Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingEquipment
Permit Issued — active, not yet Signed-off
RoofUnder Construction9p · 5 filings · 20 docs
Floor 7Under Construction4p · 1 filing · 2 docs
Floor 6Under Construction5p · 2 filings · 5 docs
Floor 5Under Construction5p · 2 filings · 5 docs
Floor 4Under Construction6p · 3 filings · 14 docs
Floor 3Under Construction5p · 2 filings · 5 docs
Floor 2Under Construction5p · 2 filings · 5 docs
Floor 1Under Construction5p · 2 filings · 5 docs
CellarUnder Construction17p · 3 filings · 10 docs
Sub-CellarUnder Construction17p · 4 filings · 20 docs
Site & exteriorUnder Construction26p · 6 filings · 19 docs
Filed — no permit issued1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
OWNERS REP504/09/2026
SMART CONSULTING NY207/08/2026
SMART CONSULTING NY.CORP203/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SPRING SCAFFOLDING LLC403/21/2026
NEW YORK ENGINEERING203/21/2026
MUNICIPAL BUILDING CONSULTANTS103/21/2026
SIERRA SAFETY CORP203/21/2026
HLZAE103/21/2026
AE DESIGN SOLUTION603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SPRING SCAFFOLDING LLCGeneral Contractor3608/13/2026
HI COOL INCGeneral Contractor303/21/2026
FACADE RES GROUP LLCGeneral Contractor307/08/2026
JUNIOR CARTER MECH. CORPPlumbing207/08/2026
CORE SCAFFOLD SYSTEMS INC.General Contractor204/09/2026
A. HTG AND PLBG WORKS INCPlumbing107/08/2026
DMT PLUMBING & HEATING CORP.Plumbing107/08/2026
WIRE UP ELEC'L CONT'G CORElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
KOENIGSBERG ENGINEERING,2247108/02/2025
JOSEPH BOTTA, PE, PC1139107/10/2024
Building Lifecycle
All (163)Filed (14)Permit Issued (30)Signed Off (3)Facade (FISP) (9)Violation (60)Inspection (15)Objection (16)Special Inspection (16)
08/12/2026
Permit issued — Sidewalk Shed
M00545644-I1-SH
06/29/2026
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
05/29/2026
Permit issued — Sidewalk Shed
M00545644-I1-SH
05/07/2026
Filed — Alteration
Filing for Post Approval Amendment of suspended scaffold plan.
M01274910-P1
04/09/2026
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/09/2026
Permit issued — General Construction
M01257881-I1-GC
03/06/2026
Permit issued — Sidewalk Shed
M00545644-I1-SH
03/05/2026
Permit issued — Protection and Mechanical Methods
M00545660-I1-PM
02/19/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/09/2026
Permit issued — Protection and Mechanical Methods
M01343243-I1-PMM
01/08/2026
Filed — Alteration
INSTALLATION OF TEMPORARY PLATFORM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01343243-I1
12/10/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/01/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
11/05/2025
Permit issued — Supported Scaffold
M01312842-I1-SF
11/03/2025
Filed — Alteration
M01312842-I1
10/20/2025
Permit issued — Suspended Scaffold
M01274910-I1-SC
09/26/2025
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
09/26/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
09/24/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/22/2025
Objection resolved — Addressed
09/22/2025
Objection resolved — Addressed
09/22/2025
Objection resolved — Addressed
09/22/2025
Objection resolved — Addressed
09/22/2025
Objection resolved — Addressed
09/22/2025
Objection resolved — Addressed
09/22/2025
Objection resolved — Addressed
09/22/2025
Objection resolved — Addressed
09/19/2025
Cycle 10 facade report submitted
09/19/2025
Cycle 10 facade report signed — UNSAFE
09/17/2025
Cycle 10 facade inspection completed
09/13/2025
Objection raised — Admin
09/13/2025
Objection raised — Structural
09/13/2025
Objection raised — Structural
09/13/2025
Objection raised — Structural
09/13/2025
Objection raised — Other
09/13/2025
Objection raised — Inspections
09/13/2025
Objection raised — Structural
09/13/2025
Objection raised — Structural
08/29/2025
Violation issued (ECB, closed)
Construction
08/25/2025
Filed — Alteration
Filing for Post Approval Amendment of suspended scaffold plan.
M01274910-I1
08/11/2025
Permit issued — General Construction
M01257881-I1-GC
08/02/2025
Filed — Alteration
exterior restoration as per plans filed herewith. no change to use, egress or occupancy.
