← Back
Factory, light manufacturing
805 EAST 139 STREET
BRONX · Mott Haven-Port Morris · BIN 2004017
💬 Discuss this project
1948Year Built
3Stories
F5Building Class
M3-1Zoning
54,325 sfGross Floor Area
1Units
LL97 Covered0 Open Violations
Factory, light manufacturing · Owner of record: 820 EAST 140TH STREET LLC · 28,277 sf lot · 1.92 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionCivilGeneralOther
Roof4p · 3 filings · 20 docs
Floor 32p · 1 filing · 16 docs
Floor 256p · 6 filings · 20 docs
Floor 14p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
820 EAST 140TH STREET407/08/2026
MARKLAND 3882807/08/2026
225 EAST REALTY PARTNERS LLC1107/08/2026
MPM 651207/08/2026
APACHE # REALTY COMPANY203/22/2026
APACHE II REALTY803/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/13/2019$6.6M—APACHE II REALTY LLC → 820 EAST 140TH STREET LLC$121/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
LEVIN ENGINEERING PLLC803/21/2026
EA DESIGN GROUP1403/21/2026
MICHAEL MUROFF ARCHITECT LLC103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CITI 2 GENERAL CONST INCGeneral Contractor807/08/2026
PRECISION BUILDING & CONSGeneral Contractor407/08/2026
RAYMOND WILSONElectrical303/21/2026
RRP PLUMBING CORPPlumbing207/08/2026
RRP PLUMBING CORPFire Protection207/08/2026
MECHANICAL EAST CO.,INCGeneral Contractor107/08/2026
A&H EXPRESS PLBG&HTG CORPPlumbing107/08/2026
DEPENDABLE MECHANICAL CORFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AK ENGINEERING PC678709/26/2024
LEVIN ENGINEERING PLLC1267402/08/2023
METRIC CONSULTING AND INS1803310/04/2022
Building Lifecycle
All (135)Filed (15)Permit Issued (15)Signed Off (6)Violation (56)Inspection (14)Objection (8)Special Inspection (21)
04/29/2026
Signed off — Alteration
APPLICATION FILED FOR MECHANICAL ADDITIONS/MODIFICATIONS TO ON THE 2ND FLOOR AND ROOF AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
X00522079-I1
04/09/2026
Signed off — Alteration
Application filed for Structural Modifications/additions on the 2nd floor and Roof as pr plans filed herewith. No change in use, egress or occupancy.
X00878855-I1
11/14/2025
Signed off — Alteration
X00454602-I1
05/20/2025
Signed off — Alteration
INSTALLATION OF DRY PIPE valves FOR FIRST FLOOR LEVEL to replace filing # 200052094 . NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00825777-I1
03/12/2025
Signed off — Alteration
FILING TO WITHDRAW PERMITTED ALT 220041979 FOR GAS SPACE HEATERS INSTALL NEW GAS PIPING TO SPACE HEATERS AND NEW RTUs. EXISTING GAS SERVICE TO REMAIN. REMOVE EXISTING 1000 CFH GAS METER .INSTALL 8 NEW GAS METERS.NO CHANGE IN USE EGRESS/OCCUPANCY.
X08008019-I1
11/19/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/10/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
10/09/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/09/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/03/2024
Permit issued — Plumbing
X00637380-I1-EW-SP
10/02/2024
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
09/26/2024
Filed — Alteration
APPLICATION FILED FOR PLUMBING/SPRINKLER ADDITIONS/MODIFICATIONS ON THE 2ND FLOOR AS PER PLANS FILED HEREWITH.
X00637380-P3
09/26/2024
Special inspection requirement — Sprinkler Systems
Ari Kamo
09/13/2024
Filed — Alteration
APPLICATION FILED FOR PLUMBING/SPRINKLER ADDITIONS/MODIFICATIONS ON THE 2ND FLOOR AS PER PLANS FILED HEREWITH.
