Roof16p · 6 filings · 20 docs
ArchitectureDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Standpipe · Structural
Install temporary fire standpipe system as per plans.
On file for this project
29 documents · 9 drawing sheets
PLUMBING MODIFICATIONS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE OR OCCUPANCY.
On file for this project
3 documents
INSTALLATION OF COOLING TOWER AS PER PLANS HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 5 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 62p · 3 filings · 18 docs
ArchitectureCivilDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods · Standpipe
Install temporary fire standpipe system as per plans.
On file for this project
29 documents
INTERIOR DEMOLITION OF EXISTING NON-LOAD BEARING PARTITIONS
On file for this project
4 documents · 1 drawing sheet
Removal of non bearing partition and related finishes as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
3 documents · 1 drawing sheet
Floor 51p · 2 filings · 18 docs
ArchitectureCivilDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods · Standpipe
Install temporary fire standpipe system as per plans.
On file for this project
29 documents
INTERIOR DEMOLITION OF EXISTING NON-LOAD BEARING PARTITIONS
On file for this project
4 documents · 1 drawing sheet
Floor 45p · 2 filings · 18 docs
ArchitectureCivilDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods · Standpipe
Install temporary fire standpipe system as per plans.
On file for this project
29 documents · 4 drawing sheets
INTERIOR DEMOLITION OF EXISTING NON-LOAD BEARING PARTITIONS
On file for this project
4 documents · 1 drawing sheet
Floor 36p · 2 filings · 18 docs
ArchitectureCivilDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods · Standpipe
Install temporary fire standpipe system as per plans.
On file for this project
29 documents · 5 drawing sheets
INTERIOR DEMOLITION OF EXISTING NON-LOAD BEARING PARTITIONS
On file for this project
4 documents · 1 drawing sheet
Floor 28p · 3 filings · 18 docs
ArchitectureCivilDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods · Standpipe
Install temporary fire standpipe system as per plans.
On file for this project
29 documents · 6 drawing sheets
INTERIOR DEMOLITION OF EXISTING NON-LOAD BEARING PARTITIONS
On file for this project
4 documents · 1 drawing sheet
Removal of non bearing partition and related finishes as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
3 documents · 1 drawing sheet
Floor 110p · 2 filings · 18 docs
ArchitectureCivilDMEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Protection and Mechanical Methods · Standpipe
Install temporary fire standpipe system as per plans.
On file for this project
29 documents · 9 drawing sheets
INTERIOR DEMOLITION OF EXISTING NON-LOAD BEARING PARTITIONS
On file for this project
4 documents · 1 drawing sheet
Cellar1 filing · 20 docs
Fire Protection
Issued Permit Scope
Standpipe
Install temporary fire standpipe system as per plans.
On file for this project
29 documents
Site & exterior9 filings · 20 docs
ArchitectureCivilDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Protection and Mechanical Methods
Install temporary fire standpipe system as per plans.
On file for this project
29 documents · 12 drawing sheets
Installation of a temporary roof protection and overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application
On file for this project
2 documents · 3 drawing sheets
TEMPORARY ROOF PROTECTION AT ADJOINING PROPERTIES DURING NB CONST, FILED SEP. ROOF PROTECTION SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
9 documents · 8 drawing sheets
Latest 3 of 9 filings on this floor.
Filed — no permit issued3 filings · 20 docs
ArchitectureElectricalFire ProtectionGeneralMechanicalPlumbingStructuralZ
Underground plumbing for new building M001164499-I1
On file for this project
105 documents · 12 drawing sheets
Modification to existing HVAC system as per plans filed herewith. No change in use, egress or occupancy under this application.
On file for this project
5 documents
No filed description on record for this project.
On file for this project
4 documents · 12 drawing sheets