← Back
Two stories - detached, small or mid-size
82-22 214 STREET
QUEENS · BIN 4165116
💬 Discuss this project
1935Year Built
2Stories
A1Building Class
R2AZoning
1,632 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Two stories - detached, small or mid-size · 5,000 sf lot · 0.33 FAR built · Flood zone X
Locations of Work
PlumbingCivil
Permit Issued — active, not yet Signed-off
RoofUnder Construction1 filing · 20 docs
Floor 2Under Construction1p · 1 filing · 20 docs
Floor 1Under Construction1p · 1 filing · 20 docs
CellarUnder Construction1p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/05/2025$1.4M—— → —$864/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ALBERT ARONOV ARCHITECT212/22/2025
SIRA ENGINEERING, PLLC111/05/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SB RENOVATION & MODELINGGeneral Contractor207/08/2026
NASARIN CONTRACTING CORPGeneral Contractor104/09/2026
FOUR POINTS P & H CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ALBERT ARONOV772312/22/2025
TRIANGLE INSPECTION & TES7495112/22/2025
AA BUILDING & INSPECTION1519112/12/2025
Building Lifecycle
All (60)Filed (3)Permit Issued (4)Violation (2)Inspection (3)Objection (18)Special Inspection (30)
08/07/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/20/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
06/17/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
04/15/2026
Permit issued — Plumbing
Q01332898-S1-PL
03/30/2026
Permit issued — Earth Work
Q01332898-I1-GC-CX
03/30/2026
Permit issued — Construction Fence
Q01314573-I1-FN
02/23/2026
Objection resolved — Addressed
02/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Albert Aronov
02/20/2026
Objection resolved — Addressed
02/20/2026
Objection resolved — Addressed
02/03/2026
Objection resolved — Addressed
02/03/2026
Objection resolved — Addressed
01/26/2026
Objection resolved — Addressed
01/26/2026
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
Rajasekhar Sakhamuri
01/14/2026
Objection raised — Plumbing
01/14/2026
Objection raised — Plumbing
01/14/2026
Objection raised — Plumbing
01/11/2026
Objection resolved — Addressed
01/11/2026
Objection resolved — Addressed
01/11/2026
Objection resolved — Addressed
01/08/2026
Objection raised — Zoning
01/08/2026
Objection raised — Admin
01/08/2026
Objection raised — Energy
01/08/2026
Objection raised — Scope
01/08/2026
Objection raised — Zoning
01/08/2026
Objection raised — Structural
12/22/2025
Filed — Alteration
Plumbing work related to alteration of one family dwelling.
Q01332898-S1
12/22/2025
Special inspection requirement — HVAC-R and service water heating equipment
Albert Aronov
12/22/2025
Special inspection requirement — Maintenance information
Albert Aronov
12/22/2025
Special inspection requirement — HVAC-R and service water heating system controls
Albert Aronov
12/22/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Albert Aronov
12/22/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Albert Aronov
12/22/2025
Special inspection requirement — Energy Code Compliance Inspections
Albert Aronov
12/12/2025
Filed — Alteration
Plumbing work related to alteration of one family dwelling.
Q01332898-I1
12/12/2025
Special inspection requirement — Structural Steel - High Strength Bolting
Albert Aronov
12/11/2025
Special inspection requirement — Final
Albert Aronov
12/11/2025
Special inspection requirement — Footing and Foundation
Albert Aronov
12/11/2025
Special inspection requirement — Structural Wood Frame
Albert Aronov
12/11/2025
Special inspection requirement — Energy Code Compliance Inspections
Albert Aronov
12/11/2025
Special inspection requirement — Fire-Resistance Rated Construction
Albert Aronov
12/11/2025
Special inspection requirement — Electric vehicle service equipment requirements
Albert Aronov
12/11/2025
Special inspection requirement — Interior lighting power
Albert Aronov
12/11/2025
Special inspection requirement — HVAC-R and service water heating system controls
Albert Aronov
12/11/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Albert Aronov
12/11/2025
Special inspection requirement — Air barrier - visual inspection
Albert Aronov
12/11/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Albert Aronov
12/11/2025
Special inspection requirement — Fenestration areas
Albert Aronov
12/11/2025
Special inspection requirement — Fenestration air leakage
Albert Aronov
12/11/2025
Special inspection requirement — HVAC-R and service water heating equipment
Albert Aronov
12/11/2025
Special inspection requirement — Insulation placement and R values
Albert Aronov
12/11/2025
Special inspection requirement — Maintenance information
Albert Aronov
12/11/2025
Special inspection requirement — Permanent certificate
Albert Aronov
12/11/2025
Special inspection requirement — Metering
Albert Aronov
12/11/2025
Special inspection requirement — Mechanical Systems
Albert Aronov
12/11/2025
Special inspection requirement — Concrete - Cast-In-Place
Albert Aronov
12/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Albert Aronov
11/13/2025
Permit issued — Construction Fence
Q01314573-I1-FN
11/12/2025
Violation issued (ECB, closed)
Construction
11/05/2025
Filed — Alteration
Temporary Construction Fence
Q01314573-I1
10/29/2002
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedFOUR POINTS P & H CORP04/15/2026