X00637380-P2
05/17/2024
Special inspection requirement — Sprinkler Systems
Ari Kamo
03/21/2024
Permit issued — Plumbing
X00637380-I1-PL
03/15/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
11/22/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/01/2023
Permit issued — Mechanical Systems
X00522079-I1-MS
10/17/2023
Filed — Alteration
APPLICATION FILED FOR MECHANICAL ADDITIONS/MODIFICATIONS TO ON THE 2ND FLOOR AND ROOF AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR OCCUPANCY
X00522079-I1
07/25/2023
Permit issued — Structural
X00878855-I1-ST
07/10/2023
Filed — Alteration
Application filed for Structural Modifications/additions on the 2nd floor and Roof as pr plans filed herewith. No change in use, egress or occupancy.
X00878855-I1
05/11/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/03/2023
Inspection — Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test
Certified
View inspection ↗
03/08/2023
Permit issued — Structural
X00562237-S1-ST
02/27/2023
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
02/24/2023
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/21/2023
Permit issued — Sprinklers
X00825777-I1-EW-SP
02/08/2023
Filed — Alteration
INSTALLATION OF DRY PIPE valves FOR FIRST FLOOR LEVEL to replace filing # 200052094 . NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00825777-I1
02/08/2023
Special inspection requirement — Sprinkler Systems
Dmitry Levin
12/02/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/23/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
10/28/2022
Permit issued — Plumbing
X08008019-I1-PL
10/04/2022
Filed — Alteration
FILING TO WITHDRAW PERMITTED ALT 220041979 FOR GAS SPACE HEATERS INSTALL NEW GAS PIPING TO SPACE HEATERS AND NEW RTUs. EXISTING GAS SERVICE TO REMAIN. REMOVE EXISTING 1000 CFH GAS METER .INSTALL 8 NEW GAS METERS.NO CHANGE IN USE EGRESS/OCCUPANCY.
X08008019-I1
09/12/2022
Permit issued — General Construction
X00522062-I1-GC
09/07/2022
Filed — Alteration
APPLICATION FILED FOR PLUMBING/SPRINKLER ADDITIONS/MODIFICATIONS ON THE 2ND FLOOR AS PER PLANS FILED HEREWITH.
X00637380-P1
08/01/2022
Special inspection requirement — Sprinkler Systems
Ari Kamo
07/06/2022
Signed off — Alteration
INSTALLATION OF MECHANICAL SYSTEM ON THE ROOF LEVEL. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00466575-I1
06/27/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/09/2022
Permit issued — Structural
X00562237-S1-ST
02/16/2022
Permit issued — Plumbing
X00637380-I1-PL
02/16/2022
Permit issued — Sprinklers
X00637380-I1-EW-SP
02/11/2022
Filed — Alteration
APPLICATION FILED FOR PLUMBING/SPRINKLER ADDITIONS/MODIFICATIONS ON THE 2ND FLOOR AS PER PLANS FILED HEREWITH.
X00637380-I1
01/24/2022
Permit issued — General Construction
X00522062-I1-GC
01/18/2022
Filed — Alteration
X00522062-I1
01/05/2022
Permit issued — General Construction
X00562237-I1-GC
12/17/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/10/2021
Filed — Alteration CO
X00562237-S1
12/09/2021
Special inspection requirement — Structural Steel - Details
SAMI HAJJAR P.E
12/07/2021
Special inspection requirement — Final
SAMI HAJJAR P.E
12/07/2021
Special inspection requirement — Structural Steel - High Strength Bolting
SAMI HAJJAR P.E
07/26/2021
Filed — Alteration CO
X00562237-I1
07/22/2021
Special inspection requirement — Shutoff dampers
Dmitry Levin
07/22/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
Dmitry Levin
07/22/2021
Special inspection requirement — HVAC-R and service water heating system controls
Dmitry Levin
07/22/2021
Special inspection requirement — Duct leakage testing, insulation and design
Dmitry Levin
07/22/2021
Special inspection requirement — HVAC-R and service water heating equipment
Dmitry Levin
07/22/2021
Special inspection requirement — Maintenance information
Dmitry Levin
07/22/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Dmitry Levin
07/22/2021
Special inspection requirement — Mechanical Systems
