| Owner | Filings | Most Recent |
|---|---|---|
| Congregation Emanu-EL | 27 | 08/28/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Kohler Ronan | 2 | 08/20/2026 |
| Joel Phagoo P.E | 1 | 01/13/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 Expediting Service | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Dynamic Installation | Scaffold | 5 | 07/08/2026 |
| Dak Electric Cont'g | Electrical | 2 | 03/21/2026 |
| WCK Electric | Electrical | 1 | 03/22/2026 |
| RTR Construction Co | General Contractor | 1 | 06/27/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Crosscheck Inspection Services | 544 | 2 | 08/20/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | RTR Construction Co | 06/01/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | Dynamic Installation | 07/05/2018 |
| DOB NOW | Sidewalk Shed | Permit Issued | Dynamic Installation | 02/12/2018 |
| DOB NOW | Sidewalk Shed | Permit Issued | Dynamic Installation | 01/16/2018 |
| BIS | PL | ISSUED | G&B Plumbing & Heating | 08/03/2018 |
| BIS | MH | ISSUED | Conceptual Construction | 07/25/2018 |
| BIS | OT | ISSUED | Conceptual Construction | 07/13/2018 |
| BIS | OT | ISSUED | AM&G Waterproofing | 05/01/2018 |
| BIS | OT | ISSUED | AM&G Waterproofing | 03/06/2018 |
| BIS | EQ | ISSUED | Champion Contracting | 03/19/2009 |
| BIS | EQ | ISSUED | York Scaffold Equipment | 03/12/2009 |
| BIS | OT | ISSUED | Tishman Interiors | 02/10/2009 |
| BIS | OT | ISSUED | Tishman Interiors | 02/10/2009 |
| BIS | EQ | ISSUED | Champion Contracting | 01/07/2009 |
| BIS | OT | ISSUED | Tishman Construction | 03/19/2008 |
| BIS | EQ | ISSUED | York Scaffold Equipment | 03/05/2008 |
| BIS | SP | ISSUED | Active Fire Sprinkler | 01/09/2006 |
| BIS | SP | ISSUED | Avtive Fire Sprinkler | 09/08/2004 |
| BIS | SP | ISSUED | Avtive Fire Sprinkler | 06/11/2003 |
| BIS | OT | RE-ISSUED | Tishman Construction | 12/19/2002 |
| BIS | PL | ISSUED | Jam Sewer Cleaning Service | 09/18/2000 |
| BIS | — | ISSUED | Barteluce Architects | 06/22/2000 |
| BIS | OT | ISSUED | Tishman Construction | 06/02/2000 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/20/2026 | Permit Issued | RTR Construction Co | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PEAD-AA30NL 880 CFM · Vrf Indoor ×2 PUZ-AK30NLHZ 30,000 BTU · Heat Pump Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2026 | Cancelled | Shuir Electrical Contractors | General Wiring |
| 01/12/2018 | Permit Issued | WCK Electric | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/26/2026 | Final | EUGENE BIFULCO | progress |
| 08/26/2026 | Post-installed Anchors | EUGENE BIFULCO | special |
| 08/26/2026 | Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components | EUGENE BIFULCO | special |
| 08/26/2026 | Mechanical Systems | EUGENE BIFULCO | special |
| 07/22/2026 | Mechanical Systems | EUGENE BIFULCO | special |
| 07/22/2026 | Post-installed Anchors | EUGENE BIFULCO | special |
| 07/22/2026 | Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components | EUGENE BIFULCO | special |
| 07/22/2026 | Final | EUGENE BIFULCO | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Temple Emanu-el | Religious | Floor 2, Penthouse | Project M01378281 |