath & Body Works.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing sprinkler system: Remove (21) existing sprinkler head and Install (18) new sprinkler heads and associated piping on the 28th Floor as per plans (Bath & Body Works.) No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 28th Floor as per plans (Bath & Body Works) No change to use, egress or occupancy.
On file for this project
5 documents
Latest 3 of 9 filings on this floor.
Floor 27FosterLane3p · 3 filings · 11 docs
Fire Protection
Issued Permit Scope
Sprinklers
General sprinkler changes on the 27th floor as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
General mechanical changes taking place on 27th floor including removal of ac unit and related ductwork. No change in use, egress or occupancy.
On file for this project
5 documents · 3 drawing sheets
Plumbing changes taking place on 27th floor including removal of fixtures. No change in use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Floor 26Shinhan Bank America, FosterLane7p · 8 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Install NEW: (1) sink, (2) drinking fountains, (1) DW, (1) chiller w/ ice, (2) FD, (2) HWHs and associated CW/san piping; REPLACE: (5) WCs, (5) lavs, (2) urinals and associated CW/sanitary piping on the 26th Flr as per plans (Shinhan Bank Renovations.)
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing Sprinkler System: Remove (10) existing sprinkler head and Install (109) new sprinkler heads and associated piping on the 26th Floor as per plans (Shinhan Bank.) No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 26th Floor as per plans (Shinhan Bank Renovations.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 25FosterLane3p · 4 filings · 16 docs
Fire ProtectionStructural
Issued Permit Scope
Sprinklers · Structural
Remove existing interior stairs, and install structural steel, new metal deck, concrete and infill stairs between the 25-26th Floors (CO)/ 26-27th Floors (Marketing) as per plans (Shinhan Bank - Renovations.) No change to use, egress or occupancy.
On file for this project
3 documents
General sprinkler changes taking place on the 25th and 26th floors as per plans filed herewith. No change in use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
General mechanical changes taking place on 25th and 26th floors including removal of ac unit and related ductwork. No change in use, egress or occupancy.
On file for this project
5 documents · 4 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 24
Floor 23
Floor 22
Floor 21
Floor 20Morgan Stanley16p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Install new plumbing fixtures: (2) hot water heaters, (2) sinks, (2) drinking fountains, (1) FD and associated Vent, Sanitary Piping and CW/HW drops and leak detectors as per plans. No change to use, egress or occupancy
On file for this project
7 documents · 3 drawing sheets
Modifications to the existing HVAC System; Remove existing units/ductwork, dampers and piping, Install new ductwork, acoustical units, HVAC units, diffusers, plenum box and grills as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
4 documents
Modifications to the existing Sprinkler System; Remove (101) existing sprinkler heads and associated piping, Install ninety-nine (99) new sprinkler heads and associated Sprinkler piping as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 19Morgan StanleyUnder Construction10p · 5 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalOther
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Additions/ Modification to existing Sprinkler system as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
7 documents · 1 drawing sheet
Interior renovation of existing office, includes new non load bearing partitions, finishes, lighting, electrical
On file for this project
9 documents · 7 drawing sheets
Addition and modifications to existing HVAC system and related ducts and piping. No change in use, egress or occupancy.
On file for this project
13 documents · 4 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 18Morgan StanleyUnder Construction12p · 6 filings · 20 docs
ArchitectureDMElectricalFire AlarmFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Plumbing modifications on the 18th floor -New instantaneous water heater new water closet, lavatory, and floor drain and piping modifications.
On file for this project
3 documents · 1 drawing sheet
Additions/ Modification to existing Sprinkler system as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
7 documents · 2 drawing sheets
Interior renovation of existing office, includes new non load bearing partitions, finishes, lighting, electrical
On file for this project
9 documents · 6 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 17Morgan Stanley3p · 4 filings · 12 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the Sprinkler System: Relocation of seventeen (17) sprinkler heads and associated piping on the 17th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing HVAC system as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
7 documents
Installation of new plumbing fixtures: (1) ice maker, (1) water filter, (1) floor drain and associated CW/sanitary piping on the 17th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 16Morgan Stanley11p · 8 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing HVAC System: Removal & cap if duct taps and diffusers; Rebalance VAV, relocate existing diffusers and VAV's on the 16th Floor as per plans (Morgan Stanley - Temp Clinic.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Minor interior demolition; Installation of new interior partitions, doors, flooring and finishes on the 16th Floor as per plans (Morgan Stanley Temp Clinic.) No change to use, egress or occupancy.
