| Owner | Filings | Most Recent |
|---|---|---|
| 8008 ESTATE LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/06/2024 | $1.7M | — | — → — | $546/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BASSIRI | 6 | 03/26/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ECDESIGN STUDIO | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KALE CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| AMC PLBG, HTG & CLNG, INC | Plumbing | 1 | 07/08/2026 |
| SMART PLBG & HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BASSIRI | 8394 | 3 | 03/26/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | AMC PLBG, HTG & CLNG, INC | 01/28/2025 |
| DOB NOW | Plumbing | Signed-off | SMART PLBG & HTG CORP | 12/04/2024 |
| DOB NOW | General Construction | Signed-off | KALE CONSTRUCTION INC | 12/02/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/26/2024 | Complete | KJK ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/12/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/22/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/03/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/03/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/27/2025 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 03/27/2025 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |
| 03/27/2025 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 03/26/2025 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 03/26/2025 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 03/26/2025 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |
| 01/17/2025 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 01/17/2025 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 01/17/2025 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |