| Firm | Filings | Most Recent |
|---|---|---|
| SQUARE ARCH, LLC | 1 | 12/02/2024 |
| MOMENTUM SOLAR | 1 | 07/31/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| KAMTECH RESTORATION CORP | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ISLAND ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| KAMTECH RESTORATION CORP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SQ. ARCH, LLC | 4802 | 1 | 12/02/2024 |
| MXV SIA LLC | 9281 | 1 | 07/31/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | KAMTECH RESTORATION CORP | 12/23/2024 |
| DOB NOW | Solar | Permit Issued | MOMENTUM SOLAR | 08/08/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/07/2024 | Complete | BERGER QUALITY ELEC'L CON | — |
| 07/31/2024 | Permit Issued | ISLAND ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2024 | Permit Issued | MOMENTUM SOLAR | 16 panels, 6.56 kw, 282 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/12/2024 | Air barrier - visual inspection | Kaijin Liang | energy_progress |
| 11/12/2024 | Fire-Resistant Penetrations and Joints | Kaijin Liang | special |
| 11/12/2024 | Structural Stability – Alterations of existing buildings | Kaijin Liang | special |
| 11/12/2024 | Energy Code Compliance Inspections | Kaijin Liang | progress |
| 11/12/2024 | Final | Kaijin Liang | progress |
| 07/31/2024 | Fire-Resistant Penetrations and Joints | Mina Makar | special |
| 07/31/2024 | Structural Stability – Alterations of existing buildings | Mina Makar | special |
| 07/31/2024 | Energy Code Compliance Inspections | Mina Makar | progress |
| 07/31/2024 | Final | Mina Makar | progress |
| 07/31/2024 | Air barrier - visual inspection | Mina Makar | energy_progress |