← Back
One family attached or semi-detached
78 TEHAMA STREET
BROOKLYN · Kensington · BIN 3123703
💬 Discuss this project
1910Year Built
2Stories
A5Building Class
R5Zoning
1,360 sfGross Floor Area
1Units
2 Open Violations 1 unresolved · 1 paperwork only ▸FDNY Report ↗
One family attached or semi-detached · 1,900 sf lot · 0.72 FAR built · Flood zone X
Locations of Work
Mechanical
Basement1p · 1 filing · 10 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/05/2014$650K—Private party → Private party$478/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BRYCE TAYLOR, ARCHITECT106/09/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
OLIVA THOMASElectrical103/21/2026
RIVIERA ELECT BROS CORPElectrical103/22/2026
?THOMAS OLIVAElectrical103/21/2026
ARNICA HEATING & AIR CONDGeneral Contractor104/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BRYCE TAYLOR, ARCHITECT8102106/09/2025
Building Lifecycle
All (15)Filed (1)Permit Issued (1)Signed Off (1)Violation (3)Objection (2)Special Inspection (7)
10/07/2025
Signed off — Alteration
Install new HVAC system (heat pump).
B01230379-I1
09/09/2025
Permit issued — Mechanical Systems
B01230379-I1-MS
06/24/2025
Objection resolved — Addressed
06/12/2025
Objection raised — Zoning
06/09/2025
Filed — Alteration
Install new HVAC system (heat pump).
B01230379-I1
06/09/2025
Special inspection requirement — HVAC-R and service water heating system controls
Bryce Taylor
06/09/2025
Special inspection requirement — HVAC-R and service water heating equipment
Bryce Taylor
06/09/2025
Special inspection requirement — Heating Systems
Bryce Taylor
06/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Bryce Taylor
06/09/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Bryce Taylor
05/22/2025
Special inspection requirement — Final
Bryce Taylor
05/22/2025
Special inspection requirement — Mechanical Systems
Bryce Taylor
02/11/2025
Violation issued (ECB, open)
Construction
02/13/2024
Violation issued (ECB, open)
Construction
01/19/2006
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offARNICA HEATING AIR COND09/09/2025
BISPLISSUEDWASOFF PLBG & UTILITY CO10/19/2017
BIS—ISSUED901 GREEN AVENUE BUILDERS08/09/2017
4 projects · most recent 08/12/2026
General Wiring
FiledStatusContractorScope
08/12/2026CompleteRIVIERA ELECT BROS CORPGeneral Wiring
05/14/2025CompleteRIVIERA ELECT BROS CORPGeneral Wiring
11/11/2024CompleteRIVIERA ELECT BROS CORPGeneral Wiring
08/16/2019CompleteBROOKYLN SOLARWORKS, LLC—
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
06/09/2025HVAC-R and service water heating system controlsBryce Taylorenergy_progress
06/09/2025HVAC-R and service water heating equipmentBryce Taylorenergy_progress
06/09/2025Heating SystemsBryce Taylorspecial
06/09/2025Fire-Resistant Penetrations and JointsBryce Taylorspecial
06/09/2025HVAC-R and service water piping design and insulationBryce Taylorenergy_progress
05/22/2025FinalBryce Taylorprogress
05/22/2025Mechanical SystemsBryce Taylorspecial
▾Documents — 82 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026B01230379-I1Request digital key ↗
▸Applications & Permits14
▸BISPLAN / WORK APPROVAL APPLICATION10
10/22/2025321207537Open ↗
05/22/2024321207537Open ↗
04/11/2024321207537Open ↗
Showing 3 of 10 on file for this type
▸BISWORK PERMIT APPLICATION3
08/21/2019340689669Open ↗
10/23/2017321207537Open ↗
08/10/2017321207537Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
04/10/2024321207537Open ↗
▸Zoning, Tax Lot & Property Records6
▸BISADDRESS: NEW HOUSE NUMBER APPROVED2
06/12/2024321207537Open ↗
03/29/2017321207537Open ↗
▸BISZONING DIAGRAM2
05/14/2024321207537Open ↗
06/07/2017321207537Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
03/29/2017321207537Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
03/29/2017321207537Open ↗
▸Seals & Professional Certifications14
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
08/03/2017321207537Open ↗
03/29/2017321207537Open ↗
03/29/2017321207537Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
08/24/2026B01230379-I1Open ↗
08/24/2026B01230379-I1Open ↗
08/24/2026B01230379-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/24/2026B01230379-I1Open ↗
08/24/2026B01230379-I1Open ↗
08/24/2026B01230379-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
07/30/2019340689669Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/21/2026B01230379-I1Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
08/18/2015321207537Open ↗
▸BISSCHEDULE B - PLUMBING1
04/10/2024321207537Open ↗
▸Safety & Tenant Protection7
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE5
08/03/2017321207537Open ↗
08/03/2017321207537Open ↗
08/03/2017321207537Open ↗
Showing 3 of 5 on file for this type
▸BISSTREET TREE CHECKLIST1
08/18/2015321207537Open ↗
▸BISTenant Protection Plan and Notes1
07/30/2019340689669Open ↗
▸Environmental & Asbestos3
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
07/30/2019340689669Open ↗
08/18/2015321207537Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/21/2026B01230379-I1Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
11/14/2019340689669Open ↗
07/30/2019340689669Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
03/29/2017321207537Open ↗
08/18/2015321207537Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/21/2024321207537Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
11/21/2024321207537Open ↗
▸BISFENESTRATION AREAS1
11/21/2024321207537Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
07/30/2019340689669Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
11/21/2024321207537Open ↗
▸BISLIGHTING IN DWELLING UNITS1
11/21/2024321207537Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
11/21/2024321207537Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
11/14/2019340689669Open ↗
▸BISFENESTRATION AIR LEAKAGE1
11/21/2024321207537Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
11/21/2024321207537Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
11/14/2019340689669Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY2
11/14/2019340689669Open ↗
07/30/2019340689669Open ↗
▸BISBORINGS / TEST PITS (TR-4) 27-7201
03/29/2017321207537Open ↗
▸Approvals, Objections & Sign-offs5
▸BISSCHEDULE A - OCCUPANCY / USE2
04/10/2024321207537Open ↗
08/18/2015321207537Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
11/14/2019340689669Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
04/05/2017321207537Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
11/14/2019340689669Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT4
11/14/2019340689669Open ↗
07/30/2019340689669Open ↗
03/29/2017321207537Open ↗
Showing 3 of 4 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE1
08/03/2017321207537Open ↗
▸Filing & Intake Forms6
▸BISADDITIONAL INFORMATION3
05/14/2024321207537Open ↗
08/20/2019340689669Open ↗
08/02/2017321207537Open ↗
▸BISEFILING COVER SHEET2
08/18/2015321207537Open ↗
08/18/2015321207537Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
07/30/2019340689669Open ↗
▸Other Documents1
▸BISPLOT DIAGRAM1
08/18/2015321207537Open ↗