Dmitry Levin
Latest 60 of 135 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offRALPH W. LANDOLFI JR.10/03/2024
DOB NOWPlumbingPermit IssuedRRP PLUMBING CORP03/21/2024
DOB NOWMechanical SystemsSigned-offPRECISION BUILDING & CONS11/01/2023
DOB NOWStructuralSigned-offPRECISION BUILDING & CONS07/25/2023
DOB NOWStructuralPermit IssuedCITI 2 GENERAL CONST INC03/08/2023
DOB NOWSprinklersSigned-offDEPENDABLE MECHANICAL COR02/21/2023
DOB NOWPlumbingSigned-offA&H EXPRESS PLBG&HTG CORP10/28/2022
DOB NOWGeneral ConstructionPermit IssuedPRECISION BUILDING & CONS09/12/2022
DOB NOWStructuralPermit IssuedCITI 2 GENERAL CONST INC03/09/2022
DOB NOWPlumbingPermit IssuedRRP PLUMBING CORP02/16/2022
DOB NOWSprinklersSigned-offRALPH W. LANDOLFI JR.02/16/2022
DOB NOWGeneral ConstructionPermit IssuedPRECISION BUILDING & CONS01/24/2022
DOB NOWGeneral ConstructionPermit IssuedCITI 2 GENERAL CONST INC01/05/2022
DOB NOWMechanical SystemsSigned-offMECHANICAL EAST CO.,INC03/16/2021
DOB NOWGeneral ConstructionSigned-offCITI 2 GENERAL CONST INC01/26/2021
BISEQISSUEDP & G CONSTRUCTION CORP01/06/2012
BISOTISSUEDP & G CONSTRUCTION CORP01/04/2012
BISEQISSUEDCS BRIDGE CORP03/21/2011
BISEQISSUEDDOSANJH CONSTRUCTION CORP01/06/2011
BISOTISSUEDDOSANJH CONSTRUCTION CORP01/06/2011
BISPLISSUEDBRUCKNER PLUMBING LTD12/23/2009
BISMHISSUEDATLAS COATING CORP08/06/1999
BISPLISSUEDROBERT MARTENS PLUMBING & HEATIN11/19/1991
BISMHISSUEDAL HERRICK INC.02/13/1991
BISSPISSUEDACME SPRINKLER CO.01/09/1991
1 project · most recent 09/26/2024
FiledStatusContractorScope
09/26/2024Signed-offRRP PLUMBING CORP20 heads
1 project · most recent 09/26/2024
Gas Water/Sanitary
FiledStatusContractorScope
09/26/2024Permit IssuedRRP PLUMBING CORPGas, Water/Sanitary
1 project · most recent 07/04/2022
General Wiring
FiledStatusContractorScope
07/04/2022CompleteTWINTECH ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 14
DateTypeResultReport
11/19/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/10/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/09/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/09/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/02/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/15/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/22/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/11/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/03/2023Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve TestCertifiedView ↗
02/27/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
02/24/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/02/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/23/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/27/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
09/26/2024Sprinkler SystemsAri Kamospecial
05/17/2024Sprinkler SystemsAri Kamospecial
02/08/2023Sprinkler SystemsDmitry Levinspecial
08/01/2022Sprinkler SystemsAri Kamospecial
12/09/2021Structural Steel - DetailsSAMI HAJJAR P.Especial
12/07/2021FinalSAMI HAJJAR P.Eprogress
12/07/2021Structural Steel - High Strength BoltingSAMI HAJJAR P.Especial
07/22/2021Shutoff dampersDmitry Levinenergy_progress
07/22/2021HVAC-R and service water piping design and insulationDmitry Levinenergy_progress
07/22/2021HVAC-R and service water heating system controlsDmitry Levinenergy_progress
07/22/2021Duct leakage testing, insulation and designDmitry Levinenergy_progress
07/22/2021HVAC-R and service water heating equipmentDmitry Levinenergy_progress
07/22/2021Maintenance informationDmitry Levinenergy_progress
07/22/2021Fire-Resistant Penetrations and JointsDmitry Levinspecial
07/22/2021Mechanical SystemsDmitry Levinspecial
07/22/2021FinalDmitry Levinprogress
07/21/2021Fire-Resistance Rated ConstructionSAMI HAJJAR P.Eprogress
07/21/2021Fire-Resistant Penetrations and JointsSAMI HAJJAR P.Especial
04/07/2021FinalDmitry Levinprogress
04/07/2021Mechanical SystemsDmitry Levinspecial
