| Owner | Filings | Most Recent |
|---|---|---|
| GREYSTAR | 66 | 07/08/2026 |
| CHELSA 27TH STREET APARTMENTS | 62 | 03/21/2026 |
| GS 800 6TH | 28 | 03/22/2026 |
| EQUITY RESIDENTIAL | 17 | 03/22/2026 |
| CEPRINE CONSTRUCTION | 4 | 07/08/2026 |
| CHEALSEA 27TH ST APARTMENTS | 3 | 03/21/2026 |
| 801 ASSOCIATES | 3 | 03/21/2026 |
| CHELSEA 27TH ST APT | 3 | 03/21/2026 |
| C6829 APARTMENTS LLC CHELSEA | 2 | 03/21/2026 |
| RW DAKE & CO., INC. | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| QWA STUDIO LLC | 4 | 05/09/2025 |
| BASSIRI | 1 | 05/05/2025 |
| ZELTA DESIGN | 5 | 06/30/2023 |
| SHAABAN ENGINEERING, LLC | 7 | 10/26/2022 |
| RIVERSIDE ENGINEERING | 1 | 05/26/2022 |
| JOSE L. PENA,P.E. | 3 | 05/25/2022 |
| SMITH & ARCHITECTS | 1 | 03/14/2022 |
| SRL ASSOCIATES | 1 | 10/06/2021 |
| KZ ENGINEERING, P.C | 3 | 08/05/2021 |
| SYSKA HENNESSY GROUP | 2 | 02/18/2021 |
| ALL CITY ENGINEERING PC | 4 | 05/26/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| KAZAM CONSULTANTS | 14 | 03/21/2026 |
| EPAC BUILDING CONSULTING INC | 10 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 4 | 03/21/2026 |
| LOUIS STRIAR | 6 | 03/21/2026 |
| PROJECT EXPEDITERS CONSULTING CO. | 4 | 03/21/2026 |
| SOL BUILDING CONSULTING SERVICES | 1 | 03/21/2026 |
| ECDESIGN STUDIO | 2 | 03/21/2026 |
| REVIT GROUP | 2 | 03/21/2026 |
| PDG BUILDING CONSULTANTS LLC LLC | 8 | 03/21/2026 |
| SKYLINE ACCESS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SIGNSTAR NYC | Scaffold | 8 | 07/08/2026 |
| CS BRIDGE CORP | General Contractor | 7 | 07/08/2026 |
| BALATON CONSULTING LLC | Scaffold | 7 | 07/08/2026 |
| PACE PLUMBING CORP | Plumbing | 6 | 07/08/2026 |
| ALL PHASE ELEC & SEC TECH | Electrical | 5 | 03/22/2026 |
| REVIT GROUP LLC | General Contractor | 3 | 07/08/2026 |
| GREEN CITY BOX TRANS INC | General Contractor | 2 | 07/08/2026 |
| G. C. PLBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| CLUNE CONSTRUCTION CO LP | General Contractor | 1 | 04/09/2026 |
| PACE PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| ARCO PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| NEW YORK STANDARD MECH CORP | Plumbing | 1 | 07/08/2026 |
| ARCHER CONSULTANTS GROUP | Fire Protection | 1 | 07/08/2026 |
| VARSITY PLBG & HTG INC | Plumbing | 1 | 07/08/2026 |
| XH&RC PLBG AND HTG INC | Plumbing | 1 | 07/08/2026 |
| AGGRESSIVE FIRE PROT LLC | Fire Protection | 1 | 07/08/2026 |
| NEPTUNE SIGNS AWNINGS | Scaffold | 1 | 07/08/2026 |
| BLAKA COOL INC | General Contractor | 1 | 07/08/2026 |
| SRM ELECTRICAL SVC INC | Electrical | 1 | 03/22/2026 |
| CEPRINE CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| CLASSIC BROTHERS CONSTRUC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| QWA STUDIO | 9293 | 4 | 05/09/2025 |
| SHAHRISH SHUVO ENGINEERIN | 8524 | 1 | 05/09/2025 |
| ZELTA INSPECT LLC | 7764 | 4 | 06/30/2023 |
| CROSSCHECK INSPECTION SER | 544 | 1 | 03/14/2022 |
| JOSEPH MARTINES PE, PLLC | 1428 | 2 | 02/18/2021 |
| DELTA TESTING LABS | 687 | 3 | 05/26/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Permit Issued | ARCHER CONSULTANTS GROUP | 04/15/2026 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG & HTG INC | 09/25/2025 |
| DOB NOW | Sign | Signed-off | NEPTUNE SIGNS&AWNINGS INC | 06/24/2025 |
| DOB NOW | Mechanical Systems | Signed-off | GREEN CITY BOX TRANS INC | 06/24/2025 |
| DOB NOW | Plumbing | Signed-off | XH&RC PLBG AND HTG INC | 04/15/2025 |
| DOB NOW | General Construction | Signed-off | GREEN CITY BOX TRANS INC | 04/15/2025 |
| DOB NOW | Plumbing | Permit Issued | G. C. PLBG & HTG INC | 03/11/2025 |
| DOB NOW | Plumbing | Permit Issued | G. C. PLBG & HTG INC | 03/10/2025 |
| DOB NOW | Plumbing | Permit Issued | PACE PLUMBING CORP | 02/16/2024 |
| DOB NOW | Plumbing | Permit Issued | PACE PLUMBING CORP | 08/18/2023 |
| DOB NOW | Plumbing | Permit Issued | PACE PLUMBING CORP | 02/22/2023 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 10/26/2022 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 10/26/2022 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 10/26/2022 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 10/26/2022 |
| DOB NOW | Sprinklers | Permit Issued | MANENGEERING BUREAU, INC | 09/12/2022 |
| DOB NOW | General Construction | Permit Issued | REVIT GROUP LLC | 09/07/2022 |
| DOB NOW | General Construction | Permit Issued | REVIT GROUP LLC | 09/03/2022 |
| DOB NOW | Plumbing | Permit Issued | ARCO PLBG AND HTG INC | 08/24/2022 |
| DOB NOW | Plumbing | Permit Issued | PACE PLUMBING CORP | 08/19/2022 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 05/27/2022 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 05/27/2022 |
| DOB NOW | Sign | Signed-off | SIGNSTAR NYC | 05/27/2022 |
| DOB NOW | General Construction | Permit Issued | REVIT GROUP LLC | 04/06/2022 |
