| Owner | Filings | Most Recent |
|---|---|---|
| DSNY | 19 | 10/20/2026 |
| NYC Department of Design and Construction | 5 | 08/05/2026 |
| DOS | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Ramboll | 4 | 09/03/2026 |
| Reuther Bowen | 1 | 04/20/2026 |
| Kouzmanoff Bainton Architects | 4 | 04/13/2026 |
| Gannett Fleming | 1 | 01/13/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Nyccode | 8 | 03/21/2026 |
| P.wolfe Consultants | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Dynamic US | General Contractor | 9 | 10/20/2026 |
| Tully Construction Co | General Contractor | 4 | 03/22/2026 |
| Aventura Construction | General Contractor | 2 | 08/05/2026 |
| Dynamic Electric System | Electrical | 1 | 03/21/2026 |
| Kleinberg Electric | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Joadem | 4350 | 7 | 09/03/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | Dynamic US | 10/19/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Dynamic US | 10/07/2026 |
| DOB NOW | Solar | Permit Issued | Dynamic US | 09/09/2026 |
| DOB NOW | General Construction | Signed-off | Aventura Construction | 08/04/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Dynamic US | 06/25/2026 |
| DOB NOW | General Construction | Permit Issued | Dynamic US | 06/22/2026 |
| DOB NOW | General Construction | Permit Issued | Dynamic US | 04/29/2026 |
| DOB NOW | Structural | Permit Issued | Dynamic US | 04/29/2026 |
| DOB NOW | General Construction | Signed-off | Aventura Construction | 03/16/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Dynamic US | 10/14/2025 |
| DOB NOW | General Construction | Permit Issued | Dynamic US | 09/23/2025 |
| BIS | FP | ISSUED | Almar Plumbing & Heating | 06/18/2013 |
| BIS | FS | ISSUED | Almar Plumbing & Heating | 05/17/2013 |
| BIS | OT | ISSUED | Tully Construction Co | 06/18/2012 |
| BIS | FP | ISSUED | Almar Plumbing & Heating | 04/23/2012 |
| BIS | FS | ISSUED | Almar Plumbing & Heating | 04/23/2012 |
| BIS | EQ | ISSUED | Tully Construction Co | 04/10/2012 |
| BIS | — | ISSUED | Tully Construction Co | 05/25/2011 |
| BIS | EQ | ISSUED | Tully Construction Co | 04/06/2011 |
| BIS | PL | ISSUED | Almar Plumbing & Heating | 09/03/2010 |
| BIS | — | ISSUED | Tully Construction Co | 08/10/2010 |
| BIS | SD | ISSUED | Almar Plumbing & Heating | 05/19/2010 |
| BIS | — | ISSUED | Tully Construction Co | 05/06/2010 |
| BIS | EQ | ISSUED | Tully Construction Co | 03/23/2010 |
| BIS | SP | ISSUED | A & F Fire Protection Co | 10/06/2009 |
| BIS | PL | ISSUED | Almar Plumbing & Heating | 08/19/2009 |
| BIS | — | ISSUED | Tully Construction Co | 06/29/2009 |
| BIS | EQ | ISSUED | Tully Construction Co | 06/19/2009 |
| BIS | SP | ISSUED | A & F Fire Protection Co | 09/30/2008 |
| BIS | PL | ISSUED | Almar Plumbing & Heating | 08/13/2008 |
| BIS | SD | ISSUED | Almar Plumbing & Heating | 05/20/2008 |
| BIS | SP | ISSUED | A & F Fire Protection Co | 09/06/2007 |
| BIS | SD | ISSUED | Almar Plumbing & Heating | 04/03/2007 |
| BIS | PL | ISSUED | Almar Plumbing & Heating | 08/21/2006 |
| BIS | SD | ISSUED | Almar Plumbing & Heating | 04/05/2006 |
| BIS | PL | ISSUED | Almar Plumbing & Heating | 09/06/2005 |
| BIS | — | ISSUED | Tully Construction Co | 07/25/2005 |
| BIS | PL | ISSUED | Almar Plumbing & Heating | 09/14/2004 |
| BIS | — | ISSUED | Tully Construction Co | 08/04/2004 |
| BIS | — | ISSUED | Tully Construction Co | 07/07/2004 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/20/2026 | Permit Issued | Dynamic US | Heating Systems, Ventilation Systems | Heating Daikin 0AH061GHCM 30,000 CFM · Rooftop Unit ×4 Ventilation Daikin 0AH039GHCM 30,000 CFM · Exhaust Fan ×16 0AH036GHCM 20,000 CFM · Exhaust Fan ×8 0AH034GHCM 15,000 CFM · Exhaust Fan ×1 Poweredaire Steam Heated Air Curtains (EHD & TFD) 352,800 BTU · Air Curtain ×12 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2026 | Complete | Hunter Electric | General Wiring |
| 04/14/2026 | Permit Issued | Kleinberg Electric | HVAC Wiring |
| 01/15/2026 | Permit Issued | Kleinberg Electric | — |
| 10/15/2025 | Permit Issued | Dynamic Electric System | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/20/2026 | Permit Issued | Dynamic US | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2026 | Permit Issued | Dynamic US | 389 panels, 196.1 kw, 37,235 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/03/2026 | Fire-Resistant Penetrations and Joints | OLULADE ADEMOKUN | special |
| 08/03/2026 | Final | OLULADE ADEMOKUN | progress |
| 08/03/2026 | Energy Code Compliance Inspections | OLULADE ADEMOKUN | progress |
| 03/06/2026 | Insulation placement and R values | OLULADE ADEMOKUN | energy_progress |
| 03/06/2026 | Energy Code Compliance Inspections | OLULADE ADEMOKUN | progress |
| 12/22/2025 | Structural Steel - Details | OLULADE ADEMOKUN | special |
| 12/22/2025 | Structural Steel - High Strength Bolting | OLULADE ADEMOKUN | special |
| 12/22/2025 | Structural Steel - Welding | OLULADE ADEMOKUN | special |
| 12/16/2025 | Final | OLULADE ADEMOKUN | progress |
| 12/15/2025 | Final | OLULADE ADEMOKUN | progress |
| 12/15/2025 | Final | OLULADE ADEMOKUN | progress |
| 10/07/2025 | Final | OLULADE ADEMOKUN | progress |
| 10/07/2025 | Mechanical Systems | OLULADE ADEMOKUN | special |
| 10/07/2025 | Fire-Resistant Penetrations and Joints | OLULADE ADEMOKUN | special |
| 11/27/2024 | Final | GEORGE GHEBRYAL | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| New York City Department of Sanitation | Government / Civic | Sub-basement, Floors 1–4, Roof | Project M01343976 Project M01333925 Project M01335023 |