← Back
BuildNYC
Primarily 1 family with 1 store or office
8125 7TH AVENUE
BROOKLYN · Dyker Heights · BIN 3151842
💬 Discuss this project
1931Year Built
2Stories
S1Building Class
R5BZoning
3,116 sfGross Floor Area
2Units
Primarily 1 family with 1 store or office · Owner of record: D.K. Realty Holdings · 1,558 sf lot · 2 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 1K.H. Werber Plbg Co7p · 1 filing · 20 docs
CellarK.H. Werber Plbg Co8p · 1 filing · 20 docs
Site & exteriorK.H. Werber Plbg Co10p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Kems Engineering and Construction604/03/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Lewsan Consulting1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Allied Building MaintenanceGeneral Contractor307/08/2026
Allied Building MaintenanceScaffold307/08/2026
K.H. Werber Plumbing CoPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
EC Special Inspections8355504/03/2025
Building Lifecycle
All (49)Filed (6)Permit Issued (6)Signed Off (3)Inspection (5)Special Inspection (29)
06/20/2025
Signed off — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-S2
06/20/2025
Signed off — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-I1
06/20/2025
Signed off — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-S1
04/03/2025
Filed — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-P2
04/03/2025
Special inspection requirement — Maintenance information
Steven Bendoraitis
04/03/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ABDALLAH ELCHERBINI
04/03/2025
Special inspection requirement — HVAC-R and service water heating equipment
Steven Bendoraitis
04/03/2025
Special inspection requirement — Energy Code Compliance Inspections
Steven Bendoraitis
04/03/2025
Special inspection requirement — HVAC-R and service water heating system controls
Steven Bendoraitis
04/03/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Steven Bendoraitis
04/03/2025
Special inspection requirement — Tenant Protection Plan Compliance
ABDALLAH ELCHERBINI
04/02/2025
Filed — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-P1
04/02/2025
Special inspection requirement — Tenant Protection Plan Compliance
04/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ABDALLAH ELCHERBINI
04/02/2025
Special inspection requirement — HVAC-R and service water heating system controls
Steven Bendoraitis
04/02/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Steven Bendoraitis
04/02/2025
Special inspection requirement — Maintenance information
Steven Bendoraitis
04/02/2025
Special inspection requirement — HVAC-R and service water heating equipment
Steven Bendoraitis
04/02/2025
Special inspection requirement — Energy Code Compliance Inspections
Steven Bendoraitis
04/02/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ABDALLAH ELCHERBINI
04/02/2025
Special inspection requirement — Tenant Protection Plan Compliance
ABDALLAH ELCHERBINI
04/02/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Steven Bendoraitis
04/02/2025
Special inspection requirement — HVAC-R and service water heating equipment
Steven Bendoraitis
04/02/2025
Special inspection requirement — Maintenance information
Steven Bendoraitis
04/02/2025
Special inspection requirement — HVAC-R and service water heating system controls
Steven Bendoraitis
03/27/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
03/27/2025
Special inspection requirement — Tenant Protection Plan Compliance
03/27/2025
Special inspection requirement — HVAC-R and service water heating system controls
Steven Bendoraitis
03/27/2025
Special inspection requirement — Maintenance information
Steven Bendoraitis
03/27/2025
Special inspection requirement — HVAC-R and service water heating equipment
Steven Bendoraitis
03/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ABDALLAH ELCHERBINI
03/27/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Steven Bendoraitis
03/24/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/16/2024
Permit issued — General Construction
B01002663-I1-GC
09/16/2024
Permit issued — Construction Fence
B01002663-S3-FN
07/03/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/03/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
05/16/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/25/2024
Permit issued — Construction Fence
B01002663-S3-FN
04/25/2024
Permit issued — General Construction
B01002663-I1-GC
04/03/2024
Permit issued — Boiler Equipment
B01002663-S2-BE
04/02/2024
Permit issued — Plumbing
B01002663-S1-PL
03/27/2024
Filed — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-S2
03/22/2024
Filed — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-I1
