← Back
One story - permanent living quarter
79 KENMORE STREET
STATEN ISLAND · Arden Heights-Rossville · BIN 5076734
💬 Discuss this project
1974Year Built
2Stories
A2Building Class
R3-1Zoning
2,086 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.52 FAR built · Flood zone X
Locations of Work
Electrical
Roof1p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC103/07/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272103/07/2024
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
11/14/2024
Signed off — Alteration
S01006770-I1
03/19/2024
Permit issued — Solar
S01006770-I1-SL
03/07/2024
Filed — Alteration
S01006770-I1
02/16/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
02/16/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
02/16/2024
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
02/16/2024
Special inspection requirement — Final
Walid Abdulla
02/16/2024
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC03/19/2024
1 project · most recent 03/07/2024
FiledStatusContractorScope
03/07/2024CompleteSUNRUN SOLAR ELECTL CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
02/16/2024Fire-Resistant Penetrations and JointsWalid Abdullaspecial
02/16/2024Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
02/16/2024Energy Code Compliance InspectionsWalid Abdullaprogress
02/16/2024FinalWalid Abdullaprogress
02/16/2024Air barrier - visual inspectionWalid Abdullaenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026S01006770-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/23/2026S01006770-I1Open ↗
08/23/2026S01006770-I1Open ↗
08/23/2026S01006770-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/23/2026S01006770-I1Open ↗
08/23/2026S01006770-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01006770-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01006770-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01006770-I1Open ↗