Predominantly retail with other uses
7500 5TH AVENUE
BROOKLYN · Bay Ridge · BIN 3148781
💬 Discuss this project
1930Year Built
3Stories
K4Building Class
R6BZoning
5,160 sfGross Floor Area
1Units
1 Active Violation 1 likely answered ▸FDNY Report ↗
Predominantly retail with other uses · Owner of record: Yong Sheng Property · 1,808 sf lot · 2.85 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofSantander3p · 2 filings · 14 docs
Floor 35th Avenue Storage7p · 3 filings · 20 docs
Floor 25th Avenue Storage2p · 1 filing · 16 docs
Floor 15th Avenue Storage10p · 2 filings · 20 docs
Cellar5th Avenue Storage, Santander15p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Lam Group1103/22/2026
Santander1003/21/2026
Independence Community Bank503/21/2026
Banco Santander303/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/16/2024$2.3M—— → —$441/sf building
06/16/2017$2.8M—Santander Bank, N.A → PERFECT JSK CORP.$543/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Adel Sageer Architect404/08/2026
MK Associates409/16/2025
Zheng & Associates204/18/2025
Concessi Engineering608/03/2022
Newtec Engineering110/18/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MPDC Design & Construction1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Urban Construction & DesignGeneral Contractor303/21/2026
HP ServicesPlumbing307/08/2026
Perry Mechanical ContractingGeneral Contractor303/21/2026
Zaq ConstructionGeneral Contractor203/21/2026
Aaron Plumbing and Mechanical SystemsPlumbing207/08/2026
Urban Construction & DesignScaffold107/08/2026
Adco ElectricalElectrical103/21/2026
Crossfield Plumbing & HeatingPlumbing106/28/2026
A.C. Morgan ElectricElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Zheng & Associates7330804/08/2026
Obaid Mian849110/18/2021
Building Lifecycle
All (96)Filed (17)Permit Issued (10)Signed Off (3)Violation (28)Inspection (10)Special Inspection (28)
04/10/2026
Special inspection requirement — Lighting in dwelling units
Jinfar Liu
04/10/2026
Special inspection requirement — Interior lighting power
Jinfar Liu
04/10/2026
Special inspection requirement — Lighting controls
Jinfar Liu
04/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jinfar Liu
04/10/2026
Special inspection requirement — Mechanical Systems
Jinfar Liu
04/10/2026
Special inspection requirement — Energy Code Compliance Inspections
Jinfar Liu
04/10/2026
Special inspection requirement — Final
Jinfar Liu
04/08/2026
Filed — Alteration
INTERIOR RENOVATION FOR EXISTING RESIDENTIAL AND COMMERICAL BUILDING @ 3RD FLOOR ONLY. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01148780-P1
04/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jinfar Liu
04/08/2026
Special inspection requirement — Mechanical Systems
Jinfar Liu
04/08/2026
Special inspection requirement — Energy Code Compliance Inspections
Jinfar Liu
04/08/2026
Special inspection requirement — Final
Jinfar Liu
04/08/2026
Special inspection requirement — Lighting in dwelling units
Jinfar Liu
04/08/2026
Special inspection requirement — Interior lighting power
Jinfar Liu
04/08/2026
Special inspection requirement — Lighting controls
Jinfar Liu
01/05/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/11/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
12/08/2025
Permit issued — Boiler Equipment
B01317853-S1-BE
12/01/2025
Filed — Alteration
INSTALLATION OF (1) NEW NAVIEN COMBI BOILER (HEAT & HOT WATER COIL) @ STAIRWAY ON THIRD FLOOR
B01317853-S1
12/01/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
12/01/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jinfar Liu
12/01/2025
Special inspection requirement — Heating Systems
Jinfar Liu
11/19/2025
Permit issued — Boiler Equipment
B01317853-I1-BE
11/13/2025
Filed — Alteration
INSTALLATION OF (1) NEW NAVIEN COMBI BOILER (HEAT & HOT WATER COIL) @ STAIRWAY ON THIRD FLOOR
B01317853-I1
11/13/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jinfar Liu
11/12/2025
Special inspection requirement — Heating Systems
Jinfar Liu
09/16/2025
Filed — Alteration
THE SCOPE OF WORK CONSISTS OF INSTALLING NEW SIGN AT THE BUILDING FACADES, NO CHANGES TO THE BUILDING USE, OCCUPANCY OR EGRESS.
