| Firm | Filings | Most Recent |
|---|---|---|
| MEHDI GHAZI, P.E., P.C. | 4 | 08/14/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| ALPHA HOME DESIGN LLC | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PRIMROSE SERVICE INC | General Contractor | 2 | 04/09/2026 |
| ROCK E SMALL PLBG&HTG INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MEHDI GHAZI, P.E. P.C. | 7129 | 4 | 08/14/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | PRIMROSE SERVICE INC | 11/12/2025 |
| DOB NOW | Structural | Signed-off | PRIMROSE SERVICE INC | 11/12/2025 |
| DOB NOW | Plumbing | Signed-off | ROCK E SMALL PLBG&HTG INC | 11/12/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Signed-off | ROCK E SMALL PLBG&HTG INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Complete | J Y ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/14/2026 | Signed-off | PRIMROSE SERVICE INC | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/02/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 04/24/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/03/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/03/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/27/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/21/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/18/2026 | Structural Steel - High Strength Bolting | MEHDI GHAZI | special |
| 08/18/2026 | Structural Steel - Welding | MEHDI GHAZI | special |
| 08/18/2026 | Structural Steel - Details | MEHDI GHAZI | special |
| 08/18/2026 | Concrete - Cast-In-Place | MEHDI GHAZI | special |
| 08/18/2026 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 08/18/2026 | Final | MEHDI GHAZI | progress |
| 03/04/2026 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 03/04/2026 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 03/04/2026 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |
| 03/04/2026 | HVAC-R and service water piping design and insulation | MEHDI GHAZI | energy_progress |
| 03/04/2026 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 03/02/2026 | Fire-Resistant Penetrations and Joints | MEHDI GHAZI | special |
| 03/02/2026 | Energy Code Compliance Inspections | MEHDI GHAZI | progress |
| 03/02/2026 | HVAC-R and service water piping design and insulation | MEHDI GHAZI | energy_progress |
| 03/02/2026 | HVAC-R and service water heating system controls | MEHDI GHAZI | energy_progress |
| 03/02/2026 | HVAC-R and service water heating equipment | MEHDI GHAZI | energy_progress |