03/22/2024
Filed — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-S1
03/22/2024
Filed — Alteration
GAS PIPING FOR FOUR (4) BOILERS AND FOUR (4) WATER HEATERS, REGISTER FOUR (4 )WATER HEATERS; INSTALL TWO (2) FIXTURE TOILET IN CELLAR, RELOCATE A SINK & CREATE A TWO (2) FIXTURE ADA TOILET ON THE 1st FLOOR
B01002663-S3
03/21/2024
Special inspection requirement — Energy Code Compliance Inspections
Steven Bendoraitis
03/21/2024
Special inspection requirement — Tenant Protection Plan Compliance
ABDALLAH ELCHERBINI
02/07/2024
Special inspection requirement — Final
Steven Bendoraitis
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offAllied Building Maintenance09/16/2024
DOB NOWConstruction FencePermit IssuedAllied Building Maintenance09/16/2024
DOB NOWConstruction FencePermit IssuedAllied Building Maintenance04/25/2024
DOB NOWGeneral ConstructionSigned-offAllied Building Maintenance04/25/2024
DOB NOWBoiler EquipmentSigned-offK.H. Werber Plumbing Co04/03/2024
DOB NOWPlumbingSigned-offK.H. Werber Plumbing Co04/02/2024
1 project · most recent 06/18/2024
General Wiring
FiledStatusContractorScope
06/18/2024Permit IssuedAbilene ElectricGeneral Wiring
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
03/27/2025Pass-Final Boiler Equipment InspectionPassView ↗
03/24/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/03/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/03/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/16/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 29
DateRequirementInspectorRole
04/03/2025Maintenance informationSteven Bendoraitisenergy_progress
04/03/2025Fire-Resistant Penetrations and JointsABDALLAH ELCHERBINIspecial
04/03/2025HVAC-R and service water heating equipmentSteven Bendoraitisenergy_progress
04/03/2025Energy Code Compliance InspectionsSteven Bendoraitisprogress
04/03/2025HVAC-R and service water heating system controlsSteven Bendoraitisenergy_progress
04/03/2025HVAC-R and service water piping design and insulationSteven Bendoraitisenergy_progress
04/03/2025Tenant Protection Plan ComplianceABDALLAH ELCHERBINIspecial
04/02/2025Tenant Protection Plan Compliance—special
04/02/2025Fire-Resistant Penetrations and JointsABDALLAH ELCHERBINIspecial
04/02/2025HVAC-R and service water heating system controlsSteven Bendoraitisenergy_progress
04/02/2025HVAC-R and service water piping design and insulationSteven Bendoraitisenergy_progress
04/02/2025Maintenance informationSteven Bendoraitisenergy_progress
04/02/2025HVAC-R and service water heating equipmentSteven Bendoraitisenergy_progress
04/02/2025Energy Code Compliance InspectionsSteven Bendoraitisprogress
04/02/2025Fire-Resistant Penetrations and JointsABDALLAH ELCHERBINIspecial
04/02/2025Tenant Protection Plan ComplianceABDALLAH ELCHERBINIspecial
04/02/2025HVAC-R and service water piping design and insulationSteven Bendoraitisenergy_progress
04/02/2025HVAC-R and service water heating equipmentSteven Bendoraitisenergy_progress
04/02/2025Maintenance informationSteven Bendoraitisenergy_progress
04/02/2025HVAC-R and service water heating system controlsSteven Bendoraitisenergy_progress
03/27/2025Tenant Protection Plan Compliance—special
03/27/2025HVAC-R and service water heating system controlsSteven Bendoraitisenergy_progress
03/27/2025Maintenance informationSteven Bendoraitisenergy_progress
03/27/2025HVAC-R and service water heating equipmentSteven Bendoraitisenergy_progress
03/27/2025Fire-Resistant Penetrations and JointsABDALLAH ELCHERBINIspecial
Latest 25 of 29.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
K.H. Werber Plbg CoIndustrial / WarehouseCellar, Floor 1
Project B01002663 Alteration · Permit Entire · 03/22/2024
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 44 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/25/2026B01002663-I1Request digital key ↗
08/25/2026B01002663-P1Request digital key ↗
08/25/2026B01002663-P2Request digital key ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications33
▸DOB NOWProgress Inspector Seal & Signature20
09/23/2026B01002663-S2Open ↗
09/23/2026B01002663-S2Open ↗
09/23/2026B01002663-S2Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/23/2026B01002663-S2Open ↗
09/23/2026B01002663-S2Open ↗
08/27/2026B01002663-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/25/2026B01002663-S2Open ↗
08/25/2026B01002663-S1Open ↗
08/13/2026B01002663-I1Open ↗
Showing 3 of 6 on file for this type
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/25/2026B01002663-S2Open ↗
08/25/2026B01002663-S1Open ↗
08/13/2026B01002663-P1Open ↗
Showing 3 of 5 on file for this type