B01213148-S3
06/02/2025
Permit issued — Plumbing
B01213148-S2-PL
05/27/2025
Filed — Alteration
THE SCOPE OF WORK CONSISTS OF INSTALLING NEW SIGN AT THE BUILDING FACADES, NO CHANGES TO THE BUILDING USE, OCCUPANCY OR EGRESS.
B01213148-S2
05/09/2025
Permit issued — General Construction
B01213148-I1-GC
05/06/2025
Permit issued — Construction Fence
B01213148-S1-FN
05/05/2025
Filed — Alteration
THE SCOPE OF WORK CONSISTS OF INSTALLING NEW SIGN AT THE BUILDING FACADES, NO CHANGES TO THE BUILDING USE, OCCUPANCY OR EGRESS.
B01213148-I1
05/05/2025
Filed — Alteration
THE SCOPE OF WORK CONSISTS OF INSTALLING NEW SIGN AT THE BUILDING FACADES, NO CHANGES TO THE BUILDING USE, OCCUPANCY OR EGRESS.
B01213148-S1
04/25/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/25/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jinfar Liu
04/23/2025
Special inspection requirement — Energy Code Compliance Inspections
Jinfar Liu
04/23/2025
Special inspection requirement — HVAC-R and service water heating system controls
Jinfar Liu
04/23/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Jinfar Liu
04/23/2025
Special inspection requirement — HVAC-R and service water heating equipment
Jinfar Liu
04/18/2025
Filed — Alteration
PLUMBING WORK FOR EXISTING COMMERICAL AND RESIDENTIAL USE BUILDING. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01148937-P1
04/16/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Jinfar Liu
04/16/2025
Special inspection requirement — Energy Code Compliance Inspections
Jinfar Liu
04/16/2025
Special inspection requirement — HVAC-R and service water heating system controls
Jinfar Liu
04/16/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Jinfar Liu
04/16/2025
Special inspection requirement — HVAC-R and service water heating equipment
Jinfar Liu
12/13/2024
Permit issued — General Construction
B01148780-I1-GC-CX
12/13/2024
Permit issued — Plumbing
B01148937-I1-PL
12/03/2024
Filed — Alteration
PLUMBING WORK FOR EXISTING COMMERICAL AND RESIDENTIAL USE BUILDING. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01148937-I1
12/03/2024
Filed — Alteration
INTERIOR RENOVATION FOR EXISTING RESIDENTIAL AND COMMERICAL BUILDING @ 3RD FLOOR ONLY. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01148780-I1
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/25/2023
Violation issued (HPD, open)
B
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/11/2023
Signed off — Alteration
B00595103-I1
12/12/2022
Signed off — Alteration
DISCONNECT EXISTING GAS PIPE TO EXISTING GAS SHUT OFF VALVE. RECONNECT EXISTING GAS PIPING TO NEW BOILER AND NEW GAS WATER HEATER. DISCONNECT EXISTING WATER PIPING AND RECONNECT TO NEW BOILER AND HOT WATER HEATER. THIS FILING IS TO REPLACE LAA 340344167.
B00679184-I1
08/05/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/03/2022
Filed — Alteration
DISCONNECT EXISTING GAS PIPE TO EXISTING GAS SHUT OFF VALVE. RECONNECT EXISTING GAS PIPING TO NEW BOILER AND NEW GAS WATER HEATER. DISCONNECT EXISTING WATER PIPING AND RECONNECT TO NEW BOILER AND HOT WATER HEATER. THIS FILING IS TO REPLACE LAA 340344167.