On file for this project
6 documents · 4 drawing sheets
Remove (1) existing drinking fountain and associated water/waste/vent piping and Install (1) new drinking fountain and new water/waste/vent piping on the 16th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 15Morgan Stanley10p · 4 filings · 12 docs
ArchitectureDMFire ProtectionGeneralMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Modifications to the existing HVAC System: Reconfiguration of HVAC ductwork on the 15th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents
Modifications to the existing Sprinkler System: Relocate (133) existing heads, Remove (7) existing sprinkler heads and install (6) new sprinkler heads and associated piping as per plans (Tenant Work - Morgan Stanley.) No change to use, egress or occupancy
On file for this project
5 documents · 1 drawing sheet
Minor interior demolition. Installation of new partitions, suspended ceilings, flooring and finishes as per plans (Tenant Work - Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
4 documents · 9 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 14Morgan Stanley8p · 4 filings · 12 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Removal of plumbing fixtures on the 9 & 14th Floors; Install (1) new drinking fountain on the 9th Floor and (1) HWH, (1) sink, (1) DF and associated CS/sanitary piping on the 14th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 9th & 14th Floors as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents · 5 drawing sheets
Modifications to the existing HVAC System: Removal of ductwork, Install new ductwork and rebalance VAV's and diffusers on the 9th & 14th Floors as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 13
Floor 12Morgan Stanley2p · 4 filings · 12 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove (1) drinking fountain & Install (1) new DF and associated piping on the 11th Floor; Remove (1) DF, Install (1) new DF, (1) sink and (1) hot water heater and associated CW/sanitary piping on the 12th Floor as per plans (Morgan Stanley.)
On file for this project
4 documents · 1 drawing sheet
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings flooring and finishes on the 11-12th Floors as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing HVAC System: Removal and relocation of existing ductwork, relocate and rebalance diffusers, rebalance VAV on the 11-12th Floors as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents
Latest 3 of 4 filings on this floor.
Floor 11Morgan Stanley2p · 4 filings · 17 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove (1) drinking fountain & Install (1) new DF and associated piping on the 11th Floor; Remove (1) DF, Install (1) new DF, (1) sink and (1) hot water heater and associated CW/sanitary piping on the 12th Floor as per plans (Morgan Stanley.)
On file for this project
4 documents · 1 drawing sheet
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings flooring and finishes on the 11-12th Floors as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents
Modifications to the existing HVAC System: Removal and relocation of existing ductwork, relocate and rebalance diffusers, rebalance VAV on the 11-12th Floors as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents
Latest 3 of 4 filings on this floor.
Floor 10Morgan Stanley4p · 5 filings · 12 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Remove: (4) FDs, (1) sink and (1) WD; Install NEW: (2) UR, (6) WC's, (6) Lav, (2) HWH, (4) FD's, (1) IM, (1) Chiller, (1) Sink, (1) DF, (1) sanitary system related sump pump & associated CW/sanitary piping on the 10th Floor as per plans (Morgan Stanley.)
On file for this project
6 documents · 2 drawing sheets
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 10th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modifications to the existing HVAC System: Installation of (4) Computer Room AC units and redistribution/install new ductwork and accessories on the 10th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents
Latest 3 of 5 filings on this floor.
Floor 9Morgan Stanley5p · 4 filings · 12 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Removal of plumbing fixtures on the 9 & 14th Floors; Install (1) new drinking fountain on the 9th Floor and (1) HWH, (1) sink, (1) DF and associated CS/sanitary piping on the 14th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 9th & 14th Floors as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents · 3 drawing sheets
Modifications to the existing HVAC System: Removal of ductwork, Install new ductwork and rebalance VAV's and diffusers on the 9th & 14th Floors as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents
Latest 3 of 4 filings on this floor.
Floor 8Morgan Stanley8p · 4 filings · 12 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Relocate (5) existing sprinkler heads and install (4) new sprinkler heads on the 7th Floor; Relocate (2) head and Install (1) new head and associated sprinkler piping on the 8th Floor per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Installation of (1) Drinking Fountain on the 7th and 8th Floors each and associated CW/sanitary piping as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing HVAC system: relocation/install new ductwork and VAV's and accessories as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 7Morgan Stanley7p · 4 filings · 12 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Relocate (5) existing sprinkler heads and install (4) new sprinkler heads on the 7th Floor; Relocate (2) head and Install (1) new head and associated sprinkler piping on the 8th Floor per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Installation of (1) Drinking Fountain on the 7th and 8th Floors each and associated CW/sanitary piping as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing HVAC system: relocation/install new ductwork and VAV's and accessories as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents
Latest 3 of 4 filings on this floor.
Floor 6Morgan Stanley9p · 3 filings · 12 docs
ArchitectureDMFire ProtectionMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
Modifications to the existing sprinkler system: Relocate (4) existing sprinkler heads and install (4) new heads and associated sprinkler piping on the 6th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
Modifications to the existing HVAC System: redistribution of ductwork for new layout on the 6th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents
Minor interior demolition. Installation of new interior partitions, doors, suspended ceilings, flooring and finishes on the 6th Floor as per plans (Morgan Stanley.) No change to use, egress or occupancy.
