← Back
BuildNYC
Two stories - detached, small or mid-size
82-15 234TH STREET
QUEENS · Bellerose · BIN 4166174
💬 Discuss this project
1930Year Built
2Stories
A1Building Class
R1-2AZoning
4,000 sfGross Floor Area
1Units
0 Active ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 6,000 sf lot · 0.67 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofResidential solar electric generation array installation1 filing · 4 docs
Floor 18p · 2 filings · 20 docs
Cellar10p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
To the Owner of 82-15 234103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Grace702/17/2025
Momentum Solar106/10/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Architectual Concept1403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Mark Contracting NYGeneral Contractor207/08/2026
All Ways Electric Corp.wElectrical103/22/2026
BR ElectricalElectrical103/22/2026
Johnny's P&H ContractingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Grace Engineering2176702/17/2025
MXV Sia9281106/10/2024
Building Lifecycle
All (49)Filed (8)Permit Issued (4)Signed Off (3)Violation (1)Inspection (6)Special Inspection (27)
05/09/2025
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 31 Panels, 12.71 kW
Q01063307-I1
03/11/2025
Signed off — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-I1
03/11/2025
Signed off — Alteration
Interior renovation to convert half bath in cellar to full bathroom, replace existing 1st floor bathroom fixtures and smoked damage existing first floor joist.
Q01053932-I1
03/05/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
02/28/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
02/18/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TARIQ SIDDIQUI
02/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
02/18/2025
Special inspection requirement — Final
TARIQ SIDDIQUI
02/18/2025
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
02/18/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
02/18/2025
Special inspection requirement — Fire-Resistance Rated Construction
TARIQ SIDDIQUI
02/17/2025
Filed — Alteration
Interior renovation to convert half bath in cellar to full bathroom, replace existing 1st floor bathroom fixtures and smoked damage existing first floor joist.
Q01053932-P1
02/17/2025
Special inspection requirement — Final
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — Fire-Resistance Rated Construction
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TARIQ SIDDIQUI
02/17/2025
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
02/13/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
01/23/2025
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-P4
01/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
01/23/2025
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
01/23/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
01/08/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
01/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
01/08/2025
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
12/17/2024
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-P3
12/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
12/17/2024
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
12/17/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
11/21/2024
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-P2
11/21/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
11/21/2024
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
11/21/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
08/30/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
08/19/2024
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-P1
08/02/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/02/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
07/30/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
TARIQ SIDDIQUI
07/30/2024
Special inspection requirement — Energy Code Compliance Inspections
TARIQ SIDDIQUI
07/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
TARIQ SIDDIQUI
07/22/2024
Permit issued — Plumbing
Q01053940-I1-PL
07/12/2024
Permit issued — General Construction
Q01053932-I1-ST
07/12/2024
Permit issued — Structural
Q01053932-I1-GC
07/01/2024
Filed — Alteration
APPLICATION FILING FOR INTERIOR RENOVATION TO CONVERT EXISTING HALF BATHROOM INTO THREE FIXTURES BATHROOM IN THE CELLAR, REPLACEMENT OF BATHTUB WITH SHOWER AT FIRST FLOOR. INSTALLATION OF NEW WASHER, GAS DRYER AND BBQ FIXTURE AS PER DRAWING.
Q01053940-I1
07/01/2024
Filed — Alteration
Interior renovation to convert half bath in cellar to full bathroom, replace existing 1st floor bathroom fixtures and smoked damage existing first floor joist.
Q01053932-I1
06/12/2024
Permit issued — Solar
Q01063307-I1-SL
06/10/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 31 Panels, 12.71 kW
Q01063307-I1
11/13/2001
Violation issued (ECB, closed)
Site Safety
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offJohnny Nanhu07/22/2024
DOB NOWGeneral ConstructionSigned-offMark Contracting NY07/12/2024
DOB NOWStructuralSigned-offMark Contracting NY07/12/2024
DOB NOWSolarSigned-offMomentum Solar06/12/2024
BISPLISSUEDJohnny's P&H Contracting02/05/2001
BIS—ISSUEDShell & B Construction01/11/2001
BISEQISSUEDShell & B Construction01/11/2001
BIS—ISSUEDShell & B Construction12/11/2000
BISEQISSUEDShell & B Construction12/11/2000
3 projects · most recent 09/09/2024
General Wiring Lighting
FiledStatusContractorScope
09/09/2024CompleteBR ElectricalGeneral Wiring, Lighting
06/07/2024CompleteIsland Electric—
03/13/2024Permit IssuedAll Ways Electric Corp.w—
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
03/05/2025Pass-Final General Construction Non-Directive 14PassView ↗
02/28/2025Fail-Final General Construction Non-Directive 14FailView ↗
02/13/2025Fail-Final General Construction Non-Directive 14FailView ↗
08/30/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/02/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/02/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 27
DateRequirementInspectorRole
02/18/2025Structural Stability – Alterations of existing buildingsTARIQ SIDDIQUIspecial
02/18/2025Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
02/18/2025FinalTARIQ SIDDIQUIprogress
02/18/2025Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
02/18/2025HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
02/18/2025Fire-Resistance Rated ConstructionTARIQ SIDDIQUIprogress
02/17/2025FinalTARIQ SIDDIQUIprogress
02/17/2025Fire-Resistance Rated ConstructionTARIQ SIDDIQUIprogress
02/17/2025HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
02/17/2025Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
02/17/2025Structural Stability – Alterations of existing buildingsTARIQ SIDDIQUIspecial
02/17/2025Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
01/23/2025Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
01/23/2025Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
01/23/2025HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
01/08/2025HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
01/08/2025Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
01/08/2025Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
12/17/2024Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
12/17/2024Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
12/17/2024HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
11/21/2024Fire-Resistant Penetrations and JointsTARIQ SIDDIQUIspecial
11/21/2024Energy Code Compliance InspectionsTARIQ SIDDIQUIprogress
11/21/2024HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
07/30/2024HVAC-R and service water piping design and insulationTARIQ SIDDIQUIenergy_progress
Latest 25 of 27.
▾Documents — 46 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/22/2026Q01063307-I1Request digital key ↗
08/22/2026Q01053940-P1Request digital key ↗
08/22/2026Q01053940-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸Zoning, Tax Lot & Property Records7
▸DOB NOWRestrictive Declaration/Easement 17
08/13/2026Q01053940-P3Open ↗
08/13/2026Q01053940-P4Open ↗
08/13/2026Q01053932-P1Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications29
▸DOB NOWProgress Inspector Seal & Signature14
10/03/2026Q01053940-I1Open ↗
10/03/2026Q01053940-I1Open ↗
10/03/2026Q01053932-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/22/2026Q01063307-I1Open ↗
08/22/2026Q01053940-P1Open ↗
08/22/2026Q01053940-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
10/03/2026Q01053940-I1Open ↗
10/03/2026Q01053932-I1Open ↗
09/29/2026Q01053940-P1Open ↗
Showing 3 of 7 on file for this type
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/22/2026Q01063307-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01063307-I1Open ↗