B00679184-P1
08/02/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/21/2022
Permit issued — Plumbing
B00679184-I1-PL
Latest 60 of 96 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWBoiler EquipmentSigned-offHP Services12/08/2025
DOB NOWBoiler EquipmentSigned-offHP Services11/19/2025
DOB NOWPlumbingPermit IssuedCrossfield Plumbing & Heating06/02/2025
DOB NOWGeneral ConstructionPermit IssuedUrban Construction & Design05/09/2025
DOB NOWConstruction FencePermit IssuedUrban Construction & Design05/06/2025
DOB NOWGeneral ConstructionPermit IssuedZaq Construction12/13/2024
DOB NOWPlumbingPermit IssuedHP Services12/13/2024
DOB NOWPlumbingSigned-offAaron Plumbing and Mechanical Systems07/21/2022
DOB NOWBoiler EquipmentSigned-offAaron Plumbing and Mechanical Systems03/03/2022
DOB NOWMechanical SystemsSigned-offPerry Mechanical Contracting10/18/2021
BISOTISSUEDQuest Builders Group02/08/2018
BISMHISSUEDQuest Builders Group02/08/2018
BISOTISSUEDQuest Builders Group02/08/2018
BISPLISSUEDA & M Warshaw Plumbing & Heating08/01/2017
BISOTISSUEDQuest Builders Group07/31/2017
BISEQISSUEDQuest Builders Group07/31/2017
BIS—ISSUEDB+W Architecture07/26/2017
BISMHISSUEDQuest Builders Group07/12/2017
BISOTISSUEDQuest Builders Group05/23/2017
BIS—ISSUEDAmerican Sign & Electrical Con08/02/2013
BIS—ISSUEDAmerican Sign & Electrical Con08/02/2013
BIS—ISSUEDGoing Sign & Servicing Co06/16/2006
BIS—ISSUEDGoing Sign & Servicing Co06/16/2006
BISMHISSUEDIntegrated HVAC Systems & Service08/01/2002
BISOTISSUEDS. Digiacomo Construction07/30/2002
BISEQISSUEDS. Digiacomo Construction07/30/2002
BISEQISSUEDActive Store Fronts10/07/1993
BISEQISSUEDCross Atlantic Wall Systems08/02/1993
1 project · most recent 04/08/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
04/08/2026Permit IssuedZaq ConstructionAir Conditioning Systems
Cooling
Gree LIV09HP230V1R32AH 9,000 BTU · Fan Coil Indoor ×10
LIV12HP230V1R32AH 12,000 BTU · Fan Coil Indoor ×10
LIV18HP230V1R32AH 18,000 BTU · Fan Coil Indoor ×10
LIV09HP230V1R32AO 9,000 BTU · Heat Pump Outdoor ×5
LIV12HP230V1R32AO 12,000 BTU · Heat Pump Outdoor ×5
LIV18HP230V1R32AO 18,000 BTU · Heat Pump Outdoor ×5
MUL24HP230V1R32AO 24,000 BTU · Heat Pump Outdoor ×5
2 projects · most recent 09/16/2025
Water/Sanitary Gas
FiledStatusContractorScope
09/16/2025Permit IssuedCrossfield Plumbing & HeatingWater/Sanitary
04/18/2025Permit IssuedHP ServicesGas, Water/Sanitary
4 projects · most recent 10/12/2025
General Wiring Lighting
FiledStatusContractorScope
10/12/2025CompleteA.C. Morgan ElectricGeneral Wiring
05/26/2025Permit IssuedBDS ElectricGeneral Wiring, Lighting
01/19/2022Permit IssuedCorp Electrical TechnologiesGeneral Wiring
03/09/2018Permit IssuedAdco Electrical2 meters, 1 new_meters
1 project · most recent 09/16/2025
Fence
FiledStatusContractorScope
09/16/2025Permit IssuedCrossfield Plumbing & HeatingFence
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
01/05/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/11/2025Pass-Final Boiler Equipment InspectionPassView ↗
12/01/2025Pass-Final Boiler Equipment InspectionPassView ↗
11/13/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/25/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/25/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/05/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/02/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/15/2022Pass-Final Boiler Equipment InspectionPassView ↗
03/18/2022No Access-Final Boiler Equipment InspectionNo AccessView ↗
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