| DOB NOW | Plumbing | Permit Issued | PACE PLUMBING CORP | 03/11/2022 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 01/29/2022 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 01/28/2022 |
| DOB NOW | Sign | Signed-off | NORTH SHORE NEON SIGN CO | 01/28/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CS BRIDGE CORP | 01/05/2022 |
| DOB NOW | Supported Scaffold | Signed-off | CEPRINE CONSTRUCTION INC | 10/07/2021 |
| DOB NOW | Supported Scaffold | Signed-off | CS BRIDGE CORP | 10/04/2021 |
| DOB NOW | Plumbing | Permit Issued | PACE PLUMBING CORP | 09/15/2021 |
| DOB NOW | Mechanical Systems | Signed-off | BLAKA COOL INC | 07/26/2021 |
| DOB NOW | Plumbing | Signed-off | NEW YORK STANDARD MECH CORP | 07/08/2021 |
| DOB NOW | Sign | Permit Issued | SIGNSTAR NYC | 07/01/2021 |
| DOB NOW | Sign | Permit Issued | SIGNSTAR NYC | 06/29/2021 |
| DOB NOW | Sign | Permit Issued | SIGNSTAR NYC | 06/29/2021 |
| DOB NOW | Sign | Permit Issued | SIGNSTAR NYC | 06/29/2021 |
| DOB NOW | Sign | Permit Issued | SIGNSTAR NYC | 06/29/2021 |
| DOB NOW | General Construction | Signed-off | CLASSIC BROTHERS CONSTRUC | 06/17/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/21/2020 | — | — | 12 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/26/2022 | Permit Issued | ARCO PLBG AND HTG INC | Water/Sanitary |
| 05/26/2020 | Permit Issued | G. C. PLBG & HTG INC | Water/Sanitary |
| 03/20/2020 | Permit Issued | VARSITY PLBG & HTG INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2025 | Complete | KJK ELECTRIC INC | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| 08/07/2024 | Complete | ALL PHASE ELEC & SEC TECH | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/20/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/05/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 04/29/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/29/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/29/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/29/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/20/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/03/2025 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 07/02/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/24/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/01/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/25/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/29/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/25/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 07/12/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/16/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/20/2022 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/15/2022 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/09/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/17/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/04/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/20/2021 | Pass-Final Construction Permit Withdrawal | Pass | View ↗ |
| 10/06/2021 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/08/2025 | Energy Code Compliance Inspections | Kun Wu | progress |
| 05/08/2025 | HVAC-R and service water piping design and insulation | Kun Wu | energy_progress |
| 05/08/2025 | HVAC-R and service water heating system controls | Kun Wu | energy_progress |
| 05/08/2025 | Fire-Resistance Rated Construction | Kun Wu | progress |
| 05/08/2025 | Tenant Protection Plan Compliance | Kun Wu | special |
| 05/08/2025 | HVAC-R and service water heating equipment | Kun Wu | energy_progress |
| 05/08/2025 | Fire-Resistant Penetrations and Joints | Kun Wu | special |
| 05/06/2025 | Tenant Protection Plan Compliance | Kun Wu | special |
| 05/06/2025 | Energy Code Compliance Inspections | Kun Wu | progress |
| 05/06/2025 | Fire-Resistant Penetrations and Joints | Kun Wu | special |
| 05/05/2025 | Mechanical Systems | Shahrish Shuvo | special |
| 05/05/2025 | Final | Kun Wu | progress |
| 05/02/2025 | Energy Code Compliance Inspections | Kun Wu | progress |
| 05/02/2025 | Fire-Resistant Penetrations and Joints | Kun Wu | special |
| 05/02/2025 | Tenant Protection Plan Compliance | Kun Wu | special |
| 04/04/2025 | Interior lighting power | Kun Wu | energy_progress |
| 04/04/2025 | Lighting controls | Kun Wu | energy_progress |
| 03/26/2025 | Energy Code Compliance Inspections | Kun Wu | progress |
| 03/26/2025 | Tenant Protection Plan Compliance | Kun Wu | special |
| 03/26/2025 | Fire-Resistant Penetrations and Joints | Kun Wu | special |
| 06/29/2023 | Mechanical Systems | ERIK LIEPINS | special |
| 06/29/2023 | Final | ERIK LIEPINS | progress |
| 06/29/2023 | Energy Code Compliance Inspections | ERIK LIEPINS | progress |
| 06/29/2023 | HVAC-R and service water heating system controls | ERIK LIEPINS | energy_progress |
| 06/29/2023 | HVAC-R and service water heating equipment | ERIK LIEPINS | energy_progress |