← Back
Two family converted from one family
77-33 88 STREET
QUEENS · Glendale · BIN 4094439
💬 Discuss this project
1920Year Built
2Stories
B3Building Class
R4AZoning
1,536 sfGross Floor Area
2Units
Two family converted from one family · 3,208 sf lot · 0.48 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/27/2022$1.2M—Private party → Private party$765/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
STUDIO HUJI408/17/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DFE CONTRACTOR LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AM ENGINEERING SERVICES P7975308/17/2025
ARCHITECTURAL CONCEPT3642308/17/2025
Building Lifecycle
All (37)Filed (4)Permit Issued (1)Inspection (2)Special Inspection (30)
08/18/2025
Special inspection requirement — Post-installed Anchors
Albert Munoz
08/18/2025
Special inspection requirement — Fenestration areas
MUZAFFAR JAMAL
08/18/2025
Special inspection requirement — Fenestration air leakage
MUZAFFAR JAMAL
08/18/2025
Special inspection requirement — Insulation placement and R values
MUZAFFAR JAMAL
08/18/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
MUZAFFAR JAMAL
08/18/2025
Special inspection requirement — Energy Code Compliance Inspections
Albert Munoz
08/18/2025
Special inspection requirement — Final
Albert Munoz
08/18/2025
Special inspection requirement — Structural Wood Frame
Albert Munoz
08/18/2025
Special inspection requirement — Preliminary
Albert Munoz
08/18/2025
Special inspection requirement — Footing and Foundation
Albert Munoz
08/18/2025
Special inspection requirement — Concrete - Cast-In-Place
MUZAFFAR JAMAL
08/18/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
MUZAFFAR JAMAL
08/17/2025
Filed — Alteration
APPLICATION FILED TO PROPOSE DECK AS PER PLAN. NO CHANGE IN USE OR OCCUPANCY
Q00945646-P3
07/16/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
MUZAFFAR JAMAL
07/16/2025
Special inspection requirement — Concrete - Cast-In-Place
MUZAFFAR JAMAL
07/16/2025
Special inspection requirement — Post-installed Anchors
Albert Munoz
07/16/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
MUZAFFAR JAMAL
07/16/2025
Special inspection requirement — Energy Code Compliance Inspections
Albert Munoz
07/16/2025
Special inspection requirement — Final
Albert Munoz
07/16/2025
Special inspection requirement — Footing and Foundation
Albert Munoz
07/16/2025
Special inspection requirement — Preliminary
Albert Munoz
07/16/2025
Special inspection requirement — Structural Wood Frame
Albert Munoz
07/16/2025
Special inspection requirement — Fenestration air leakage
MUZAFFAR JAMAL
07/16/2025
Special inspection requirement — Fenestration areas
MUZAFFAR JAMAL
07/16/2025
Special inspection requirement — Insulation placement and R values
MUZAFFAR JAMAL
07/02/2024
Filed — Alteration
APPLICATION FILED TO PROPOSE DECK AS PER PLAN. NO CHANGE IN USE OR OCCUPANCY
Q00945646-P2
07/01/2024
Special inspection requirement — Concrete - Cast-In-Place
MUZAFFAR JAMAL
07/01/2024
Special inspection requirement — Fenestration air leakage
MUZAFFAR JAMAL
07/01/2024
Special inspection requirement — Insulation placement and R values
MUZAFFAR JAMAL
07/01/2024
Special inspection requirement — Fenestration areas
MUZAFFAR JAMAL
07/01/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
MUZAFFAR JAMAL
07/01/2024
Special inspection requirement — Structural Wood Frame
Albert Munoz
06/12/2024
Permit issued — Foundation
Q00945646-I1-GC-CX
04/29/2024
Filed — Alteration
APPLICATION FILED TO PROPOSE DECK AS PER PLAN. NO CHANGE IN USE OR OCCUPANCY
Q00945646-P1
12/05/2023
Filed — Alteration
APPLICATION FILED TO PROPOSE DECK AS PER PLAN. NO CHANGE IN USE OR OCCUPANCY
Q00945646-I1
11/22/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
11/20/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFoundationPermit IssuedDFE CONTRACTOR LLC06/12/2024
BISOTISSUEDPRO CUSTOM SOLAR LLC08/10/2022
BISPLISSUEDZ.W. PLBG & HTG CORP09/23/2003
BIS—ISSUEDJ&F QUALITY CONTRACTING08/11/2003
2 projects · most recent 08/25/2023
General Wiring
FiledStatusContractorScope
08/25/2023Permit IssuedRELIANT POWER SYSTEMS LLCGeneral Wiring
08/26/2022CompleteISLAND ELECTRIC CORP—