04/10/2026Lighting in dwelling unitsJinfar Liuenergy_progress
04/10/2026Interior lighting powerJinfar Liuenergy_progress
04/10/2026Lighting controlsJinfar Liuenergy_progress
04/10/2026Fire-Resistant Penetrations and JointsJinfar Liuspecial
04/10/2026Mechanical SystemsJinfar Liuspecial
04/10/2026Energy Code Compliance InspectionsJinfar Liuprogress
04/10/2026FinalJinfar Liuprogress
04/08/2026Fire-Resistant Penetrations and JointsJinfar Liuspecial
04/08/2026Mechanical SystemsJinfar Liuspecial
04/08/2026Energy Code Compliance InspectionsJinfar Liuprogress
04/08/2026FinalJinfar Liuprogress
04/08/2026Lighting in dwelling unitsJinfar Liuenergy_progress
04/08/2026Interior lighting powerJinfar Liuenergy_progress
04/08/2026Lighting controlsJinfar Liuenergy_progress
12/01/2025Fire-Resistant Penetrations and JointsJinfar Liuspecial
12/01/2025Heating SystemsJinfar Liuspecial
11/12/2025Fire-Resistant Penetrations and JointsJinfar Liuspecial
11/12/2025Heating SystemsJinfar Liuspecial
04/23/2025Fire-Resistant Penetrations and JointsJinfar Liuspecial
04/23/2025Energy Code Compliance InspectionsJinfar Liuprogress
04/23/2025HVAC-R and service water heating system controlsJinfar Liuenergy_progress
04/23/2025HVAC-R and service water piping design and insulationJinfar Liuenergy_progress
04/23/2025HVAC-R and service water heating equipmentJinfar Liuenergy_progress
04/16/2025Fire-Resistant Penetrations and JointsJinfar Liuspecial
04/16/2025Energy Code Compliance InspectionsJinfar Liuprogress
Latest 25 of 28.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
5th Avenue StorageIndustrial / WarehouseCellar, Floors 1–3
Project B01148780 Alteration · Permit Entire · 12/03/2024
Project B01148937 Alteration · Permit Entire · 12/03/2024
SantanderBank / Financial branchCellar, Roof
Project B00679184 Alteration · LOC Issued · 07/19/2022
Project B00679318 Alteration · LOC Issued · 02/16/2022
Project B00595103 Alteration · LOC Issued · 10/18/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 250 on file (BIS + DOB NOW)
▸Plans & Drawings17
▸DOB NOWPlans/Sketch17
09/01/2026B00595103-I1Request digital key ↗
08/31/2026B00679318-P3Request digital key ↗
08/31/2026B00679318-P2Request digital key ↗
Showing 3 of 17 on file for this type
▸Applications & Permits46
▸BISPLAN / WORK APPROVAL APPLICATION36
03/25/2025321587092Open ↗
03/18/2025321587092Open ↗
01/24/2025321587092Open ↗
Showing 3 of 36 on file for this type
▸BISWORK PERMIT APPLICATION8
08/01/2017340505153Open ↗
07/31/2017340505126Open ↗
07/26/2017321587092Open ↗
Showing 3 of 8 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
04/19/2018321587092Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
12/21/2017321587092Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
07/26/2017321587092Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
01/12/2023321587092Open ↗
▸Seals & Professional Certifications61
▸DOB NOWDPL-1: Design Professional Seal & Signature17
09/01/2026B00595103-I1Open ↗
08/31/2026B00679318-P3Open ↗
08/31/2026B00679318-I1Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
08/27/2026B01148780-I1Open ↗
08/27/2026B01148780-I1Open ↗
08/27/2026B01148780-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/23/2026B01317853-I1Open ↗
09/23/2026B01317853-S1Open ↗
09/23/2026B01317853-S1Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION9
10/06/2017321646091Open ↗
10/06/2017321646091Open ↗
08/17/2017340505144Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
07/11/2017340505153Open ↗
06/08/2017321587092Open ↗
05/19/2017340505144Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
06/08/2017321587092Open ↗
