| Owner | Filings | Most Recent |
|---|---|---|
| 799 801 PRES TENANTS CORP | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BHK ENGINEERING | 1 | 05/26/2026 |
| CLAIRE DAVENPORT ARCHITECTE INC. | 2 | 12/04/2025 |
| MCSWEENEY ENGINEERING | 3 | 11/24/2025 |
| MICHAEL DERUVO & ASSOC. ARCHITECTS | 7 | 10/23/2025 |
| B-CUBED ENGINEERING LLC | 1 | 02/24/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARCH-FORM DESIGN BUILD | 14 | 03/21/2026 |
| TOM ENNIS ASSOCIATES | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GREEN CONVERSIONS INC | General Contractor | 5 | 07/08/2026 |
| PROFICIENT HOME IMPROVEM* | General Contractor | 3 | 07/08/2026 |
| MEGHNA CONSTRUCTION | General Contractor | 1 | 09/19/2026 |
| BLAZE PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| SHAW MECHANICAL INC | Plumbing | 1 | 06/28/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BHK ENGINEERING, D.P.C. | 9589 | 1 | 05/26/2026 |
| ARCO ENGINEERING PC | 3769 | 3 | 11/24/2025 |
| WORLD DESIGN ARCHITECTURE | 9323 | 4 | 10/23/2025 |
| B-CUBED ENGINEERING LLC | 6023 | 2 | 02/24/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | MEGHNA CONSTRUCTION | 09/18/2026 |
| DOB NOW | Mechanical Systems | Signed-off | GREEN CONVERSIONS INC | 10/22/2025 |
| DOB NOW | Plumbing | Signed-off | BLAZE PLUMBING & HEATING | 08/18/2025 |
| DOB NOW | Mechanical Systems | Signed-off | PROFICIENT HOME IMPROVEM* | 08/14/2025 |
| DOB NOW | Plumbing | Signed-off | JAMES CRUZ | 07/16/2025 |
| DOB NOW | Structural | Signed-off | GREEN CONVERSIONS INC | 07/15/2025 |
| DOB NOW | General Construction | Signed-off | PROFICIENT HOME IMPROVEM* | 06/20/2025 |
| DOB NOW | General Construction | Signed-off | GREEN CONVERSIONS INC | 02/21/2025 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/10/2025 | Signed-off | PROFICIENT HOME IMPROVEM* | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric 1.66-TON MULTI-ZONE INVERTER HEAT-PUMP SYSTEM MODEL#: MXZ-2C20NA4
9,000 BTU/H WALL-MOUNTED INDOOR UNIT MODEL#: MSZ-GL09NA
12,000 BTU/H WALL-MOUNTED INDOOR UNIT MODEL#: MSZ-GL12NA 13,500 BTU · Split System ×12 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/24/2025 | Signed-off | SHAW MECHANICAL INC | Gas, Water/Sanitary |
| 06/10/2025 | — | — | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/26/2026 | Complete | DENMAR ELECTRIC CORP | General Wiring |
| 07/29/2025 | Permit Issued | KENNETH FISK ELECTRIC COR | General Wiring |
| 07/03/2018 | Permit Issued | WCK ELECTRIC CORP. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/26/2026 | Permit Issued | MEGHNA CONSTRUCTION | Steel, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/19/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/14/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/12/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/18/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/11/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/26/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/05/2026 | Tenant Protection Plan Compliance | William DeGraaff | special |
| 04/24/2026 | Post-installed Anchors | William DeGraaff | special |
| 04/24/2026 | Structural Stability – Alterations of existing buildings | William DeGraaff | special |
| 04/07/2026 | Masonry | William DeGraaff | special |
| 04/07/2026 | Structural Steel - Details | William DeGraaff | special |
| 03/13/2026 | Final | William DeGraaff | progress |
| 11/13/2025 | Fire-Resistant Penetrations and Joints | JOSE MANTRANA | special |
| 10/22/2025 | Fire-Resistant Penetrations and Joints | William Alicea | special |
| 09/16/2025 | Fire-Resistant Penetrations and Joints | William Alicea | special |
| 05/28/2025 | Tenant Protection Plan Compliance | — | special |
| 05/27/2025 | Final | MICHAEL DERUVO | progress |
| 05/27/2025 | Mechanical Systems | — | special |
| 05/27/2025 | Final | MICHAEL DERUVO | progress |
| 01/28/2025 | Structural Steel - Welding | Domenico Antonelli | special |
| 01/28/2025 | Structural Stability – Alterations of existing buildings | Domenico Antonelli | special |
| 01/28/2025 | Structural Steel - High Strength Bolting | Domenico Antonelli | special |
| 01/28/2025 | Structural Steel - Details | Domenico Antonelli | special |
| 01/13/2025 | Final | Domenico Antonelli | progress |
| 11/15/2024 | Final | Michael McSweeney | progress |
| 11/15/2024 | Mechanical Systems | JOSE MANTRANA | special |