1920Year Built
2Stories
B9Building Class
R6BZoning
2,880 sfGross Floor Area
2Units
Miscellaneous two family · 2,003 sf lot · 1.44 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofSteel deck installation5p · 3 filings · 20 docs
Bulkhead1p · 1 filing · 20 docs
Penthouse15p · 1 filing · 20 docs
Floor 4Steel deck installation22p · 4 filings · 20 docs
Floor 3Steel deck installation23p · 4 filings · 20 docs
Floor 2Steel deck installation23p · 4 filings · 20 docs
Floor 1Steel deck installation22p · 4 filings · 20 docs
CellarSteel deck installation24p · 5 filings · 20 docs
Site & exteriorConstruction fence installation12p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Pacific Holding Enterprises507/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/02/2023$1.3M—Private party → Private party$444/sf building
06/26/2020$1.6M—Private party → Private party$552/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY Building Associates603/25/2026
Madriaga Engineering205/27/2025
Bangash Associates211/12/2024
Rigid Structural Design107/05/2024
J&R Design and Inspection402/05/2024
Pramodray Shah, P.E101/15/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
High Quality 3382203/21/2026
Highquality Construction VNW603/21/2026
Rigid Structural Design103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
B36 ServicesGeneral Contractor1707/08/2026
B36 ServicesScaffold303/21/2026
High Quality ConstructionScaffold307/08/2026
Catman PlumbingPlumbing207/08/2026
Case PlumbingFire Protection107/08/2026
A.C. Morgan ElectricElectrical103/22/2026
QMB Plumbing & HeatingPlumbing107/08/2026
Nash Electric ServicesElectrical103/22/2026
High Quality ConstructionGeneral Contractor104/09/2026
Pacific Holding Enterpr*Scaffold107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM Engineering62441103/25/2026
Building Lifecycle
All (90)Filed (16)Permit Issued (15)Signed Off (7)Inspection (8)Objection (14)Special Inspection (30)
07/29/2026
Special inspection requirement — Protection of exposed foundation insulation
NARESH MAHANGU
07/29/2026
Special inspection requirement — Fenestration areas
NARESH MAHANGU
07/29/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
07/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
07/29/2026
Special inspection requirement — Exterior lighting power
NARESH MAHANGU
07/29/2026
Special inspection requirement — Lighting in dwelling units
NARESH MAHANGU
07/29/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
NARESH MAHANGU
07/29/2026
Special inspection requirement — Air barrier — testing
NARESH MAHANGU
07/29/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
07/29/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
NARESH MAHANGU
07/29/2026
Special inspection requirement — Insulation placement and R values
NARESH MAHANGU
07/29/2026
Special inspection requirement — Interior lighting power
NARESH MAHANGU
07/29/2026
Special inspection requirement — Fenestration air leakage
NARESH MAHANGU
07/29/2026
Special inspection requirement — Lighting controls
NARESH MAHANGU
07/29/2026
Special inspection requirement — Fire-Resistance Rated Construction
NARESH MAHANGU
07/29/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
07/29/2026
Special inspection requirement — Metering
NARESH MAHANGU
03/25/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT OF AN EXISTING 2-STORY TWO-FAMILY BUILDING TO 4-STORY THREE-FAMILY MIXED-USE BUILDING AS PER PLAN. OBTAIN A NEW CERTIFICATE OF OCCUPANCY.
B00856974-P4
03/25/2026
Special inspection requirement — Protection of exposed foundation insulation
NARESH MAHANGU
03/25/2026
Special inspection requirement — Lighting in dwelling units
NARESH MAHANGU
03/25/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
03/25/2026
Special inspection requirement — Lighting controls
NARESH MAHANGU
03/25/2026
Special inspection requirement — Fenestration areas
NARESH MAHANGU
03/25/2026
Special inspection requirement — Fenestration air leakage
NARESH MAHANGU
03/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
03/25/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
NARESH MAHANGU
03/25/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
NARESH MAHANGU
03/25/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
NARESH MAHANGU
03/25/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
03/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
NARESH MAHANGU
03/25/2026
Special inspection requirement — Metering
NARESH MAHANGU
03/17/2026
Permit issued — General Construction
B00856974-I1-GC
12/29/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/27/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT OF AN EXISTING 2-STORY TWO-FAMILY BUILDING TO 4-STORY THREE-FAMILY MIXED-USE BUILDING AS PER PLAN. OBTAIN A NEW CERTIFICATE OF OCCUPANCY.
B00856974-P3
10/21/2025
Signed off — Alteration
BOILER FILING IS CONJUCT WITH A1 JOB #B00856974-I1
B00994557-I1
10/21/2025
Signed off — Alteration
FILE FOUNDATION AND STRUCTURAL WORK TYPES IN CONJUNCTION WITH ALT-CO NEW BUILDING WITH EXISTING ELEMENTS TO REMAIN JOB APPLICATION JOB#B00682906.
B00986484-I1
10/21/2025
Signed off — Alteration
FILING FOR SPRINKLER WORK IN CONJUNCTION WITH DOB APPLICATION#B00856974-I1 AND PLUMBING JOB #B00994557-I1. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01159006-I1
06/20/2025
Signed off — Alteration
BOILER FILING IS CONJUCT WITH A1 JOB #B00856974-I1
B00994557-S2
06/03/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
05/30/2025
Signed off — Alteration
BOILER FILING IS CONJUCT WITH A1 JOB #B00856974-I1
B00994557-S1
05/29/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/28/2025
Permit issued — Boiler Equipment
B00994557-S2-BE
05/27/2025
Filed — Alteration
BOILER FILING IS CONJUCT WITH A1 JOB #B00856974-I1
B00994557-S2
05/19/2025
Permit issued — Sprinklers
B01159006-I1-EW-SP
05/16/2025
Signed off — Alteration
CONSTRUCTION FENCE OUTSIDE OF PROPERTY LINE BUT WITHIN 3 FEET OF PROPERTY LINE.
B00967988-I1
04/25/2025
Permit issued — General Construction
B00856974-I1-GC
04/25/2025
Permit issued — General Construction
B00986484-I1-GC-CX
03/17/2025
Inspection — Pass-Final House Connection
Pass
View inspection ↗
03/13/2025
Permit issued — Plumbing
B00994557-S1-PL
02/28/2025
Objection raised — Plumbing
02/28/2025
Objection resolved — Addressed
02/18/2025
Filed — Alteration
BOILER FILING IS CONJUCT WITH A1 JOB #B00856974-I1
B00994557-S1
02/10/2025
Permit issued — General Construction
B00856974-I1-GC
01/09/2025
Filed — Alteration
FILING FOR SPRINKLER WORK IN CONJUNCTION WITH DOB APPLICATION#B00856974-I1 AND PLUMBING JOB #B00994557-I1. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
B01159006-I1
12/30/2024
Signed off — Alteration
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
B01076016-I1
12/18/2024
Objection raised — Other
12/18/2024
Objection resolved — Addressed
12/16/2024
Permit issued — Construction Fence
B00967988-I1-FN
12/12/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT OF AN EXISTING 2-STORY TWO-FAMILY BUILDING TO 4-STORY THREE-FAMILY MIXED-USE BUILDING AS PER PLAN. OBTAIN A NEW CERTIFICATE OF OCCUPANCY.
B00856974-P2
11/18/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
Latest 60 of 90 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedHigh Quality Construction03/17/2026
DOB NOWBoiler EquipmentSigned-offCatman Plumbing05/28/2025
DOB NOWSprinklersSigned-offS & L Plumbing05/19/2025
DOB NOWGeneral ConstructionPermit IssuedB36 Services04/25/2025
DOB NOWGeneral ConstructionSigned-offB36 Services04/25/2025
DOB NOWPlumbingSigned-offQMB Plumbing & Heating03/13/2025
DOB NOWGeneral ConstructionPermit IssuedB36 Services02/10/2025
DOB NOWConstruction FenceSigned-offHigh Quality Construction12/16/2024
DOB NOWPlumbingSigned-offCatman Plumbing10/17/2024
DOB NOWGeneral ConstructionSigned-offB36 Services09/19/2024
DOB NOWSidewalk ShedSigned-offPacific Holding Enterpr*07/05/2024
DOB NOWGeneral ConstructionPermit IssuedB36 Services06/17/2024
DOB NOWGeneral ConstructionPermit IssuedB36 Services02/27/2024
DOB NOWGeneral ConstructionPermit IssuedB36 Services12/20/2023
DOB NOWConstruction FenceSigned-offHigh Quality Construction11/29/2023
BISPLISSUEDFountain of Trevi06/21/2000
BISOTISSUEDD'Arancio & Sansone Contractors12/01/1999
2 projects · most recent 08/06/2024
General Wiring
FiledStatusContractorScope
08/06/2024CompleteA.C. Morgan ElectricGeneral Wiring
07/16/2024CompleteNash Electric Services—
1 project · most recent 02/05/2024
FiledStatusContractorScope
02/05/2024——2 scope_items
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
12/29/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/03/2025Pass-Final Boiler Equipment InspectionPassView ↗
05/29/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/17/2025Pass-Final House ConnectionPassView ↗
11/18/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/18/2024Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
11/18/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
11/18/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 110
DateRequirementInspectorRole
07/29/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
07/29/2026Air barrier — testing NARESH MAHANGUenergy_progress
07/29/2026Insulation placement and R valuesNARESH MAHANGUenergy_progress
07/29/2026Fenestration areasNARESH MAHANGUenergy_progress
07/29/2026Lighting controlsNARESH MAHANGUenergy_progress
07/29/2026Protection of exposed foundation insulationNARESH MAHANGUenergy_progress
07/29/2026Exterior lighting powerNARESH MAHANGUenergy_progress
07/29/2026Fenestration and door U-factor and product ratingsNARESH MAHANGUenergy_progress
07/29/2026MeteringNARESH MAHANGUenergy_progress
07/29/2026Lighting in dwelling unitsNARESH MAHANGUenergy_progress
07/29/2026Fenestration air leakageNARESH MAHANGUenergy_progress
07/29/2026Interior lighting powerNARESH MAHANGUenergy_progress
07/29/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
07/29/2026Exterior Insulation and Finish Systems (EIFS)NARESH MAHANGUspecial
07/29/2026Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
07/29/2026Fire-Resistance Rated ConstructionNARESH MAHANGUprogress
07/29/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
03/25/2026Interior lighting powerNARESH MAHANGUenergy_progress
03/25/2026Exterior Insulation and Finish Systems (EIFS)NARESH MAHANGUspecial
03/25/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
03/25/2026Structural Stability – Alterations of existing buildingsNARESH MAHANGUspecial
03/25/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
03/25/2026Fire-Resistance Rated ConstructionNARESH MAHANGUprogress
03/25/2026Fenestration and door U-factor and product ratingsNARESH MAHANGUenergy_progress
03/25/2026Lighting controlsNARESH MAHANGUenergy_progress
Latest 25 of 110.
▾Documents — 129 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch16
08/26/2026B00967988-I1Request digital key ↗
08/26/2026B00986524-P1Request digital key ↗
08/26/2026B00986524-I1Request digital key ↗
Showing 3 of 16 on file for this type
▸Zoning, Tax Lot & Property Records12
▸DOB NOWZD1: DOB Zoning Diagram7
08/17/2026B00856974-I1Open ↗
08/17/2026B00856974-P4Open ↗
08/13/2026B00856974-P1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWZoning Exhibit form (1-5)5
08/13/2026B00856974-P1Open ↗
08/13/2026B00856974-P4Open ↗
08/13/2026B00856974-P2Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications63
▸DOB NOWSpecial Inspector Seal & Signature26
10/07/2026B00986484-I1Open ↗
10/07/2026B00986484-I1Open ↗
10/07/2026B00986484-I1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWProgress Inspector Seal & Signature21
10/07/2026B00986484-I1Open ↗
10/07/2026B00986484-I1Open ↗
09/23/2026B00856974-I1Open ↗
Showing 3 of 21 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/26/2026B00986524-I1Open ↗
08/26/2026B00986524-P1Open ↗
08/26/2026B00986484-I1Open ↗
Showing 3 of 16 on file for this type
▸Trade Schedules & Equipment5
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)5
08/13/2026B00856974-P3Open ↗
08/13/2026B00856974-P4Open ↗
08/13/2026B00856974-P1Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection1
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00856974-I1Open ↗
▸Environmental & Asbestos13
▸DOB NOWDEP ACP-5: Asbestos Assessment Report13
08/26/2026B00986524-P1Open ↗
08/26/2026B00986524-I1Open ↗
08/26/2026B00986484-I1Open ↗
Showing 3 of 13 on file for this type
▸Other Documents19
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
08/13/2026B00856974-P4Open ↗
08/13/2026B00856974-P3Open ↗
08/13/2026B00856974-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWSite Survey: Initial5
08/13/2026B00856974-P4Open ↗
08/13/2026B00856974-P3Open ↗
08/13/2026B00856974-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProperty Ownership Certification5
08/17/2026B00856974-I1Open ↗
08/17/2026B00856974-P2Open ↗
08/17/2026B00856974-P3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWAdjoining Owners Notification2
08/13/2026B00986484-I1Open ↗
08/13/2026B00986524-I1Open ↗
▸DOB NOWPlot Diagram2
08/13/2026B00986524-P1Open ↗
08/13/2026B00986524-I1Open ↗