| Firm | Filings | Most Recent |
|---|---|---|
| TRINITY SOLAR LLC | 2 | 05/06/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| ACA ASSOCIATES | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TRINITY SOLAR LLC | General Contractor | 3 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BITOPI CONSULTANTS LLC | 7036 | 2 | 05/06/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | TRINITY SOLAR LLC | 03/27/2025 |
| BIS | MH | ISSUED | TTC SERVICE CORP | 05/30/2013 |
| BIS | — | ISSUED | V.A BUILDERS CORP | 10/17/2012 |
| BIS | PL | ISSUED | W.R. PLBG AND HTG CORP | 05/27/2011 |
| BIS | EQ | ISSUED | V.A BUILDERS CORP | 04/18/2011 |
| BIS | — | ISSUED | V.A BUILDERS CORP | 04/18/2011 |
| BIS | — | RE-ISSUED | V.A BUILDERS CORP | 04/18/2011 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/24/2025 | Complete | REDLINE ELECTRIC INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/06/2026 | Signed-off | TRINITY SOLAR LLC | 27 panels, 11.07 kw, 1,599 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/08/2026 | Fire-Resistant Penetrations and Joints | KAMRUL AHSAN | special |
| 05/08/2026 | Final | Ayracon Almaraz | progress |
| 05/08/2026 | Energy Code Compliance Inspections | Ayracon Almaraz | progress |
| 05/08/2026 | Air barrier - visual inspection | Ayracon Almaraz | energy_progress |