One story - permanent living quarter
81-36 249 STREET
QUEENS · BIN 4174691
💬 Discuss this project
1955Year Built
1.67Stories
A2Building Class
R2AZoning
1,436 sfGross Floor Area
1Units
One story - permanent living quarter · 4,000 sf lot · 0.36 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/09/2024$740K—— → —$515/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC102/21/2025
MUMTAZ ENTERPRISES102/12/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
SHEIKH EXPEDITING203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN SOLAR ELECTL CORPElectrical103/22/2026
GREAT AMERICAN CONSTR SERGeneral Contractor104/09/2026
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272102/21/2025
LUCID BUILDING ENGINEERIN8196102/12/2025
Building Lifecycle
All (13)Filed (2)Permit Issued (2)Signed Off (1)Special Inspection (8)
12/15/2025
Signed off — Alteration
APPLICATION FILE TO INSTALL ONE (1) MASONRY STAIR AND CELLAR EXIT DOOR AT REAR SIDE OF THE BUILDING AND MINOR INTERIOR RENOVATION AT CELLAR FLOOR AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01166596-I1
02/28/2025
Permit issued — Solar
Q01179693-I1-SL
02/24/2025
Permit issued — General Construction
Q01166596-I1-GC
02/21/2025
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
Q01179693-I1
02/12/2025
Filed — Alteration
APPLICATION FILE TO INSTALL ONE (1) MASONRY STAIR AND CELLAR EXIT DOOR AT REAR SIDE OF THE BUILDING AND MINOR INTERIOR RENOVATION AT CELLAR FLOOR AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01166596-I1
02/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
02/11/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
02/11/2025
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
02/11/2025
Special inspection requirement — Final
Walid Abdulla
02/11/2025
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
01/13/2025
Special inspection requirement — Masonry
YUNHO LEE
01/13/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
YUNHO LEE
01/13/2025
Special inspection requirement — Final
Mumtaz Hussain
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC02/28/2025
DOB NOWGeneral ConstructionSigned-offGREAT AMERICAN CONSTR SER02/24/2025
1 project · most recent 02/21/2025
General Wiring
FiledStatusContractorScope
02/21/2025CompleteSUNRUN SOLAR ELECTL CORPGeneral Wiring
1 project · most recent 02/21/2025
FiledStatusContractorScope
02/21/2025Signed-offSUNRUN INSTALLATION SVC23 panels, 9.43 kw, 486.12 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
02/11/2025Fire-Resistant Penetrations and JointsWalid Abdullaspecial
02/11/2025Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
02/11/2025Energy Code Compliance InspectionsWalid Abdullaprogress
02/11/2025FinalWalid Abdullaprogress
02/11/2025Air barrier - visual inspectionWalid Abdullaenergy_progress
01/13/2025MasonryYUNHO LEEspecial
01/13/2025Structural Stability – Alterations of existing buildingsYUNHO LEEspecial
01/13/2025FinalMumtaz Hussainprogress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/20/2026Q01166596-I1Request digital key ↗
08/20/2026Q01179693-I1Request digital key ↗
▸Seals & Professional Certifications10
▸DOB NOWProgress Inspector Seal & Signature4
08/28/2026Q01166596-I1Open ↗
08/27/2026Q01179693-I1Open ↗
08/27/2026Q01179693-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/28/2026Q01166596-I1Open ↗
08/28/2026Q01166596-I1Open ↗
08/27/2026Q01179693-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/13/2026Q01166596-I1Open ↗
08/13/2026Q01179693-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q01179693-I1Open ↗
08/13/2026Q01166596-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01179693-I1Open ↗