← Back
Zoned residential, not Manhattan
76 EAST 53 STREET
BROOKLYN · East Flatbush-Rugby · BIN 3100241
💬 Discuss this project
0Year Built
—Stories
V0Building Class
R6Zoning
0 sfGross Floor Area
0Units
Rent Stabilized8 Open Violations ▸FDNY Report ↗
Zoned residential, not Manhattan · Owner of record: EAST 53 RESIDENCE LLC · 3,325 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneralOther
Roof1 filing · 20 docs
Penthouse1 filing · 20 docs
Floor 41 filing · 20 docs
Floor 31 filing · 20 docs
Floor 21 filing · 20 docs
Floor 12 filings · 20 docs
Site & exterior4p · 5 filings · 10 docs
Filed — no permit issued46p · 4 filings · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BROOKBRIDGE DEVELOPERS1504/09/2026
MS INVESTMENTS 31404/09/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/26/2025$1.2M—EAST EDGE BK LLC → EAST 53 RESIDENCE LLC— not available
01/21/2020$925K—— → —— not available
07/26/2018$750K—Private party → RPK HOLDINGS LLC— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BADALY ENGINEERING PLLC501/24/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PETER KLEIN ASSOC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MJH CONSTRUCTION CORPGeneral Contractor604/09/2026
PRECISION HOIST & SCAFFO*General Contractor604/09/2026
HARRY'S DESIGN INCGeneral Contractor204/09/2026
MAMC CONSULTING REPS LLCGeneral Contractor104/09/2026
QUALITY PIPING, INCFire Protection107/08/2026
NESS MECHANICAL P & H INCPlumbing107/08/2026
Y&L INTERIOR LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BADALY ARCHITECT PLLC7137101/24/2022
HRF SERVICES CORP5616109/08/2020
Building Lifecycle
All (62)Filed (5)Permit Issued (16)Violation (9)Inspection (11)Objection (4)Special Inspection (14)Tax Incentive (3)
01/01/2030
421-a(16) construction completed
03/19/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
03/12/2026
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
02/24/2026
Inspection — Fail-Final Curb Cut Non-Directive 14
Fail
View inspection ↗
12/23/2025
Inspection — Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test
Certified
View inspection ↗
12/23/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
12/22/2025
Permit issued — Curb Cut
B01084388-S2-CC
12/19/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/30/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
10/30/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
10/30/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/12/2025
Permit issued — Mechanical Systems
B01084388-S4-MS
08/21/2025
Permit issued — Protection and Mechanical Methods
B01267587-I1-PMM
08/20/2025
Permit issued — Protection and Mechanical Methods
B01267591-I1-PMM
08/18/2025
Permit issued — Supported Scaffold
B01267577-I1-SF
08/18/2025
Permit issued — Sidewalk Shed
B01267539-I1-SH
08/15/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
08/15/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
08/12/2025
Permit issued — Plumbing
B01084388-S6-PL
08/08/2025
Permit issued — Sprinklers
B01084388-S3-EW-SP
07/14/2025
Permit issued — Support of Excavation
B01084388-S5-SE
07/14/2025
Permit issued — Structural
B01084388-I1-ST
07/09/2025
Permit issued — Earth Work
B01084388-S1-FO-EA
06/17/2025
Permit issued — Construction Fence
B01085903-I1-FN
04/16/2025
Violation issued (ECB, closed)
Construction
04/16/2025
Violation issued (ECB, closed)
Construction
08/14/2024
421-a(16) registration filed
05/01/2023
Violation issued (ECB, closed)
Construction
01/23/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/23/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/04/2023
Violation issued (ECB, closed)
Construction
01/04/2023
Violation issued (ECB, closed)
Construction
12/13/2022
Permit issued — Construction Fence
B00338252-I1-FN
06/14/2022
421-a(16) construction commenced
01/24/2022
Filed — Alteration
B00361222-I1
12/27/2021
Violation issued (ECB, closed)
Construction
10/20/2021
Filed — Alteration
B00609098-I1
10/15/2021
Permit issued — Construction Fence
B00338252-I1-FN
06/02/2021
Special inspection requirement — Mechanical Systems
FAHAD FATEH
06/02/2021
Special inspection requirement — Final
FAHAD FATEH
06/02/2021
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
06/02/2021
Special inspection requirement — HVAC and service water heating system controls
FAHAD FATEH
06/02/2021
Special inspection requirement — HVAC insulation and sealing
FAHAD FATEH
06/02/2021
Special inspection requirement — Shutoff dampers
FAHAD FATEH
06/02/2021
Special inspection requirement — HVAC and service water heating equipment
FAHAD FATEH
06/01/2021
Objection resolved — Addressed
12/02/2020
Objection resolved — Addressed
10/28/2020
Filed — Alteration
Provide new mechanical system in conjunction with New Building Application #340740620.
B00393869-P1
10/28/2020
Filed — Alteration
B00393854-I1
10/28/2020
Objection raised — Scope
10/28/2020
Objection raised — Scope
10/27/2020
Special inspection requirement — Mechanical Systems
10/27/2020
Special inspection requirement — Energy Code Compliance Inspections
10/27/2020
Special inspection requirement — Final
10/27/2020
Special inspection requirement — HVAC insulation and sealing
10/27/2020
Special inspection requirement — HVAC and service water heating equipment
10/27/2020
Special inspection requirement — Shutoff dampers
10/27/2020
Special inspection requirement — HVAC and service water heating system controls
09/30/2020
Violation issued (ECB, closed)
Construction
09/08/2020
Filed — Alteration
Provide new mechanical system in conjunction with New Building Application #340740620.
