← Back
BuildNYC
Public elementary, junior or senior high
81-14 257TH STREET
QUEENS · BIN 4178464
💬 Discuss this project
1957Year Built
3Stories
W1Building Class
R2AZoning
171,000 sfGross Floor Area
0Units
LL97 Covered7 Active Violations 0 unresolved · 7 paperwork only 2 likely answered ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC Department of Parks and Recreation · 120,000 sf lot · 1.43 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofJ.H.S. 172Under Construction5p · 1 filing · 18 docs
Floor 3J.H.S. 172Under Construction5p · 1 filing · 18 docs
Floor 2J.H.S. 172, Irwin Altman Middle School 172Under Construction5p · 2 filings · 18 docs
Floor 1J.H.S. 172, Irwin Altman Middle School 172Under Construction12p · 4 filings · 18 docs
BasementJ.H.S. 172Under Construction1p · 1 filing · 18 docs
Sub-BasementJ.H.S. 172, Irwin Altman Middle School 172Under Construction7p · 2 filings · 18 docs
Site & exteriorIrwin Altman Middle School 172Under Construction25p · 2 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority7708/26/2026
NYC Department of Education203/22/2026
New York City Public School203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NYMS Consulting212/24/2025
Eme Group/Salas O'Brien205/12/2025
NYC School Construction Authority309/20/2024
Infinity Design410/05/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC School Construction Authority303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Litehouse BuildersScaffold2407/08/2026
Central Mechanical Systemsspecialty_contractor1008/26/2026
Central Mechanical SystemsScaffold308/07/2026
Olympic Plumbing & Heating ServicePlumbing207/02/2026
Sortino JosephElectrical103/21/2026
A & S ElectricElectrical103/21/2026
Raiden ElectricElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Universal Testing and Ins400712/24/2025
Building Lifecycle
All (150)Filed (11)Permit Issued (28)Signed Off (1)Violation (60)Inspection (1)Objection (20)Special Inspection (29)
08/18/2026
Permit issued — General Construction
Q01110919-I1-GC
08/18/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
08/06/2026
Permit issued — Supported Scaffold
Q01125356-I1-SF
08/05/2026
Permit issued — Structural
Q01110919-I1-ST
08/05/2026
Permit issued — Mechanical Systems
Q01110919-S1-MS
07/01/2026
Signed off — Alteration
Q00650387-I1
03/06/2026
Violation issued (ECB, open)
Construction
03/06/2026
Violation issued (ECB, open)
Construction
03/06/2026
Violation issued (ECB, open)
Construction
03/06/2026
Violation issued (ECB, open)
Construction
02/05/2026
Permit issued — Plumbing
Q01110919-S2-PL
01/05/2026
Special inspection requirement — Post-installed Anchors
NELSON LOPEZ
12/24/2025
Filed — Alteration
JHS 172Q, INSTALLATION OF SUPPORTED SCAFFOLD AND STAIR TOWER TO ACCESS THE EXISTING MASONRY CHIMNEY TOP TO INSTALL NEW CHIMNEY LINER/S SUBMITTING ON BEHALF OF CONTRACTOR IN CONJUNCTION WITH DOB # Q01110919. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Q01125356-P1
11/21/2025
Objection resolved — Addressed
11/21/2025
Objection resolved — Addressed
10/10/2025
Permit issued — Construction Fence
Q00650387-I1-FN
10/10/2025
Permit issued — Supported Scaffold
Q00650386-I1-SF
10/09/2025
Violation issued (FDNY_ORDER, closed)
10/09/2025
Violation issued (FDNY_ORDER, closed)
10/09/2025
Violation issued (FDNY_ORDER, closed)
09/25/2025
Permit issued — Structural
Q01110919-I1-GC
09/25/2025
Permit issued — Supported Scaffold
Q01125356-I1-SF
09/25/2025
Permit issued — Structural
Q01110919-I1-ST
09/25/2025
Permit issued — Mechanical Systems
Q01110919-S1-MS
08/25/2025
Violation issued (ECB, open)
Boilers
08/25/2025
Objection resolved — Addressed
07/25/2025
Objection resolved — Addressed
07/25/2025
Objection resolved — Addressed
07/25/2025
Objection resolved — Addressed
07/25/2025
Objection resolved — Addressed
07/25/2025
Objection resolved — Addressed
06/16/2025
Special inspection requirement — Energy Code Compliance Inspections
Asma Hashmi
06/13/2025
Objection resolved — Addressed
06/11/2025
Violation issued (FDNY_ORDER, closed)
06/02/2025
Objection raised — Zoning
06/02/2025
Objection raised — Zoning
06/02/2025
Objection raised — Other
06/02/2025
Objection raised — Scope
05/28/2025
Objection raised — Other
05/28/2025
Objection raised — Zoning
05/28/2025
Objection raised — Zoning
05/28/2025
Objection raised — Plumbing
05/28/2025
Objection raised — Mechanical
05/12/2025
Filed — Alteration
THE SCOPE OF WORK INCLUDES ALL LABOR, MATERIALS, AND EQUIPMENT NECESSARY TO COMPLETE INSTALLATION OF THE SUPPLEMENTAL COOLING SYSTEM IN GYMNASIUM SPACE.
