| Owner | Filings | Most Recent |
|---|---|---|
| 82-19 NB | 69 | 09/01/2026 |
| SAFE-SHIELD ENTERPRISES | 10 | 07/08/2026 |
| CELATECH CONSTRUCTION COR | 6 | 03/22/2026 |
| CONSTRUCTION COR CELATECH | 3 | 03/22/2026 |
| COR CELATECH CONSTRUCTION | 3 | 03/22/2026 |
| SAFE-SHEILD ENTERPRISE IN | 1 | 03/22/2026 |
| ECI CONWAY INC | 1 | 03/22/2026 |
| SERVICE CORP INC | 2 | 03/21/2026 |
| SERVICE CORP | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/04/2021 | $2.3M | — | SCI FUNERAL SERVICES OF NEW YORK, INC → 82-19 NB LLC | $318/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FRANK PETRUSO ARCHITECT PC | 6 | 07/23/2026 |
| NAUDUS PROFESSIONAL ENGINEERING | 7 | 05/14/2026 |
| VATCHE GHAZARIAN, PE | 6 | 11/05/2024 |
| ASHRAF CORP | 2 | 04/28/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| FRANK PETRUSORA AOL COM | 8 | 03/21/2026 |
| DANICO SERVICES | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CELATECH CONSTRUCTION COR | General Contractor | 50 | 07/08/2026 |
| SAFE-SHEILD ENTERPRISE IN | General Contractor | 6 | 07/08/2026 |
| MORELL BUILDERS INC | General Contractor | 3 | 03/21/2026 |
| JUST PLBG & HTG INC | Plumbing | 2 | 07/04/2026 |
| KWONG MING ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| AQUEDUCT MECHANICAL CORP | Fire Protection | 1 | 07/02/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| IP CONCRETE TESTING AND I | 6252 | 20 | 07/23/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | CELATECH CONSTRUCTION COR | 01/07/2026 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 11/12/2024 |
| DOB NOW | Plumbing | Signed-off | MOHAMED ABDELRAZEK | 09/26/2024 |
| DOB NOW | General Construction | Permit Issued | CELATECH CONSTRUCTION COR | 05/31/2024 |
| DOB NOW | General Construction | Permit Issued | CELATECH CONSTRUCTION COR | 04/25/2024 |
| DOB NOW | Construction Fence | Signed-off | CELATECH CONSTRUCTION COR | 04/25/2024 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 04/23/2024 |
| DOB NOW | Plumbing | Signed-off | AQUEDUCT MECHANICAL CORP | 01/25/2024 |
| DOB NOW | General Construction | Permit Issued | CELATECH CONSTRUCTION COR | 05/18/2023 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 05/16/2023 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 05/16/2023 |
| DOB NOW | Construction Fence | Signed-off | CELATECH CONSTRUCTION COR | 05/15/2023 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 05/15/2023 |
| DOB NOW | General Construction | Permit Issued | CELATECH CONSTRUCTION COR | 04/27/2023 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 04/25/2023 |
| DOB NOW | Construction Fence | Signed-off | CELATECH CONSTRUCTION COR | 04/24/2023 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 04/24/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CELATECH CONSTRUCTION COR | 04/24/2023 |
| DOB NOW | Structural | Signed-off | CELATECH CONSTRUCTION COR | 03/22/2023 |
| DOB NOW | General Construction | Permit Issued | CELATECH CONSTRUCTION COR | 03/22/2023 |
| DOB NOW | Construction Fence | Signed-off | CELATECH CONSTRUCTION COR | 03/10/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CELATECH CONSTRUCTION COR | 03/09/2023 |
| DOB NOW | Foundation | Signed-off | CELATECH CONSTRUCTION COR | 03/09/2023 |
| DOB NOW | Foundation | Signed-off | CELATECH CONSTRUCTION COR | 03/09/2023 |
| DOB NOW | Structural | Signed-off | CELATECH CONSTRUCTION COR | 03/09/2023 |
| DOB NOW | Supported Scaffold | Signed-off | SAFE-SHEILD ENTERPRISE IN | 02/06/2023 |
| DOB NOW | Foundation | Signed-off | CELATECH CONSTRUCTION COR | 02/03/2023 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 02/03/2023 |
| DOB NOW | Sprinklers | Signed-off | MOHAMED ABDELRAZEK | 01/24/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFE-SHEILD ENTERPRISE IN | 01/06/2023 |
| DOB NOW | Foundation | Signed-off | CELATECH CONSTRUCTION COR | 01/04/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CELATECH CONSTRUCTION COR | 01/04/2023 |
