Two stories - detached, small or mid-size
79 EAST RALEIGH AVENUE
STATEN ISLAND · BIN 5008219
💬 Discuss this project
1920Year Built
2.5Stories
A1Building Class
R2Zoning
1,380 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,600 sf lot · 0.38 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectrical
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofSolar electric array installation5p · 2 filings · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Square Arch105/11/2026
James Stout Architect & Associates101/10/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Sologistics103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Sunpower Corporation, SystemsGeneral Contractor303/21/2026
SolantaGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Sq. Arch4802105/11/2026
James J Stout Architects5913101/10/2024
Building Lifecycle
11/07/2026
Permit expired, never signed off — Solar
The city's record still shows this permit as issued, with no sign-off on its filing
S01400506-I1-SL
05/12/2026
Permit issued — Solar
S01400506-I1-SL
05/11/2026
Filed — Alteration
Installation of solar electric generation system for utility interconnection. No changes being made to use, occupancy, egress, or anything not marked on the planset and supporting documents
S01400506-I1
05/11/2026
Special inspection requirement — Air barrier - visual inspection
Chun Feng
05/11/2026
Special inspection requirement — Post-installed Anchors
Chun Feng
16 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedSolanta05/12/2026
DOB NOWSolarSigned-offSunpower Corporation, Systems01/24/2024
3 projects · most recent 06/19/2026
FiledStatusContractorScope
06/19/2026CompleteSource Electric—
05/11/2026CompleteSource Electric—
01/01/2024CompleteBerger Quality Electrical Con—
1 project · most recent 05/11/2026
FiledStatusContractorScope
05/11/2026Permit IssuedSolanta—
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
05/11/2026Air barrier - visual inspectionChun Fengenergy_progress
05/11/2026Post-installed AnchorsChun Fengspecial
05/11/2026Fire-Resistant Penetrations and JointsChun Fengspecial
05/11/2026Energy Code Compliance InspectionsChun Fengprogress
05/11/2026FinalChun Fengprogress
01/02/2024Fire-Resistant Penetrations and JointsJAMES J STOUTspecial
01/02/2024Structural Stability – Alterations of existing buildingsJAMES J STOUTspecial
01/02/2024Energy Code Compliance InspectionsJAMES J STOUTprogress
01/02/2024FinalJAMES J STOUTprogress
01/02/2024Air barrier - visual inspectionJAMES J STOUTenergy_progress
15 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account