1 project · most recent 08/17/2025
Concrete Wood
FiledStatusContractorScope
08/17/2025Permit IssuedDFE CONTRACTOR LLCConcrete, Wood
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
11/22/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
11/20/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 36
DateRequirementInspectorRole
08/18/2025Post-installed AnchorsAlbert Munozspecial
08/18/2025Fenestration areasMUZAFFAR JAMALenergy_progress
08/18/2025Fenestration air leakageMUZAFFAR JAMALenergy_progress
08/18/2025Insulation placement and R valuesMUZAFFAR JAMALenergy_progress
08/18/2025Fenestration and door U-factor and product ratingsMUZAFFAR JAMALenergy_progress
08/18/2025Energy Code Compliance InspectionsAlbert Munozprogress
08/18/2025FinalAlbert Munozprogress
08/18/2025Structural Wood FrameAlbert Munozprogress
08/18/2025PreliminaryAlbert Munozprogress
08/18/2025Footing and FoundationAlbert Munozprogress
08/18/2025Concrete - Cast-In-PlaceMUZAFFAR JAMALspecial
08/18/2025Structural Stability – Alterations of existing buildingsMUZAFFAR JAMALspecial
07/16/2025Fenestration and door U-factor and product ratingsMUZAFFAR JAMALenergy_progress
07/16/2025Concrete - Cast-In-PlaceMUZAFFAR JAMALspecial
07/16/2025Post-installed AnchorsAlbert Munozspecial
07/16/2025Structural Stability – Alterations of existing buildingsMUZAFFAR JAMALspecial
07/16/2025Energy Code Compliance InspectionsAlbert Munozprogress
07/16/2025FinalAlbert Munozprogress
07/16/2025Footing and FoundationAlbert Munozprogress
07/16/2025PreliminaryAlbert Munozprogress
07/16/2025Structural Wood FrameAlbert Munozprogress
07/16/2025Fenestration air leakageMUZAFFAR JAMALenergy_progress
07/16/2025Fenestration areasMUZAFFAR JAMALenergy_progress
07/16/2025Insulation placement and R valuesMUZAFFAR JAMALenergy_progress
07/01/2024Concrete - Cast-In-PlaceMUZAFFAR JAMALspecial
Latest 25 of 36.
▾Documents — 69 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/22/2026Q00945646-I1Request digital key ↗
08/22/2026Q00945646-P1Request digital key ↗
08/22/2026Q00945646-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits9
▸BISPLAN / WORK APPROVAL APPLICATION7
05/07/2025440737712Open ↗
02/10/2025440737712Open ↗
02/06/2025440737712Open ↗
Showing 3 of 7 on file for this type
▸BISWORK PERMIT APPLICATION1
08/10/2022440737712Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
02/11/2025440737712Open ↗
▸Seals & Professional Certifications33
▸DOB NOWProgress Inspector Seal & Signature18
09/01/2026Q00945646-P3Open ↗
09/01/2026Q00945646-P3Open ↗
09/01/2026Q00945646-P3Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/01/2026Q00945646-P3Open ↗
09/01/2026Q00945646-P3Open ↗
09/01/2026Q00945646-P3Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/22/2026Q00945646-I1Open ↗
08/22/2026Q00945646-P1Open ↗
08/13/2026Q00945646-P2Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
08/09/2022440737712Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
08/10/2022440737712Open ↗
▸Safety & Tenant Protection1
▸BISTPP1: TENANT PROTECTION PLAN1
08/10/2022440737712Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/22/2026Q00945646-I1Open ↗
08/22/2026Q00945646-P1Open ↗
08/22/2026Q00945646-P2Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
08/09/2022440737712Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
02/14/2025440737712Open ↗
08/09/2022440737712Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/14/2025440737712Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
08/09/2022440737712Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
02/14/2025440737712Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
02/14/2025440737712Open ↗
08/09/2022440737712Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
02/19/2025440737712Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
02/19/2025440737712Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
08/09/2022440737712Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
02/14/2025440737712Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION5
06/26/2024440737712Open ↗
04/16/2024440737712Open ↗
11/06/2023440737712Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
08/09/2022440737712Open ↗