| Owner | Filings | Most Recent |
|---|---|---|
| JBMA LLC | 2 | 09/12/2026 |
| CEPRINE CONSTRUCTION | 5 | 03/22/2026 |
| NEW YORK CITY PRIME | 5 | 03/22/2026 |
| 772 PARK AVE CORP BHS | 9 | 03/22/2026 |
| 772 PARK AVE CORP BHS C77 | 1 | 03/22/2026 |
| A M & G WATERPROOFING LLC | 1 | 03/22/2026 |
| BROWN HARRIS STEVENS | 24 | 03/22/2026 |
| TO OWNER OF 770 PARK AVE | 2 | 03/22/2026 |
| CHARTER COMMUNICATIONS | 1 | 03/22/2026 |
| 770 PARK AVENUE | 96 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RIGID STRUCTURAL DESIGN, LLC | 1 | 06/18/2026 |
| JOHN B MURRAY ARCHITECT, LLC | 12 | 06/12/2026 |
| CES ENGINEERING LLC | 9 | 06/12/2026 |
| RJD ENGINEERING LLC | 2 | 04/14/2026 |
| JOSHUA BRANDFONBRENER ARCHITECT | 3 | 04/09/2026 |
| HAGE ENGINEERING PC | 5 | 05/20/2025 |
| KZ ENGINEERING, P.C | 4 | 04/23/2025 |
| MIDTOWN PRESERVATION | 2 | 03/04/2025 |
| VOLUME SPACE CONSULTING INC. | 1 | 09/05/2024 |
| WELLWORTH CONSULTING LLC | 1 | 08/12/2024 |
| HANINGTON ENGINEERING CONSULTANTS | 4 | 06/09/2023 |
| T.P. GREER ARCHITECTS | 2 | 05/15/2023 |
| KENDALL ENGINEERING PC | 2 | 12/16/2022 |
| TOHFAZ UDDIN PE PC | 6 | 12/14/2022 |
| URBAN INTEGRATIONS | 3 | 09/28/2022 |
| BARRY BERG ARCHITECT PLLC | 2 | 04/07/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| OUTSOURCE CONSULTANTS, INC. | 2 | 03/21/2026 |
| J CALLAHAN CONSULTING | 54 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 6 | 03/21/2026 |
| SPRING SCAFFOLDING LLC | 10 | 03/21/2026 |
| MIDTOWN PRESERVATION ARCHITECTURE | 4 | 03/21/2026 |
| UNITED SAFETY CONSULTANTS | 3 | 03/21/2026 |
| BODNAR ARCHITECTURE P C | 8 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 2 | 03/21/2026 |
| GREEN STUDIO | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PETER COSOLA INC | General Contractor | 24 | 07/08/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 22 | 07/08/2026 |
| WEST NEW YORK RESTORATION OF CT | General Contractor | 12 | 09/25/2026 |
| S. DONADIC INC | General Contractor | 7 | 07/08/2026 |
| CEPRINE CONSTRUCTION INC | General Contractor | 5 | 09/12/2026 |
| SKYLINE RESTORATION INC | General Contractor | 5 | 07/08/2026 |
| DONATO PLUMBING, INC | Plumbing | 4 | 07/08/2026 |
| TACONIC BUILDERS INC | General Contractor | 4 | 03/21/2026 |
| NEW YORK CITY PRIME CORP | General Contractor | 3 | 03/21/2026 |
| HOBBS, INC | General Contractor | 3 | 03/21/2026 |
| R.J.C. MECHANICAL CORP | Plumbing | 2 | 07/08/2026 |
| HI-TECH WIRING ELECL SVCS | Electrical | 2 | 03/22/2026 |
| MODERN TREND ELECL CONTRG | Electrical | 2 | 03/22/2026 |
| WARREN OSTROFF | Electrical | 2 | 03/21/2026 |
| WARREN OSTROFF ELEC., INC | Electrical | 2 | 03/22/2026 |
| LIEBHABER COMPANY INC | General Contractor | 2 | 06/28/2026 |
| TCM CORPORATION | General Contractor | 2 | 06/28/2026 |
| VELLA INTERIORS INC | General Contractor | 2 | 08/14/2026 |
| MASTER 2 PLBG & HTG INC | Plumbing | 1 | 08/05/2026 |
| FINTAN MURRAY | Electrical | 1 | 03/21/2026 |
| ROBERT CHIMENTI | Electrical | 1 | 03/21/2026 |
| P & Z ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| IMPACT PLUMBING INC | Plumbing | 1 | 06/27/2026 |
| ARISTA AIR CONDITIONING CORP | General Contractor | 1 | 07/08/2026 |
| ROBERT CHIMENTI | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MEP INSPECTIONS, INC | 1102 | 17 | 04/14/2026 |
| BEYOND ARCH LLC | 3600 | 3 | 04/09/2026 |
| KZ ENGINEERING, P.C. | 4665 | 3 | 02/06/2026 |
| CHEN ENGINEERING SERVICES | 1826 | 5 | 05/20/2025 |
| MIDTOWN PRESERVATION ARCH | 2634 | 1 | 03/04/2025 |
| OUTSOURCE SPECIAL INSPECT | 2827 | 1 | 05/10/2023 |
| KENDALL ENGINEERING PC | 4154 | 2 | 12/16/2022 |
| METRIC CONSULTING AND INS | 1803 | 2 | 06/08/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | WEST NEW YORK RESTORATION OF CT | 09/24/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | CEPRINE CONSTRUCTION INC | 09/10/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | VELLA INTERIORS INC | 08/13/2026 |
| DOB NOW | Plumbing | Permit Issued | MASTER 2 PLBG & HTG INC | 08/04/2026 |
| DOB NOW | General Construction | Permit Issued | VELLA INTERIORS INC | 07/20/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | WEST NEW YORK RESTORATION OF CT | 06/30/2026 |