Q01218569-I1
05/12/2025
Filed — Alteration
THE SCOPE OF WORK INCLUDES ALL LABOR, MATERIALS, AND EQUIPMENT NECESSARY TO COMPLETE INSTALLATION OF THE SUPPLEMENTAL COOLING SYSTEM IN CAFETERIA.
Q01218868-I1
05/01/2025
Special inspection requirement — Energy Code Compliance Inspections
04/30/2025
Special inspection requirement — Mechanical Systems
04/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/30/2025
Special inspection requirement — Post-installed Anchors
04/30/2025
Special inspection requirement — Maintenance information
Asma Hashmi
04/30/2025
Special inspection requirement — HVAC-R and service water heating equipment
Asma Hashmi
04/30/2025
Special inspection requirement — HVAC-R and service water heating system controls
Asma Hashmi
04/30/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Asma Hashmi
04/30/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
04/30/2025
Special inspection requirement — Maintenance information
04/30/2025
Special inspection requirement — Final
04/30/2025
Special inspection requirement — Mechanical Systems
04/30/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/30/2025
Special inspection requirement — Post-installed Anchors
04/30/2025
Special inspection requirement — Final
Asma Hashmi
Latest 60 of 150 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedCentral Mechanical Systems08/18/2026
DOB NOWSupported ScaffoldPermit IssuedCentral Mechanical Systems08/06/2026
DOB NOWStructuralPermit IssuedCentral Mechanical Systems08/05/2026
DOB NOWMechanical SystemsPermit IssuedCentral Mechanical Systems08/05/2026
DOB NOWPlumbingPermit IssuedOlympic Plumbing & Heating Service02/05/2026
DOB NOWConstruction FenceSigned-offLitehouse Builders10/10/2025
DOB NOWSupported ScaffoldPermit IssuedLitehouse Builders10/10/2025
DOB NOWStructuralPermit IssuedCentral Mechanical System09/25/2025
DOB NOWSupported ScaffoldPermit IssuedCentral Mechanical System09/25/2025
DOB NOWStructuralPermit IssuedCentral Mechanical System09/25/2025
DOB NOWMechanical SystemsPermit IssuedCentral Mechanical System09/25/2025
DOB NOWSidewalk ShedPermit IssuedLitehouse Builders02/27/2025
DOB NOWPlumbingPermit IssuedOlympic Plumbing & Heating Service11/07/2024
DOB NOWMechanical SystemsPermit IssuedCentral Mechanical System10/15/2024
DOB NOWGeneral ConstructionPermit IssuedCentral Mechanical System10/15/2024
DOB NOWStructuralPermit IssuedCentral Mechanical System10/15/2024
DOB NOWSupported ScaffoldPermit IssuedCentral Mechanical System10/15/2024
DOB NOWSupported ScaffoldPermit IssuedLitehouse Builders09/11/2024
DOB NOWConstruction FenceSigned-offLitehouse Builders09/11/2024
DOB NOWSidewalk ShedPermit IssuedLitehouse Builders02/29/2024
DOB NOWSupported ScaffoldPermit IssuedLitehouse Builders09/20/2023
DOB NOWConstruction FenceSigned-offLitehouse Builders09/20/2023
DOB NOWSupported ScaffoldPermit IssuedLitehouse Builders02/16/2023
DOB NOWSidewalk ShedPermit IssuedLitehouse Builders02/16/2023
DOB NOWConstruction FenceSigned-offLitehouse Builders01/27/2023
DOB NOWSupported ScaffoldPermit IssuedLitehouse Builders02/07/2022
DOB NOWSidewalk ShedPermit IssuedLitehouse Builders02/04/2022
DOB NOWConstruction FenceSigned-offLitehouse Builders01/25/2022
BISOTISSUEDLitehouse Builders07/08/2025
BISOTISSUEDLitehouse Builders07/08/2025
BISMHISSUEDACS System Associates04/25/2025
BISOTISSUEDLitehouse Builders03/19/2025
BISOTISSUEDLitehouse Builders08/07/2024
BISOTISSUEDLitehouse Builders08/07/2024
BISPLISSUEDForsythe P&H08/06/2024
BISMHISSUEDACS System Associates05/02/2024
