← Back
Two family brick
776 BARTHOLDI STREET
BRONX · BIN 2056354
💬 Discuss this project
1965Year Built
2Stories
B1Building Class
R4Zoning
2,100 sfGross Floor Area
2Units
Two family brick · 2,130 sf lot · 0.99 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction3p · 1 filing · 12 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/06/2024$714K—Private party → Private party$340/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC202/26/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOLAR CONTRACTING LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854202/26/2026
Building Lifecycle
All (14)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (10)
05/15/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDIN
X01348172-I1
03/18/2026
Permit issued — Solar
X01348172-I1-SL
03/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
03/12/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
03/12/2026
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
03/12/2026
Special inspection requirement — Final
TOM PETERSEN
03/12/2026
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
02/26/2026
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDIN
X01348172-P1
02/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
02/26/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
02/26/2026
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
02/26/2026
Special inspection requirement — Final
TOM PETERSEN
02/26/2026
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
01/21/2026
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDIN
X01348172-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSOLAR CONTRACTING LLC03/18/2026
2 projects · most recent 05/05/2026
FiledStatusContractorScope
05/05/2026CompleteSOLAR ELEC CONTRACTNG LLC2 meters
04/14/2025Permit IssuedL J ELEC'L SERV. INC.2 meters, 2 new_meters
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
03/12/2026Fire-Resistant Penetrations and JointsTOM PETERSENspecial
03/12/2026Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
03/12/2026Energy Code Compliance InspectionsTOM PETERSENprogress
03/12/2026FinalTOM PETERSENprogress
03/12/2026Air barrier - visual inspectionTOM PETERSENenergy_progress
02/26/2026Fire-Resistant Penetrations and JointsTOM PETERSENspecial
02/26/2026Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
02/26/2026Energy Code Compliance InspectionsTOM PETERSENprogress
02/26/2026FinalTOM PETERSENprogress
02/26/2026Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 12 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026X01348172-I1Request digital key ↗
08/17/2026X01348172-P1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
08/31/2026X01348172-I1Open ↗
08/31/2026X01348172-I1Open ↗
08/31/2026X01348172-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026X01348172-P1Open ↗
08/17/2026X01348172-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/31/2026X01348172-I1Open ↗
08/31/2026X01348172-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026X01348172-P1Open ↗
08/17/2026X01348172-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/17/2026X01348172-I1Open ↗