Locations of Work
ArchitectureElectrical
Roof7p · 2 filings · 12 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/07/2022$575K—— → —$666/sf building
10/07/2021$300K—Private party → EMEK 26 LLC$347/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC110/14/2025
MOMENTUM SOLAR105/30/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOLAR CONTRACTING LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854110/14/2025
MXV SIA LLC9281105/30/2025
Building Lifecycle
All (12)Filed (2)Permit Issued (2)Signed Off (1)Objection (2)Special Inspection (5)
05/08/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM.ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THENYC DEPARTMENT OF BUILDINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B01302503-I1
11/03/2025
Permit issued — Solar
B01302503-I1-SL
10/20/2025
Objection resolved — Addressed
10/16/2025
Objection raised — Other
10/14/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM.ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THENYC DEPARTMENT OF BUILDINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B01302503-I1
10/14/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
10/14/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
10/14/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
10/14/2025
Special inspection requirement — Final
TOM PETERSEN
10/14/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
06/05/2025
Permit issued — Solar
B01233770-I1-SL
05/30/2025
Filed — Alteration
INSTALLATION OF SOLAR PANELS, ROOFTOP, RAILED, GRID-TIED, 7 MODULES, 3.01KW
B01233770-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSOLAR CONTRACTING LLC11/03/2025
DOB NOWSolarPermit IssuedMOMENTUM SOLAR06/05/2025
3 projects · most recent 03/14/2026
FiledStatusContractorScope
03/14/2026CompleteVILLAGE ELECTL CONTRS INC—
02/19/2026CompleteSOLAR ELEC CONTRACTNG LLC1 meters
06/27/2025Permit IssuedISLAND ELECTRIC CORP—
1 project · most recent 05/30/2025
FiledStatusContractorScope
05/30/2025Permit IssuedMOMENTUM SOLAR7 panels, 3.01 kw, 123 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
10/14/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
10/14/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
10/14/2025Energy Code Compliance InspectionsTOM PETERSENprogress
10/14/2025FinalTOM PETERSENprogress
10/14/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 23 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/21/2026B01233770-I1Request digital key ↗
08/15/2026B01302503-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION2
06/13/2023340889514Open ↗
05/25/2023340889514Open ↗
▸Seals & Professional Certifications9
▸DOB NOWProgress Inspector Seal & Signature3
09/02/2026B01302503-I1Open ↗
09/02/2026B01302503-I1Open ↗
09/02/2026B01302503-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026B01233770-I1Open ↗
08/13/2026B01302503-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/02/2026B01302503-I1Open ↗
09/02/2026B01302503-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
05/25/2023340889514Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/25/2023340889514Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026B01302503-I1Open ↗
08/13/2026B01233770-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
05/25/2023340889514Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
05/25/2023340889514Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
05/25/2023340889514Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
05/25/2023340889514Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
05/25/2023340889514Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/15/2026B01302503-I1Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
05/25/2023340889514Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
05/25/2023340889514Open ↗