| DOB NOW | Plumbing | Permit Issued | IMPACT PLUMBING INC | 06/23/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | LIEBHABER COMPANY INC | 06/22/2026 |
| DOB NOW | General Construction | Permit Issued | LIEBHABER COMPANY INC | 06/22/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | CEPRINE CONSTRUCTION INC | 06/18/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | TCM CORPORATION | 05/22/2026 |
| DOB NOW | General Construction | Permit Issued | TCM CORPORATION | 05/22/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | A. PETER LUGER CONST INC | 03/31/2026 |
| DOB NOW | General Construction | Signed-off | A. PETER LUGER CONST INC | 03/13/2026 |
| DOB NOW | General Construction | Signed-off | SAPOL CONSTRUCTION LLC | 09/18/2025 |
| DOB NOW | Structural | Signed-off | SAPOL CONSTRUCTION LLC | 09/17/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | WEST NEW YORK RESTORATION | 09/10/2025 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 07/03/2025 |
| DOB NOW | Mechanical Systems | Signed-off | SAPOL CONSTRUCTION LLC | 07/01/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | A. PETER LUGER CONST INC | 04/28/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | A. PETER LUGER CONST INC | 04/24/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | A. PETER LUGER CONST INC | 04/24/2025 |
| DOB NOW | General Construction | Signed-off | A. PETER LUGER CONST INC | 04/21/2025 |
| DOB NOW | General Construction | Signed-off | A. PETER LUGER CONST INC | 04/14/2025 |
| DOB NOW | Structural | Signed-off | SAPOL CONSTRUCTION LLC | 09/23/2024 |
| DOB NOW | General Construction | Signed-off | SAPOL CONSTRUCTION LLC | 09/23/2024 |
| DOB NOW | Supported Scaffold | Signed-off | NEW YORK CITY PRIME CORP | 09/06/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SPRING SCAFFOLDING LLC | 08/23/2024 |
| DOB NOW | Structural | Signed-off | SAPOL CONSTRUCTION LLC | 08/22/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | SPRING SCAFFOLDING LLC | 08/12/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | SKYTRAC ACCESS GROUP LLC | 07/30/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SAPOL CONSTRUCTION LLC | 07/10/2024 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 07/05/2024 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 06/04/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SPRING SCAFFOLDING LLC | 09/21/2023 |
| DOB NOW | Supported Scaffold | Signed-off | SPRING SCAFFOLDING LLC | 06/02/2023 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 05/24/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | ARISTA AIR CONDITIONING C | 05/23/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | HOBBS, INC | 05/19/2023 |
| DOB NOW | General Construction | Signed-off | PETER COSOLA INC | 03/10/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/12/2026 | — | — | Air Conditioning Systems | Cooling National Comfort NCP4244000B 24,000 BTU · Condensing Unit ×3 NCP4184000B 18,000 BTU · Condensing Unit ×2 |
| 04/14/2026 | Permit Issued | VELLA INTERIORS INC | Air Conditioning Systems, Heating and Air Conditioning Systems | Cooling National Comfort 30HX00X2CB 2 tons · Fan Coil Indoor ×2 Carrier FT5ANXB24 2 tons · Fan Coil Indoor ×1 Heat / Cool National Comfort NCP5304000A-D1 26,800 BTU · Condensing Unit ×3 NCP5184000A-D1 18,600 BTU · Condensing Unit ×1 NCP5244000A-D1 23,600 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/14/2026 | Permit Issued | MASTER 2 PLBG & HTG INC | Gas, Water/Sanitary |
| 08/03/2023 | — | — | Gas, Water/Sanitary |
| 07/29/2021 | Permit Issued | R.J.C. MECHANICAL CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/22/2026 | Permit Issued | AVALON ELECTRIC CORP. | General Wiring |
| 06/02/2026 | Permit Issued | MICHAEL BROS. ELECT. CORP | General Wiring |
| 07/11/2025 | Complete | ROBERT CHIMENTI | 2 meters, 1 new_meters |
| 05/14/2025 | Complete | WARREN OSTROFF ELEC., INC | General Wiring |
| 02/18/2025 | Permit Issued | NASH ELECTRIC SERVICES IN | — |
| 08/14/2024 | Complete | TOP SHELF ELECTRIC CORP | — |
| 06/11/2024 | Complete | P & Z ELECTRIC CORP | — |
| 05/28/2024 | Complete | P & Z ELECTRIC CORP | — |