M01257881-I1
07/25/2025
Special inspection requirement — Concrete - Cast-In-Place
RICHARD KOENIGSBERG
07/18/2025
Special inspection requirement — Final
RICHARD KOENIGSBERG
07/18/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
RICHARD KOENIGSBERG
07/18/2025
Special inspection requirement — Masonry
RICHARD KOENIGSBERG
07/18/2025
Special inspection requirement — Post-installed Anchors
RICHARD KOENIGSBERG
06/17/2025
Signed off — Alteration
GAS TO GAS REPLACEMENT . REPLACEMENT OF TWO EXISTING GAS FIRED HOT WATER HEATERS WITH THREE GAS FIRED HOT WATER HEATERS AND THREE INDIRECT WATER HEATERS
M01141086-I1
05/28/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/02/2025
Special inspection requirement — Maintenance information
HOWARD KRIGSMAN
05/02/2025
Special inspection requirement — HVAC-R and service water heating system controls
HOWARD KRIGSMAN
05/02/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
HOWARD KRIGSMAN
05/02/2025
Special inspection requirement — HVAC-R and service water heating equipment
HOWARD KRIGSMAN
05/01/2025
Filed — Alteration
GAS TO GAS REPLACEMENT . REPLACEMENT OF TWO EXISTING GAS FIRED HOT WATER HEATERS WITH THREE GAS FIRED HOT WATER HEATERS AND THREE INDIRECT WATER HEATERS
M01141086-P1
04/28/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/11/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
03/07/2025
Violation issued (ECB, closed)
Construction
02/27/2025
Permit issued — Protection and Mechanical Methods
M00545660-I1-PM
02/27/2025
Permit issued — Sidewalk Shed
M00545644-I1-SH
11/20/2024
Permit issued — Plumbing
M01141086-I1-PL
Latest 60 of 163 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedSPRING SCAFFOLDING LLC08/12/2026
DOB NOWSidewalk ShedPermit IssuedSPRING SCAFFOLDING LLC05/29/2026
DOB NOWGeneral ConstructionPermit IssuedFACADE RES GROUP LLC03/09/2026
DOB NOWSidewalk ShedPermit IssuedSPRING SCAFFOLDING LLC03/06/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedSPRING SCAFFOLDING LLC03/05/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedCORE SCAFFOLD SYSTEMS INC01/09/2026
DOB NOWSupported ScaffoldPermit IssuedCORE SCAFFOLD SYSTEMS INC11/05/2025
DOB NOWSuspended ScaffoldPermit IssuedFACADE RES GROUP LLC10/20/2025
DOB NOWGeneral ConstructionPermit IssuedFACADE RES GROUP LLC08/11/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedSPRING SCAFFOLDING LLC02/27/2025
DOB NOWSidewalk ShedPermit IssuedSPRING SCAFFOLDING LLC02/27/2025
DOB NOWPlumbingSigned-offD.H. EAGLE PLUMBING, LLC11/20/2024
DOB NOWMechanical SystemsSigned-offHI COOL INC09/27/2024
DOB NOWSidewalk ShedPermit IssuedSPRING SCAFFOLDING LLC08/07/2024
DOB NOWProtection and Mechanical MethodsPermit IssuedSPRING SCAFFOLDING LLC06/04/2024
DOB NOWPlumbingPermit IssuedJUNIOR CARTER MECH. CORP05/01/2024
DOB NOWPlumbingPermit IssuedJUNIOR CARTER MECH. CORP02/16/2024
DOB NOWSidewalk ShedPermit IssuedSPRING SCAFFOLDING LLC08/09/2023
DOB NOWPlumbingPermit IssuedDMT PLUMBING & HEATING CO06/07/2023
DOB NOWProtection and Mechanical MethodsPermit IssuedSPRING SCAFFOLDING LLC06/02/2023
DOB NOWSidewalk ShedPermit IssuedSPRING SCAFFOLDING LLC08/09/2022
DOB NOWProtection and Mechanical MethodsPermit IssuedSPRING SCAFFOLDING LLC06/03/2022
DOB NOWSidewalk ShedPermit IssuedSPRING SCAFFOLDING LLC08/18/2021
DOB NOWProtection and Mechanical MethodsPermit IssuedSPRING SCAFFOLDING LLC06/24/2021
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC03/03/2021
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC12/18/2020
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC03/02/2020
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC12/19/2019
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC12/27/2018
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC10/25/2018
BISPLISSUEDJUNIOR CARTER MECH. CORP01/26/2023
BISFPISSUEDLUND FIRE PRODUCTS CO INC11/21/2016
BISSPISSUEDSAFETY FIRE SPRINKLER CORP03/31/2015
BISPLISSUEDJUNIOR CARTER MECH. CORP04/24/2014
BISBLISSUEDPASSEGGIO PLBG & HTG CORP.08/23/2006
BISMHISSUEDAES NJ COGEN CO INC08/17/2006
BISPLISSUEDPASSEGGIO PLBG & HTG CORP.08/17/2006
BISMHISSUEDG. FAZIO CONSTRUCTION CO02/13/2001
BISOTISSUEDG. FAZIO CONSTRUCTION CO02/13/2001
BISOTISSUEDG. FAZIO CONSTRUCTION CO08/17/1999
+ 1 more permits on file
1 project · most recent 06/15/2023
Gas
FiledStatusContractorScope
06/15/2023Permit IssuedDMT PLUMBING & HEATING COGas
5 projects · most recent 08/11/2026
General Wiring
FiledStatusContractorScope
08/11/2026Permit IssuedSPICE ELECTRIC COMPANY—
01/08/2024Permit IssuedCAPUTEK ELEC'L SERVICES,—
05/17/2023Permit IssuedMARTIN DORKINGeneral Wiring
03/27/2023CompleteWIRE UP ELEC'L CONT'G COR—
10/24/2018Permit IssuedTOP SHELF ELECTRIC CORP—
1 project · most recent 06/09/2021
Masonry
FiledStatusContractorScope
06/09/2021——Masonry
1 project · most recent 06/23/2021
Sidewalk Shed
FiledStatusContractorScope
06/23/2021Permit IssuedSPRING SCAFFOLDING LLCSidewalk Shed
1 project · most recent 05/07/2026
Suspended Scaffold
FiledStatusContractorScope
