ECB04/14/2026ATOI OBSERVED NON-CONFORMING CONSTRUCTION FENCE. FENCE TO BE INSTALLED AROUND ENTIRE SITE ALONG 39TH STREETB & 8TH AVE FENCE. FENCE NOT INSTALLED TO SECURE ENTIRE SITE. ADDITIONAL 6 FT HIGH WOODEN STUDS EXTENDE$2K due
ECB04/14/2026ATOI OBSERVED WORK WITHOUT A PERMIT. UNPERMITTED/UNAPPROVED SIGNS INSTALLED AT FACADE OF BUILDING. 4 SIGNS FACING 8TH AVE AND 2 SIGNS FACING 39 STREET DISPLAYING "M2 PARTY K", OBTAIN PERMIT$2K due
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION
DOB03/16/2020VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
DOB03/16/2020VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
DOB08/16/1993V-DOB VIOLATION - ACTIVE