| Owner | Filings | Most Recent |
|---|---|---|
| BRICKSTONE GROUP | 7 | 07/08/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/09/2024 | $2.3M | — | — → — | $1,053/sf building |
| 03/23/2023 | $900K | — | — → — | $417/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CL ENGINEERING P.C. | 4 | 09/26/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| WM ARCH | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JOE ELECTRICAL INC | Electrical | 1 | 03/22/2026 |
| TWO BROTHERS K CONST CORP | General Contractor | 1 | 07/08/2026 |
| PLBG P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CL ENGINEERING P.C. | 6781 | 2 | 09/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | TWO BROTHERS K CONST CORP | 04/20/2023 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 04/20/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2023 | Complete | JOE ELECTRICAL INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/25/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/13/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/12/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 10/04/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 06/07/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/07/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/07/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/27/2023 | Structural Stability – Alterations of existing buildings | CHRISTIAN LOZADA | special |
| 09/27/2023 | Energy Code Compliance Inspections | CHRISTIAN LOZADA | progress |
| 09/27/2023 | Maintenance information | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | HVAC-R and service water heating system controls | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | HVAC-R and service water heating equipment | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | HVAC-R and service water piping design and insulation | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | Structural Cold-Formed Steel | CHRISTIAN LOZADA | special |
| 09/27/2023 | Fire-Resistant Penetrations and Joints | CHRISTIAN LOZADA | special |
| 09/27/2023 | Energy Code Compliance Inspections | CHRISTIAN LOZADA | progress |
| 09/27/2023 | Structural Wood Frame | CHRISTIAN LOZADA | progress |
| 09/27/2023 | Final | CHRISTIAN LOZADA | progress |
| 09/27/2023 | Interior lighting power | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | Insulation placement and R values | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | Fenestration and door U-factor and product ratings | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | Metering | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | Fenestration air leakage | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | Air barrier - visual inspection | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | HVAC-R and service water piping design and insulation | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | Fenestration areas | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | HVAC-R and service water heating equipment | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | Maintenance information | CHRISTIAN LOZADA | energy_progress |
| 09/27/2023 | HVAC-R and service water heating system controls | CHRISTIAN LOZADA | energy_progress |
| 09/19/2023 | Insulation placement and R values | CHRISTIAN LOZADA | energy_progress |
| 09/19/2023 | HVAC-R and service water piping design and insulation | CHRISTIAN LOZADA | energy_progress |
| 09/19/2023 | HVAC-R and service water heating system controls | CHRISTIAN LOZADA | energy_progress |