DOB NOWEarth WorkPermit IssuedSB RENOVATION & MODELING03/30/2026
DOB NOWConstruction FencePermit IssuedSB RENOVATION & MODELING03/30/2026
DOB NOWConstruction FencePermit IssuedNASARIN CONTRACTING CORP11/13/2025
BISOTISSUEDONFORCE SOLAR, INC03/10/2015
BISMHISSUEDS & M DUCT WORK LLC02/11/2004
BISPLISSUEDRAO PLUMBING & HEATING LLC03/26/2002
BIS—ISSUEDMORGAN HOWARD HOLDING CORP03/12/2002
1 job · most recent 12/22/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
12/22/2025Permit IssuedFOUR POINTS P & H CORPGas, Storm, Water/Sanitary
3 jobs · most recent 07/24/2026
General Wiring
FiledStatusContractorScope
07/24/2026Permit IssuedJOSEPH WEINSTEIN ELECTRIC1 meters
04/15/2026Permit IssuedGREEN POWER ELECTRIC CORPGeneral Wiring
12/30/2025Permit IssuedAGG CONTROLS ELECT CORPGeneral Wiring
1 job · most recent 11/05/2025
Fence
FiledStatusContractorScope
11/05/2025Permit IssuedSB RENOVATION & MODELINGFence
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
08/07/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
07/20/2026Pass-Final PL - UndergroundPassView ↗
06/17/2026Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 35
DateRequirementInspectorRole
02/23/2026Fire-Resistant Penetrations and JointsAlbert Aronovspecial
01/26/2026Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesRajasekhar Sakhamurispecial
12/22/2025HVAC-R and service water heating equipmentAlbert Aronovenergy_progress
12/22/2025Maintenance informationAlbert Aronovenergy_progress
12/22/2025HVAC-R and service water heating system controlsAlbert Aronovenergy_progress
12/22/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationAlbert Aronovspecial
12/22/2025HVAC-R and service water piping design and insulationAlbert Aronovenergy_progress
12/22/2025Energy Code Compliance InspectionsAlbert Aronovprogress
12/12/2025Structural Steel - High Strength BoltingAlbert Aronovspecial
12/11/2025FinalAlbert Aronovprogress
12/11/2025Footing and FoundationAlbert Aronovprogress
12/11/2025Structural Wood FrameAlbert Aronovprogress
12/11/2025Energy Code Compliance InspectionsAlbert Aronovprogress
12/11/2025Fire-Resistance Rated ConstructionAlbert Aronovprogress
12/11/2025Electric vehicle service equipment requirementsAlbert Aronovenergy_progress
12/11/2025Interior lighting powerAlbert Aronovenergy_progress
12/11/2025HVAC-R and service water heating system controlsAlbert Aronovenergy_progress
12/11/2025Fenestration and door U-factor and product ratingsAlbert Aronovenergy_progress
12/11/2025Air barrier - visual inspectionAlbert Aronovenergy_progress
12/11/2025HVAC-R and service water piping design and insulationAlbert Aronovenergy_progress
12/11/2025Fenestration areasAlbert Aronovenergy_progress
12/11/2025Fenestration air leakageAlbert Aronovenergy_progress
12/11/2025HVAC-R and service water heating equipmentAlbert Aronovenergy_progress
12/11/2025Insulation placement and R valuesAlbert Aronovenergy_progress
12/11/2025Maintenance informationAlbert Aronovenergy_progress
Latest 25 of 35.
▾Documents — 48 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/18/2026Q01314573-I1Request digital key ↗
08/18/2026Q01332898-S1Request digital key ↗
08/18/2026Q01332898-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
12/30/2014440189341Open ↗
▸BISWORK PERMIT APPLICATION1
03/10/2015440189341Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01332898-I1Open ↗
▸Seals & Professional Certifications16
▸DOB NOWSpecial Inspector Seal & Signature7
08/27/2026Q01332898-I1Open ↗
08/27/2026Q01332898-I1Open ↗
08/27/2026Q01332898-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
08/27/2026Q01332898-I1Open ↗
08/27/2026Q01332898-I1Open ↗
08/27/2026Q01332898-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/13/2026Q01332898-S1Open ↗
08/13/2026Q01332898-I1Open ↗
08/13/2026Q01314573-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
12/30/2014440189341Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026Q01332898-I1Open ↗
08/13/2026Q01332898-S1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
12/30/2014440189341Open ↗
▸Energy Compliance5
▸BISSOLAR TAX ABATEMENT APPLICATION2
07/18/2016440189341Open ↗
12/30/2014440189341Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
07/18/2016440189341Open ↗
03/02/2015440189341Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/18/2016440189341Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY2
07/18/2016440189341Open ↗
03/02/2015440189341Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q01332898-I1Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026Q01332898-I1Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
07/18/2016440189341Open ↗
▸BISThird Party Electrical Signoff Compliance Report1
07/18/2016440189341Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
07/18/2016440189341Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
07/18/2016440189341Open ↗
12/30/2014440189341Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION4
12/22/2016440189341Open ↗
02/11/2016440189341Open ↗
01/22/2016440189341Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
12/30/2014440189341Open ↗
▸Other Documents4
▸DOB NOWPlot Diagram1
08/13/2026Q01332898-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01332898-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01332898-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q01332898-I1Open ↗