| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/11/2024 | Permit Issued | WATERMARK PLUMBING CORP | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/10/2025 | Permit Issued | I.P. ELECTRIC INC | — |
| 10/31/2024 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/24/2024 | Permit Issued | HUNT B CONSTRUCTION INC | Fence |
| Owner | Filings | Most Recent |
|---|---|---|
| HUNT B CONSTRUCTION | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/24/2021 | $845K | — | Private party → Private party | $264/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ARCHITECTURAL CONCEPT | 5 | 02/06/2026 |
| CHUN FENG, ARCHITECT | 1 | 08/20/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| AMERGY SOLAR | 2 | 03/21/2026 |
| ARCHITECTUAL CONCEPT | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HUNT B CONSTRUCTION INC | General Contractor | 10 | 07/28/2026 |
| JASDISH BUILDERS CORP | General Contractor | 3 | 03/21/2026 |
| WATERMARK PLUMBING CORP | Plumbing | 2 | 09/12/2026 |
| AMERGY SOLAR INC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ARCHITECTURAL CONCEPT | 3642 | 3 | 02/06/2026 |
| SQ. ARCH, LLC | 4802 | 1 | 08/20/2025 |
| TRIANGLE INSPECTION & TES | 7495 | 1 | 07/11/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | WATERMARK PLUMBING CORP | 09/10/2026 |
| DOB NOW | General Construction | Permit Issued | HUNT B CONSTRUCTION INC | 07/27/2026 |
| DOB NOW | Structural | Permit Issued | HUNT B CONSTRUCTION INC | 07/24/2026 |
| DOB NOW | Construction Fence | Permit Issued | HUNT B CONSTRUCTION INC | 07/23/2026 |
| DOB NOW | Solar | Permit Issued | AMERGY SOLAR INC | 08/21/2025 |
| DOB NOW | Construction Fence | Permit Issued | JASDISH BUILDERS CORP | 03/24/2025 |
| DOB NOW | Plumbing | Permit Issued | WATERMARK PLUMBING CORP | 02/26/2025 |
| DOB NOW | Foundation | Permit Issued | HUNT B CONSTRUCTION INC | 08/28/2024 |
| DOB NOW | Earth Work | Permit Issued | HUNT B CONSTRUCTION INC | 08/28/2024 |
| DOB NOW | Foundation | Permit Issued | HUNT B CONSTRUCTION INC | 08/27/2024 |
| DOB NOW | Structural | Permit Issued | HUNT B CONSTRUCTION INC | 08/27/2024 |
| DOB NOW | Construction Fence | Permit Issued | HUNT B CONSTRUCTION INC | 06/10/2024 |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/25/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 03/07/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/07/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/07/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/06/2026 | Ventilation and air distribution system | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | HVAC-R and service water heating system controls | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Air barrier - visual inspection | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Interior lighting power | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Protection of exposed foundation insulation | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Electric vehicle service equipment requirements | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | HVAC-R and service water piping design and insulation | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Metering | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Air barrier — testing | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Fenestration air leakage | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Maintenance information | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Duct leakage testing, insulation and design | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Fenestration and door U-factor and product ratings | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Fireplaces | MUZAFFAR JAMAL | energy_progress |
| 02/06/2026 | Concrete - Cast-In-Place | MUZAFFAR JAMAL | special |
| 02/06/2026 | Demolition | MUZAFFAR JAMAL | special |
| 02/06/2026 | Excavations - Sheeting, Shoring, and Bracing | MUZAFFAR JAMAL | special |
| 02/06/2026 | Fire-Resistant Penetrations and Joints | MUZAFFAR JAMAL | special |
| 02/06/2026 | Heating Systems | MUZAFFAR JAMAL | special |
| 02/06/2026 | Masonry | MUZAFFAR JAMAL | special |
| 02/06/2026 | Mechanical Systems | MUZAFFAR JAMAL | special |
| 02/06/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MUZAFFAR JAMAL | special |
| 02/06/2026 | Structural Stability – Alterations of existing buildings | MUZAFFAR JAMAL | special |
| 02/06/2026 | Structural Steel - Details | MUZAFFAR JAMAL | special |
| 02/06/2026 | Structural Steel - High Strength Bolting | MUZAFFAR JAMAL | special |