B00393869-I1
Latest 60 of 62 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWCurb CutSigned-offMJH CONSTRUCTION CORP12/22/2025
DOB NOWMechanical SystemsSigned-offMJH CONSTRUCTION CORP09/12/2025
DOB NOWProtection and Mechanical MethodsSigned-offPRECISION HOIST & SCAFFO*08/21/2025
DOB NOWProtection and Mechanical MethodsSigned-offPRECISION HOIST & SCAFFO*08/20/2025
DOB NOWSupported ScaffoldSigned-offPRECISION HOIST & SCAFFO*08/18/2025
DOB NOWSidewalk ShedSigned-offPRECISION HOIST & SCAFFO*08/18/2025
DOB NOWPlumbingSigned-offNESS MECHANICAL P & H INC08/12/2025
DOB NOWSprinklersSigned-offQUALITY PIPING, INC08/08/2025
DOB NOWSupport of ExcavationSigned-offMJH CONSTRUCTION CORP07/14/2025
DOB NOWStructuralSigned-offMJH CONSTRUCTION CORP07/14/2025
DOB NOWEarth WorkSigned-offMJH CONSTRUCTION CORP07/09/2025
DOB NOWConstruction FenceSigned-offMJH CONSTRUCTION CORP06/17/2025
DOB NOWConstruction FenceSigned-offMAMC CONSULTING REPS LLC12/13/2022
DOB NOWConstruction FenceSigned-offY&L INTERIOR LLC10/15/2021
DOB NOWConstruction FenceSigned-offHARRY'S DESIGN INC08/13/2020
DOB NOWConstruction FenceSigned-offHARRY'S DESIGN INC07/23/2020
BIS—ISSUEDHARRY'S DESIGN INC09/08/2020
1 project · most recent 10/28/2020
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
10/28/2020——Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Lg ARUN024GSS4 24,000 BTU · Vrf Outdoor ×50
ARUN038GSS4 38,000 BTU · Vrf Outdoor ×15
Trane 4WCC4024A1000A 27,000 BTU · Condensing Unit ×5
Heating
Qmark CWH1151DSAF 2,560 BTU · Electric Heater ×75
Lg ARUN024GSS4 27,000 BTU · Vrf Outdoor ×50
4YCC4038A1060A 42,000 BTU · Vrf Outdoor ×15
Markel 6300 SERIES 06671502 17,065 BTU · Electric Heater ×5
Trane 4WCC4024A1000A 22,000 BTU · Packaged Unit ×5
Ventilation
York EVD06R 146 CFM · Rooftop Unit ×25
EVD08S 236 CFM · Rooftop Unit ×5
EVD10S 385 CFM · Rooftop Unit ×5
EVD11R 736 CFM · Rooftop Unit ×5
▾Field Inspections (DOB CAP) — 11
DateTypeResultReport
03/19/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
03/12/2026Pass-Final Curb Cut Non-Directive 14PassView ↗
02/24/2026Fail-Final Curb Cut Non-Directive 14FailView ↗
12/23/2025Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve TestCertifiedView ↗
12/23/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/19/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/30/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/30/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
10/30/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/15/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
08/15/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
06/02/2021Mechanical SystemsFAHAD FATEHspecial
06/02/2021FinalFAHAD FATEHprogress
06/02/2021Energy Code Compliance InspectionsFAHAD FATEHprogress
06/02/2021HVAC and service water heating system controls FAHAD FATEHenergy_progress
06/02/2021HVAC insulation and sealing FAHAD FATEHenergy_progress
06/02/2021Shutoff dampersFAHAD FATEHenergy_progress
06/02/2021HVAC and service water heating equipment FAHAD FATEHenergy_progress
10/27/2020Mechanical Systems—special
10/27/2020Energy Code Compliance Inspections—progress
10/27/2020Final—progress
10/27/2020HVAC insulation and sealing —energy_progress
10/27/2020HVAC and service water heating equipment —energy_progress
10/27/2020Shutoff dampers—energy_progress
10/27/2020HVAC and service water heating system controls —energy_progress
▾Documents — 20 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/02/2026B00393869-I1Request digital key ↗
08/14/2026B00393869-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/02/2026B00393854-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
08/31/2026B00361222-I1Request digital key ↗
▸DOB NOWPlans/Sketch1
09/01/2026B00609098-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/02/2026B00393854-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
02/01/2020322032821Open ↗
▸BISWORK PERMIT APPLICATION1
10/27/2020322032821Open ↗
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature5
09/02/2026B00393869-I1Open ↗
09/02/2026B00393869-P1Open ↗
09/02/2026B00393854-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
08/23/2026B00393869-I1Open ↗
08/23/2026B00393869-I1Open ↗
▸Safety & Tenant Protection1
▸BISANTI-HARASSMENT CHECKLIST1
02/01/2020322032821Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
10/27/2020322032821Open ↗
10/27/2020322032821Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
02/01/2020322032821Open ↗
▸Other Documents1
▸DOB NOWStructural Peer Review Report1
08/13/2026B00361222-I1Open ↗