| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/29/2020 | $1.3M | — | Private party → Private party | $419/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CD ARCHITECT STUDIO, LLP | 6 | 07/02/2025 |
| NY BUILDING ASSOCIATES INC | 1 | 04/14/2025 |
| AUTOMATED DESIGN ENGINEERING, PLLC | 1 | 06/24/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| CD ARCHITECT STUDIO | 6 | 03/21/2026 |
| BROOKLYN SOLARWORKS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MROD CONSTRUCTION INC | General Contractor | 3 | 07/08/2026 |
| BROOKLYN SOLARWORKS LLC | General Contractor | 1 | 07/08/2026 |
| EMPIRE PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| STUDIO NYANDAK ARCHITECTU | 8378 | 4 | 07/02/2025 |
| NKM ENGINEERING PLLC | 6244 | 1 | 04/14/2025 |
| CD ARCHITECT STUDIO, LLP | 2573 | 2 | 01/25/2024 |
| AUTOMATED DESIGN CONSULTA | 895 | 1 | 06/24/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | BROOKLYN SOLARWORKS LLC | 04/16/2025 |
| DOB NOW | General Construction | Permit Issued | MROD CONSTRUCTION INC | 10/24/2023 |
| DOB NOW | General Construction | Permit Issued | MROD CONSTRUCTION INC | 08/17/2022 |
| DOB NOW | Plumbing | Signed-off | EMPIRE PLUMBING INC | 01/05/2022 |
| DOB NOW | General Construction | Permit Issued | MROD CONSTRUCTION INC | 09/01/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/24/2021 | — | — | Air Conditioning Systems, Heating Systems | Cooling Mitsubishi Electric MUZ-FS18NAH 17,200 BTU · Heat Pump Outdoor ×1 PUMY-HP48NKMU1 48,000 BTU · Vrf Outdoor ×1 Heating Mitsubishi Electric MUZ-FS18NAH 19,000 BTU · Heat Pump Outdoor ×1 PUMY-HP48NKMU1 54,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2025 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| 03/14/2023 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/27/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/08/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/08/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 11/02/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/19/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/19/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/03/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/08/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |
| 04/08/2025 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 04/08/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 04/08/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 04/08/2025 | Final | NARESH MAHANGU | progress |
| 01/25/2024 | Maintenance information | TENZIN NYANDAK | energy_progress |
| 01/25/2024 | Fire-Resistant Penetrations and Joints | TENZIN NYANDAK | special |
| 01/25/2024 | Energy Code Compliance Inspections | TENZIN NYANDAK | progress |
| 06/14/2021 | HVAC-R and service water piping design and insulation | Gregory Mortman | energy_progress |
| 06/14/2021 | HVAC-R and service water heating equipment | Gregory Mortman | energy_progress |
| 06/14/2021 | Energy Code Compliance Inspections | Gregory Mortman | progress |
| 06/14/2021 | HVAC-R and service water heating system controls | Gregory Mortman | energy_progress |
| 05/14/2021 | Maintenance information | Peter D'Angelo | energy_progress |
| 05/14/2021 | Fire-Resistant Penetrations and Joints | Peter D'Angelo | special |
| 05/14/2021 | Energy Code Compliance Inspections | Peter D'Angelo | progress |
| 04/22/2021 | Mechanical Systems | Gregory Mortman | special |
| 04/22/2021 | Final | Gregory Mortman | progress |