BISOTISSUEDLitehouse Builders07/13/2023
BISOTISSUEDLitehouse Builders07/13/2023
BISMHISSUEDACS System Associates04/27/2023
BISOTISSUEDLitehouse Builders07/11/2022
+ 38 more permits on file
3 projects · most recent 05/12/2025
Air Conditioning Systems Others Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
05/12/2025——Air Conditioning Systems
Cooling
Fujitsu ASUA36TLAV2 34,000 BTU · Fan Coil Indoor ×10
AOU120RLAVL 120,000 BTU · Condensing Unit ×2
AOU72RLAVL 72,000 BTU · Condensing Unit ×2
05/12/2025——Air Conditioning Systems
Cooling
Fujitsu CASSETTE - AUUB48TLAV2 48,000 BTU · Fan Coil Indoor ×10
AOUA360ULBVG5 360,000 BTU · Condensing Unit ×1
09/20/2024Permit IssuedCentral Mechanical SystemOthers, Ventilation Systems
Ventilation
Us Draft TDF-620 8,500 CFM · Exhaust Fan ×1
1 project · most recent 09/20/2024
Storm
FiledStatusContractorScope
09/20/2024Permit IssuedOlympic Plumbing & Heating ServiceStorm
17 projects · most recent 09/22/2026
General Wiring
FiledStatusContractorScope
09/22/2026Permit IssuedStanco System Electrical ContGeneral Wiring
09/04/2026CompleteCharan Electrical Enterp's—
04/21/2026CompleteGemini Electric Co—
07/09/2025Permit IssuedEverest ElectricGeneral Wiring
02/24/2025Permit IssuedDNR ElectricGeneral Wiring
12/01/2023CompleteAnco Electl Contctng—
08/16/2023CompleteCharan Electrical Enterp's—
08/08/2023CompleteJamcob ElectricGeneral Wiring
06/14/2023CompleteGemini Electric Co—
01/19/2023CompleteCharan Electrical Enterp's—
05/04/2022Permit IssuedStanco System Electrical Cont—
04/07/2022CompleteCharan Electrical Enterp's—
02/03/2022Permit IssuedRaiden Electric—
09/23/2021CompleteCharan Electrical Enterp's—
03/01/2021CompleteLevis Electr'l ContractingGeneral Wiring
1 project · most recent 09/20/2024
Masonry
FiledStatusContractorScope
09/20/2024Permit IssuedCentral Mechanical SystemMasonry
2 projects · most recent 12/24/2025
Scaffold
FiledStatusContractorScope
12/24/2025Permit IssuedCentral Mechanical SystemScaffold
10/05/2022Permit IssuedLitehouse BuildersScaffold
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
08/18/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 29
DateRequirementInspectorRole
01/05/2026Post-installed AnchorsNELSON LOPEZspecial
06/16/2025Energy Code Compliance InspectionsAsma Hashmiprogress
05/01/2025Energy Code Compliance Inspections—progress
04/30/2025Mechanical Systems—special
04/30/2025Fire-Resistant Penetrations and Joints—special
04/30/2025Post-installed Anchors—special
04/30/2025Maintenance informationAsma Hashmienergy_progress
04/30/2025HVAC-R and service water heating equipmentAsma Hashmienergy_progress
04/30/2025HVAC-R and service water heating system controlsAsma Hashmienergy_progress
04/30/2025HVAC-R and service water piping design and insulationAsma Hashmienergy_progress
04/30/2025HVAC-R and service water piping design and insulation—energy_progress
04/30/2025Maintenance information—energy_progress
04/30/2025Final—progress
04/30/2025Mechanical Systems—special
04/30/2025Fire-Resistant Penetrations and Joints—special
04/30/2025Post-installed Anchors—special
04/30/2025FinalAsma Hashmiprogress
04/30/2025HVAC-R and service water heating system controls—energy_progress
04/30/2025HVAC-R and service water heating equipment—energy_progress
09/25/2024Post-installed AnchorsNELSON LOPEZspecial
09/24/2024Energy Code Compliance InspectionsNELSON LOPEZprogress
09/24/2024Electrical motors and elevatorsNELSON LOPEZenergy_progress
09/20/2024HVAC-R and service water piping design and insulationNELSON LOPEZenergy_progress