| 05/16/2024 | Complete | THE METRO GROUP ELECTRIC | General Wiring |
| 07/25/2023 | Complete | WARREN OSTROFF ELEC., INC | — |
| 05/22/2023 | Complete | HI-TECH WIRING ELECL SVCS | General Wiring |
| 05/17/2022 | Complete | APOLLO ELECTRIC INC. | General Wiring |
| 05/13/2022 | Complete | APOLLO ELECTRIC INC. | — |
| 05/12/2022 | Complete | AE ELECTRIC INC | — |
| 01/20/2022 | Complete | CENTENNIAL ELEVATOR INDUS | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2026 | Permit Issued | CEPRINE CONSTRUCTION INC | Sidewalk Shed |
| 04/23/2025 | Permit Issued | WEST NEW YORK RESTORATION | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/06/2026 | Permit Issued | WEST NEW YORK RESTORATION | Suspended Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/06/2026 | Permit Issued | WEST NEW YORK RESTORATION | Suspended Scaffold (SC) |
| 05/30/2024 | — | — | Suspended Scaffold (SC) |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/30/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/09/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/05/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/08/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 12/08/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 11/20/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 11/20/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 11/14/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 11/14/2025 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 10/07/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/27/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/27/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/06/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/28/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/01/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/30/2023 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 05/22/2023 | Fail-Final PL - More than 10 Requested Floors | Fail | View ↗ |
| 11/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/14/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/03/2022 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 06/10/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/01/2021 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/17/2021 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/10/2026 | Tenant Protection Plan Compliance | — | special |
| 06/10/2026 | Final | — | progress |
| 04/09/2026 | HVAC-R and service water heating system controls | josh brandfonbrener | energy_progress |
| 04/09/2026 | HVAC-R and service water piping design and insulation | josh brandfonbrener | energy_progress |
| 04/09/2026 | Maintenance information | josh brandfonbrener | energy_progress |
| 04/09/2026 | HVAC-R and service water heating equipment | josh brandfonbrener | energy_progress |
| 04/09/2026 | Shutoff dampers | josh brandfonbrener | energy_progress |
| 04/09/2026 | Duct leakage testing, insulation and design | josh brandfonbrener | energy_progress |
| 04/08/2026 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |
| 04/03/2026 | Final | Nicolas Crosetto | progress |
| 04/03/2026 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |
| 04/03/2026 | Final | Nicolas Crosetto | progress |
| 04/03/2026 | Fire-Resistance Rated Construction | Nicolas Crosetto | progress |
| 04/03/2026 | Post-installed Anchors | Nicolas Crosetto | special |
| 04/03/2026 | Mechanical Systems | Nicolas Crosetto | special |
| 02/12/2026 | Post-installed Anchors | Karol Zdancewicz | special |
| 02/12/2026 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 02/05/2026 | Post-installed Anchors | Karol Zdancewicz | special |
| 02/05/2026 | Tenant Protection Plan Compliance | Hackjong Choi | special |
| 02/05/2026 | Fire-Resistant Penetrations and Joints | Hackjong Choi | special |
| 02/05/2026 | Alternative Materials - OTCR Buildings Bulletin Number | Karol Zdancewicz | special |
| 02/05/2026 | Final | josh brandfonbrener | progress |
| 02/05/2026 | Tenant Protection Plan Compliance | Hackjong Choi | special |
| 02/05/2026 | Mechanical Systems | Hackjong Choi | special |
| 10/17/2025 | Fire-Resistant Penetrations and Joints | Nicolas Crosetto | special |