04/07/2021Fire-Resistant Penetrations and JointsDmitry Levinspecial
▾Documents — 140 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch11
08/24/2026X00522062-I1Request digital key ↗
08/24/2026X00562237-I1Request digital key ↗
08/24/2026X00562237-S1Request digital key ↗
Showing 3 of 11 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems3
08/25/2026X00466575-I1Request digital key ↗
08/15/2026X00466575-P2Request digital key ↗
08/14/2026X00466575-P1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
08/25/2026X00454602-I1Request digital key ↗
▸Applications & Permits16
▸BISPLAN / WORK APPROVAL APPLICATION9
01/13/2023200052094Open ↗
06/04/2021220160867Open ↗
06/04/2021200089518Open ↗
Showing 3 of 9 on file for this type
▸BISWORK PERMIT APPLICATION7
01/06/2012220160867Open ↗
01/05/2012220160867Open ↗
04/08/2011220075219Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications54
▸DOB NOWDPL-1: Design Professional Seal & Signature15
08/25/2026X00466575-P1Open ↗
08/25/2026X00466575-I1Open ↗
08/24/2026X00522062-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature11
08/28/2026X00466575-I1Open ↗
08/28/2026X00466575-I1Open ↗
08/28/2026X00562237-S1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
08/28/2026X00466575-I1Open ↗
08/28/2026X00466575-I1Open ↗
08/28/2026X00466575-I1Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION8
10/06/2011220095858Open ↗
04/20/2011220092646Open ↗
04/20/2011220092646Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
01/05/2012220160867Open ↗
01/06/2011220092646Open ↗
12/07/2010220095858Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST5
01/05/2012220160867Open ↗
01/06/2011220092646Open ↗
12/07/2010220095858Open ↗
Showing 3 of 5 on file for this type
▸Trade Schedules & Equipment3
▸BISSELF-CERT PLUMBING NOTICE2
01/26/2010220041979Open ↗
01/15/2010220041979Open ↗
▸BISSCHEDULE B - PLUMBING1
12/23/2009220041979Open ↗
▸Safety & Tenant Protection4
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X00562237-I1Open ↗
▸DOB NOWStreet Tree Checklist1
08/13/2026X00562237-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026X00562237-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026X00562237-I1Open ↗
▸Environmental & Asbestos16
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/24/2026X00522062-I1Open ↗
08/24/2026X00562237-I1Open ↗
08/24/2026X00562237-S1Open ↗
Showing 3 of 9 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
01/05/2012220160867Open ↗
12/07/2010220095858Open ↗
12/23/2009220041979Open ↗
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/23/2026X00878855-I1Open ↗
08/22/2026X00522079-I1Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
01/06/2011220092646Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
08/03/2010220075219Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY1
01/05/2012220160867Open ↗
▸BISPTA4-SOLAR TAX ABATEMENT APPLICATION1
10/06/2011220095858Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026X00466575-I1Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
07/01/2020220075219Open ↗
▸Approvals, Objections & Sign-offs16
▸BISADMINISTRATIVE OBJECTIONS5
01/05/2012220160867Open ↗
01/06/2011220092646Open ↗
12/07/2010220095858Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
01/13/2023200052094Open ↗
10/06/2011220095858Open ↗
10/06/2011220095858Open ↗
Showing 3 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
07/01/2020220075219Open ↗
10/06/2011220095858Open ↗
04/20/2011220092646Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS1
10/06/2011220095858Open ↗
▸BISSHED LETTER1
03/23/2011220075219Open ↗
▸Cost, Insurance & Ownership6
▸BISCOST AFFIDAVIT6
01/05/2012220160867Open ↗
10/06/2011220095858Open ↗
04/11/2011220092646Open ↗
Showing 3 of 6 on file for this type
▸Filing & Intake Forms5
▸BISEFILING COVER SHEET5
01/05/2012220160867Open ↗
01/06/2011220092646Open ↗
12/07/2010220095858Open ↗
Showing 3 of 5 on file for this type
▸Other Documents1
▸DOB NOWFinal Survey1
08/13/2026X00562237-I1Open ↗