09/20/2024Maintenance informationNELSON LOPEZenergy_progress
09/19/2024Post-installed AnchorsNELSON LOPEZspecial
Latest 25 of 29.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Irwin Altman Middle School 172EducationSub-basement, Floors 1, 2
Project Q01218569 Alteration · Approved · 05/12/2025
Project Q01218868 Alteration · Approved · 05/12/2025
Project Q01125356 Alteration · Permit Entire · 10/11/2024
Project Q00650378 Alteration · Permit Entire · 01/06/2022
Project Q00650386 Alteration · Permit Entire · 01/06/2022
Project Q00650387 Alteration · LOC Issued · 01/06/2022
J.H.S. 172EducationSub-basement, Floors 1–3, Roof
Project Q01110919 Alteration · Permit Entire · 09/20/2024
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 93 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/26/2026Q00650387-I1Request digital key ↗
08/26/2026Q00650378-I1Request digital key ↗
08/25/2026Q00650386-P1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION3
10/06/2010410070131Open ↗
07/13/2010410070131Open ↗
03/31/2008410070131Open ↗
▸BISWORK PERMIT APPLICATION2
04/15/2008410070131Open ↗
04/15/2008410070131Open ↗
▸Seals & Professional Certifications22
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/26/2026Q00650387-I1Open ↗
08/26/2026Q00650378-I1Open ↗
08/25/2026Q00650386-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/06/2026Q01110919-S1Open ↗
08/26/2026Q01110919-S2Open ↗
08/25/2026Q01125356-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
10/08/2010410070131Open ↗
03/31/2008410070131Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
10/06/2010410070131Open ↗
03/31/2008410070131Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/06/2026Q01110919-S1Open ↗
09/06/2026Q01110919-S1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
03/31/2008410070131Open ↗
▸Trade Schedules & Equipment2
▸BISSCHEDULE B - PLUMBING1
03/31/2008410070131Open ↗
▸BISSELF-CERT PLUMBING NOTICE1
08/21/2008410070131Open ↗
▸Safety & Tenant Protection6
▸DOB NOWNYCSCA - Approved Site Safety Plans6
08/25/2026Q00650386-I1Open ↗
08/13/2026Q00650378-I1Open ↗
08/13/2026Q01125356-P1Open ↗
Showing 3 of 6 on file for this type
▸Environmental & Asbestos1
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
03/31/2008410070131Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
09/28/2021421102452Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
09/28/2021421102452Open ↗
▸Approvals, Objections & Sign-offs33
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter11
08/25/2026Q00650386-I1Open ↗
08/21/2026Q01110919-S1Open ↗
08/21/2026Q01110919-S2Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)11
08/25/2026Q00650386-I1Open ↗
08/20/2026Q01218868-I1Open ↗
08/13/2026Q00650378-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)4
08/26/2026Q00650387-I1Open ↗
08/13/2026Q01110919-S2Open ↗
08/13/2026Q01110919-I1Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
04/14/2008410070131Open ↗
03/31/2008410070131Open ↗
03/14/2008410070131Open ↗
▸DOB NOWDEP Variance (V5) letter3
08/21/2026Q01110919-S2Open ↗
08/21/2026Q01110919-S1Open ↗
08/14/2026Q01110919-I1Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
10/08/2010410070131Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
04/15/2008410070131Open ↗
▸Other Documents10
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal9
08/25/2026Q00650386-I1Open ↗
08/13/2026Q01125356-P1Open ↗
08/13/2026Q00650387-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWNYCSCA Exhibit 21
08/26/2026Q00650387-I1Open ↗