05/07/2026Permit IssuedFACADE RES GROUP LLCSuspended Scaffold
1 project · most recent 05/07/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
05/07/2026Permit IssuedFACADE RES GROUP LLCSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 15
DateTypeResultReport
06/29/2026Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
02/19/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/10/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/01/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
09/26/2025Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
09/26/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/28/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/28/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/11/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
07/05/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
04/30/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
03/19/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/03/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/03/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
06/21/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
07/25/2025Concrete - Cast-In-PlaceRICHARD KOENIGSBERGspecial
07/18/2025FinalRICHARD KOENIGSBERGprogress
07/18/2025Structural Stability – Alterations of existing buildingsRICHARD KOENIGSBERGspecial
07/18/2025MasonryRICHARD KOENIGSBERGspecial
07/18/2025Post-installed AnchorsRICHARD KOENIGSBERGspecial
05/02/2025Maintenance informationHOWARD KRIGSMANenergy_progress
05/02/2025HVAC-R and service water heating system controlsHOWARD KRIGSMANenergy_progress
05/02/2025HVAC-R and service water piping design and insulationHOWARD KRIGSMANenergy_progress
05/02/2025HVAC-R and service water heating equipmentHOWARD KRIGSMANenergy_progress
06/15/2023Energy Code Compliance InspectionsLOUIS ARENAprogress
06/15/2023Energy Code Compliance InspectionsLOUIS ARENAprogress
05/27/2021Air barrier — testing —energy_progress
05/26/2021Structural Steel - Welding—special
05/26/2021Structural Stability – Alterations of existing buildings—special
05/26/2021Final—progress
05/26/2021Masonry—special
▾Documents — 82 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch14
09/06/2026M00090845-I1Request digital key ↗
09/03/2026M00529083-I1Request digital key ↗
09/03/2026M00545644-I1Request digital key ↗
Showing 3 of 14 on file for this type
▸Applications & Permits8
▸BISPLAN / WORK APPROVAL APPLICATION5
04/20/2023104450871Open ↗
12/09/2022104450871Open ↗
12/06/2022104450871Open ↗
Showing 3 of 5 on file for this type
▸BISWORK PERMIT APPLICATION3
01/26/2023104450871Open ↗
11/25/2016122922141Open ↗
03/30/2015140327527Open ↗
▸Seals & Professional Certifications31
▸DOB NOWDPL-1: Design Professional Seal & Signature15
09/06/2026M00090845-I1Open ↗
09/03/2026M00545644-I1Open ↗
08/30/2026M00880243-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/01/2026M00880243-P1Open ↗
09/01/2026M01141086-I1Open ↗
09/01/2026M01141086-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026M01257881-I1Open ↗
09/01/2026M01257881-I1Open ↗
09/01/2026M01257881-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
10/31/2017122922141Open ↗
10/20/2016122922141Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
03/30/2015140327527Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/30/2015140327527Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
03/30/2015140327527Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING2
04/20/2023104450871Open ↗
03/30/2015140327527Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
06/30/2015140327527Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/30/2026M00880243-I1Open ↗
08/26/2026M01076545-I1Open ↗
08/25/2026M01141086-I1Open ↗
Showing 3 of 6 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
10/20/2016122922141Open ↗
▸Energy Compliance1
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026M01141086-I1Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY1
03/30/2015140327527Open ↗
▸BIS* STRUCTURAL STABILITY 1 RCNY:16-011
05/12/2023104450871Open ↗
▸BIS* FINAL INSPECTION DIRECTIVE 14 OF 19751
05/12/2023104450871Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
05/15/2023104450871Open ↗
10/31/2017122922141Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
01/26/2023104450871Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT3
10/31/2017122922141Open ↗
10/20/2016122922141Open ↗
03/30/2015140327527Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
05/12/2023104450871Open ↗
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET1
10/20/2016122922141Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
03/30/2015140327527Open ↗
▸BISBOROUGH INTAKE FORM1
10/31/2017122922141Open ↗
▸Other Documents5
▸DOB NOWManufacturer's Specifications2
08/17/2026M01274910-P1Open ↗
08/13/2026M01274910-I1Open ↗
▸DOB NOWCalculations2
08/17/2026M01274910-P1Open ↗
08/13/2026M01274910-I1Open ↗
▸BISFIRE SUPP ANSUL APPROVL: FD-FSS1
10/31/2017122922141Open ↗