| Owner | Filings | Most Recent |
|---|---|---|
| STEEL CONSTRUCTION | 4 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| HAYM S. GROSS, ARCHITECT | 1 | 10/16/2025 |
| MJE PROFESSIONAL SERVICES | 1 | 10/03/2025 |
| J&R DESIGN AND INSPECTION CORP. | 4 | 06/12/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| HIGH QUALITY 338 | 2 | 03/21/2026 |
| BRITZ ENTERPRISES INC. | 2 | 03/21/2026 |
| SNR EXPEDITING DESIGN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HIGH QUALITY CONSTRUCTION | General Contractor | 2 | 03/21/2026 |
| RIKE ASSOCIATES INC | General Contractor | 1 | 04/09/2026 |
| STEEL CONSTRUCTION LLC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RIKE TECH ASSOCIATES LLC | 2965 | 1 | 10/16/2025 |
| J&R DESIGN AND INSPECTION | 6637 | 3 | 10/27/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | RIKE ASSOCIATES INC | 10/24/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | STEEL CONSTRUCTION LLC | 10/06/2025 |
| DOB NOW | General Construction | Signed-off | HIGH QUALITY CONSTRUCTION | 05/27/2022 |
| BIS | EQ | ISSUED | DLC DEVELOPMENT CORP | 01/03/2019 |
| BIS | SP | ISSUED | QMB PLUMBING & HTG INC | 02/12/2013 |
| BIS | PL | ISSUED | QMB PLUMBING & HEATING INC | 02/12/2013 |
| BIS | SP | ISSUED | QMB PLUMBING & HTG INC | 11/02/2009 |
| BIS | PL | ISSUED | QMB PLUMBING & HEATING INC | 11/02/2009 |
| BIS | EQ | ISSUED | AMERICAN SCAFFOLDING PARTS CORP | 06/29/1998 |
| BIS | OT | ISSUED | AMERICAN SCAFFOLDING PARTS CORP | 06/29/1998 |
| BIS | PL | ISSUED | KIN CHI PLUMBING & HEATING CORP | 10/26/1994 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/07/2025 | Complete | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/03/2025 | Signed-off | STEEL CONSTRUCTION LLC | Sidewalk Shed |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/28/2022 | Final | Robert Truskosky | progress |
| 10/28/2022 | Fire-Resistance Rated Construction | Robert Truskosky | progress |
| 10/28/2022 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 10/28/2022 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 10/27/2022 | Final | Robert Truskosky | progress |
| 10/27/2022 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 10/27/2022 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 10/27/2022 | Fire-Resistance Rated Construction | Robert Truskosky | progress |
| 08/30/2022 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 08/30/2022 | Fire-Resistance Rated Construction | Robert Truskosky | progress |
| 08/30/2022 | Final | Robert Truskosky | progress |
| 08/30/2022 | Energy Code Compliance Inspections | Robert Truskosky | progress |