08/13/2013320780419Open ↗
08/12/2013320780400Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
07/11/2017340505153Open ↗
05/19/2017340505144Open ↗
05/19/2017340505126Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
07/11/2017340505153Open ↗
05/19/2017340505144Open ↗
05/19/2017340505126Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM2
08/13/2013320780419Open ↗
08/12/2013320780400Open ↗
▸Trade Schedules & Equipment3
▸BISFA - FDNY APPROVAL : FD-FAA1
10/25/2022321584549Open ↗
▸BISSCHEDULE B - PLUMBING1
07/11/2017340505153Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
10/06/2017321646091Open ↗
▸Safety & Tenant Protection6
▸BISSTREET TREE CHECKLIST4
06/14/2023321587092Open ↗
11/22/2021321599392Open ↗
07/17/2017321587092Open ↗
Showing 3 of 4 on file for this type
▸BISTenant Protection Plan and Notes1
10/06/2017321646091Open ↗
▸BISSTREET TREE SIGNOFF1
03/14/2022321587092Open ↗
▸Environmental & Asbestos21
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
09/01/2026B00595103-I1Open ↗
08/31/2026B00679318-P3Open ↗
08/31/2026B00679318-I1Open ↗
Showing 3 of 13 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)8
11/22/2021321599392Open ↗
10/06/2017321646091Open ↗
07/11/2017340505153Open ↗
Showing 3 of 8 on file for this type
▸Energy Compliance23
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY11
05/16/2022340505153Open ↗
11/22/2021321599392Open ↗
06/21/2021340505126Open ↗
Showing 3 of 11 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
05/16/2022340505153Open ↗
06/21/2021340505126Open ↗
09/29/2020340505126Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
08/17/2017340505144Open ↗
07/19/2017321587092Open ↗
07/19/2017321587092Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
07/11/2017340505153Open ↗
05/19/2017340505126Open ↗
▸BISNYCECC ANALYSIS2
05/31/2023321587092Open ↗
05/19/2017340505126Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
03/14/2022321587092Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00595103-I1Open ↗
▸Inspections & Test Reports12
▸BISTECHNICAL REPORT: RESPONSIBILITY12
05/16/2022340505153Open ↗
04/22/2022300286483Open ↗
04/22/2022300286483Open ↗
Showing 3 of 12 on file for this type
▸Approvals, Objections & Sign-offs17
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
10/27/2022321584549Open ↗
05/17/2022340505153Open ↗
04/26/2022300286483Open ↗
Showing 3 of 7 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE6
12/08/2021321599392Open ↗
05/06/2021321599392Open ↗
10/06/2017321646091Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
08/13/2013320780419Open ↗
08/12/2013320780400Open ↗
▸BISLetter of Intent to Revoke1
07/27/2017340505126Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
11/22/2021321599392Open ↗
▸Cost, Insurance & Ownership19
▸BISCOST AFFIDAVIT17
10/13/2022321584549Open ↗
12/06/2021321587092Open ↗
11/22/2021321587092Open ↗
Showing 3 of 17 on file for this type
▸BISCOST AFFIDAVIT ESTIMATE: (PW3)1
06/14/2022321587092Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
05/16/2022340505153Open ↗
▸Filing & Intake Forms21
▸BISADDITIONAL INFORMATION11
04/22/2022300286483Open ↗
06/18/2021300286483Open ↗
02/21/2018321587092Open ↗
Showing 3 of 11 on file for this type
▸BISEFILING COVER SHEET6
02/03/2021321599392Open ↗
10/06/2017321646091Open ↗
06/12/2017321587092Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
07/11/2017340505153Open ↗
05/19/2017340505144Open ↗
05/19/2017340505126Open ↗
▸BISBOROUGH INTAKE FORM1
04/19/2018321587092Open ↗
▸Other Documents2
▸BISPLOT DIAGRAM2
10/06/2017321646091Open ↗
06/08/2017321587092Open ↗