| DOB NOW | Construction Fence | Signed-off | CELATECH CONSTRUCTION COR | 09/13/2022 |
| DOB NOW | General Construction | Permit Issued | CELATECH CONSTRUCTION COR | 08/04/2022 |
| DOB NOW | Structural | Signed-off | CELATECH CONSTRUCTION COR | 08/03/2022 |
| DOB NOW | General Construction | Signed-off | CELATECH CONSTRUCTION COR | 05/06/2022 |
| DOB NOW | Supported Scaffold | Signed-off | SAFE-SHEILD ENTERPRISE IN | 04/29/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFE-SHEILD ENTERPRISE IN | 04/22/2022 |
| DOB NOW | General Construction | Signed-off | MORELL BUILDERS INC | 02/23/2022 |
| BIS | MH | ISSUED | AIRDEX INC | 09/09/2004 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/14/2026 | Signed-off | CELATECH CONSTRUCTION COR | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/11/2025 | Signed-off | AQUEDUCT MECHANICAL CORP | 270 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/11/2025 | Signed-off | 2M MECHANICAL LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/28/2026 | Complete | QEC ELECTRICAL SVCE CORP | General Wiring |
| 05/16/2023 | Permit Issued | KWONG MING ELECTRIC INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/08/2026 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 03/30/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/20/2026 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 09/18/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/15/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/10/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/22/2025 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 12/16/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 11/29/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 01/02/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/28/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/21/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/08/2026 | Wall Panels, Curtain Walls, and Veneers | INDARDEO PARBHUNATH | special |
| 07/08/2026 | Air barrier - visual inspection | Vatche Ghazarian | energy_progress |
| 07/08/2026 | Fenestration and door U-factor and product ratings | Vatche Ghazarian | energy_progress |
| 07/08/2026 | Masonry | INDARDEO PARBHUNATH | special |
| 07/08/2026 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 07/08/2026 | Exterior Insulation and Finish Systems (EIFS) | INDARDEO PARBHUNATH | special |
| 07/08/2026 | Fenestration air leakage | Vatche Ghazarian | energy_progress |
| 07/08/2026 | Insulation placement and R values | Vatche Ghazarian | energy_progress |
| 05/18/2026 | HVAC-R and service water heating equipment | Vatche Ghazarian | energy_progress |
| 05/18/2026 | HVAC-R and service water heating system controls | Vatche Ghazarian | energy_progress |
| 05/18/2026 | Interior lighting power | Vatche Ghazarian | energy_progress |
| 05/18/2026 | Lighting controls | Vatche Ghazarian | energy_progress |
| 05/18/2026 | Shutoff dampers | Vatche Ghazarian | energy_progress |
| 05/18/2026 | HVAC-R and service water piping design and insulation | Vatche Ghazarian | energy_progress |
| 05/18/2026 | Maintenance information | Vatche Ghazarian | energy_progress |
| 05/18/2026 | Final | Vatche Ghazarian | progress |
| 05/18/2026 | Energy Code Compliance Inspections | Vatche Ghazarian | progress |
| 05/18/2026 | Mechanical Systems | INDARDEO PARBHUNATH | special |
| 05/18/2026 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 10/11/2025 | Sprinkler Systems | INDARDEO PARBHUNATH | special |
| 10/11/2025 | Post-installed Anchors | INDARDEO PARBHUNATH | special |
| 10/11/2025 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 10/02/2025 | Air barrier - visual inspection | Vatche Ghazarian | energy_progress |
| 10/02/2025 | Fenestration and door U-factor and product ratings | Vatche Ghazarian | energy_progress |
| 10/02/2025 | Insulation placement and R values | Vatche Ghazarian | energy_progress |