← Back
Miscellaneous one family
805 FOUNTAIN AVENUE
BROOKLYN · East New York-City Line · BIN 3099086
💬 Discuss this project
1930Year Built
1Stories
A9Building Class
R4Zoning
766 sfGross Floor Area
1Units
Miscellaneous one family · Owner of record: BAYTUN NAAFI LLC · 3,840 sf lot · 0.2 FAR built · Flood zone X500
Locations of Work
ArchitectureElectricalMechanicalPlumbingCivilGeneralOther
Filed — no permit issued25p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BRICOLAGE DESIGNS605/05/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BRICOLAGE DESIGNS603/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519505/05/2025
Building Lifecycle
All (30)Special Inspection (30)
05/13/2025
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
05/13/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
05/13/2025
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
05/13/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
05/13/2025
Special inspection requirement — Maintenance information
Younes Abouyaala
05/13/2025
Special inspection requirement — Metering
Younes Abouyaala
05/05/2025
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
05/05/2025
Special inspection requirement — Maintenance information
Younes Abouyaala
05/05/2025
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
05/05/2025
Special inspection requirement — Metering
Younes Abouyaala
05/05/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
05/05/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
05/02/2025
Special inspection requirement — Final
NAVEEN KUMAR
05/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
05/02/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
05/02/2025
Special inspection requirement — Structural Steel - Details
Younes Abouyaala
05/02/2025
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
05/02/2025
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
05/02/2025
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
05/02/2025
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
05/02/2025
Special inspection requirement — Lighting in dwelling units
Younes Abouyaala
05/02/2025
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
11/07/2023
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
11/07/2023
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
11/07/2023
Special inspection requirement — Lighting in dwelling units
Younes Abouyaala
11/07/2023
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
10/09/2023
Special inspection requirement — Structural Steel - Details
Younes Abouyaala
10/09/2023
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
10/09/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
10/09/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
Nothing on file for this building.
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 32
DateRequirementInspectorRole
05/13/2025HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
05/13/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
05/13/2025HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
05/13/2025HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
05/13/2025Maintenance informationYounes Abouyaalaenergy_progress
05/13/2025MeteringYounes Abouyaalaenergy_progress
05/05/2025HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
05/05/2025Maintenance informationYounes Abouyaalaenergy_progress
05/05/2025HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
05/05/2025MeteringYounes Abouyaalaenergy_progress
05/05/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
05/05/2025HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
05/02/2025FinalNAVEEN KUMARprogress
05/02/2025Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
05/02/2025Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
05/02/2025Structural Steel - DetailsYounes Abouyaalaspecial
05/02/2025Energy Code Compliance InspectionsYounes Abouyaalaprogress
05/02/2025Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
05/02/2025HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
05/02/2025HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
05/02/2025Lighting in dwelling unitsYounes Abouyaalaenergy_progress
05/02/2025Insulation placement and R valuesYounes Abouyaalaenergy_progress
11/07/2023HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
11/07/2023Insulation placement and R valuesYounes Abouyaalaenergy_progress
11/07/2023Lighting in dwelling unitsYounes Abouyaalaenergy_progress
Latest 25 of 32.
Nothing on file for this building.