On file for this project
6 documents · 8 drawing sheets
Floor 5
Floor 4Morgan StanleyUnder Construction8p · 4 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing Sprinkler System: Relocate (1) head and install (1) new head on the 4th Floor; Relocate (3) heads and install (1) new on the 34th Floor as per plans (Morgan Stanley - ADA Restroom.) No change to use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
Modifications to the existing HVAC System: Install new ductwork. Connect to existing toilet exhaust ductwork and installation of a new toilet exhaust fan inline with existing ductwork on the 4th & 34th Floors as per plans (Morgan Stanley ADA Restroom.)
On file for this project
12 documents
Install new plumbing fixtures: (1) FD, (1) WC, (1) lavatory and (1) Janitor Sink on the 4th Floor and (1) FD, (1) WC, (1) lavatory on the 34th Floor and associated CW/sanitary piping on both as per plans (Morgan Stanley - ADA/ Gender Neutral Restroom.)
On file for this project
7 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 3Morgan Stanley2p · 1 filing · 12 docs
Fire ProtectionMechanical
Issued Permit Scope
Mechanical Systems · Sprinklers
Modification to mechanical systems as per plans filed herewith. No change in use, occupancy or egress.
On file for this project
23 documents · 2 drawing sheets
Floor 2
Floor 1Interior renovation for existing store, 1st floor8p · 6 filings · 18 docs
ArchitectureCivilDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Construction Fence · General Construction · Mechanical Systems · Plumbing · Sprinklers
INTERIOR RENOVATION FOR EXISTING STORE AT PARTIAL 1ST FLOOR AS PER PLAN FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
18 documents · 5 drawing sheets
APPLICATION FILED FOR RELOCATION AND INSTALLATION OF PLUMBING FIXTURES (GAS & DOMESTIC) AND SPRINKLER HEADS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents
PROPOSED PLUMBING FOR EATING AND DRINKING ESTABLISHMENT - FIRST FLOOR. NEW PLUMBING FIXTURES (SINKS). NO CHANGE TO EXISTING BATHROOM. NO GAS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
3 documents
Latest 3 of 6 filings on this floor.
MezzanineTenant space interior removal and fitout1 filing · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems
APPLICATION FILED FOR INTERIOR REMOVAL AND NEW FITOUT IN TENANT SPACE, INCLUDING PARTITIONS, CEILING, FINISHES, AND MECHANICAL WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
25 documents
CellarPlumbing fixture and sprinkler head installation13p · 2 filings · 20 docs
ArchitectureCivilDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Sprinklers
APPLICATION FILED FOR RELOCATION AND INSTALLATION OF PLUMBING FIXTURES (GAS & DOMESTIC) AND SPRINKLER HEADS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 2 drawing sheets
APPLICATION FILED FOR INTERIOR REMOVAL AND NEW FITOUT IN TENANT SPACE, INCLUDING PARTITIONS, CEILING, FINISHES, AND MECHANICAL WORK AS PER PLANS FILED HEREWITH. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
25 documents · 11 drawing sheets
Sub-CellarMorgan Stanley4p · 3 filings · 12 docs
DMFire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Sprinklers
APPLICATION FILED FOR RELOCATION AND INSTALLATION OF PLUMBING FIXTURES (GAS & DOMESTIC) AND SPRINKLER HEADS. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
On file for this project
7 documents · 1 drawing sheet
Modification to sprinkler systems as per plans filed herewith. No change in use, occupancy or egress.
On file for this project
3 documents · 2 drawing sheets
Modification to mechanical systems as per plans filed herewith. No change in use, occupancy or egress.
On file for this project
23 documents · 1 drawing sheet
Site & exteriorSpinUnder Construction14 filings · 20 docs
ArchitectureGeneralMechanicalStructural
Issued Permit Scope
Sidewalk Shed · Sign · Structural
Erect sign structure for illuminated (LED) projecting advertising sign on wall. AKA 1620 Broadway.- Signs filed under separte applications #'s M01427533 and M01427538. No change of use, egress or occupancy
On file for this project
7 documents · 8 drawing sheets
Erect illuminated projecting advertising sign on wall- AKA 1620 Broadway-Sign A (North Elevation).- Structure filed under # M01427549. No change of use, egress or occupancy
On file for this project
3 documents · 7 drawing sheets
Erect illuminated projecting advertising sign on wall-AKA 1620 Broadway- Sign B (South Elevation). Structure filed separately under # M01427549. No change of use, egress or occupancy
On file for this project
3 documents · 7 drawing sheets
Latest 3 of 14 filings on this floor.