← Back
Five to six families
829 HALSEY STREET
BROOKLYN · BIN 3039971
💬 Discuss this project
1910Year Built
3Stories
C2Building Class
R6BZoning
4,850 sfGross Floor Area
6Units
Rent Stabilized67 Open Violations ▸FDNY Report ↗
Five to six families · Owner of record: 829 HALSEY LLC · 2,600 sf lot · 1.87 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalFire ProtectionOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction10p · 1 filing · 16 docs
Cellar4p · 1 filing · 4 docs
Sub-BasementUnder Construction1 filing · 16 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
829 HALSEY LLC203/22/2026
KG MANAGEMENT CNSLTNG103/22/2026
KG MANAGEMENT CNSLTING IN203/22/2026
829 HALSEY OWNER503/22/2026
IWC 827-829 HALSEY STREET LLC403/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/06/2021$1.2M—829 HALSEY OWNER LLC → 829 HALSEY LLC$247/sf building
12/06/2018$1.5M—IWC 827-829 HALSEY STREET LLC → 829 HALSEY OWNER LLC$304/sf building
06/30/2014$1.1M—— → —$228/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TECTONIC ENGINEERING & SURVEYING CO310/22/2025
RISE ARCHITECTURE103/09/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JACK JAFFA & ASSOCIATES103/21/2026
CONSTRUCTION PERMIT SERVICES303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BUDO MAINTENANCE CORPGeneral Contractor603/21/2026
RC3 ELECTRIC, LLCGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TECTONIC ENGINEERING CONS106310/22/2025
BIZ DESIGNS LLC6312103/09/2022
SIA INSPECTIONS LLC7306103/09/2022
Building Lifecycle
All (73)Filed (4)Permit Issued (4)Signed Off (1)Violation (60)Objection (4)
09/03/2026
Violation issued (HPD, open)
C
09/03/2026
Violation issued (HPD, open)
A
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
A
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
A
09/03/2026
Violation issued (HPD, open)
C
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
C
09/03/2026
Violation issued (HPD, open)
A
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
A
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
B
09/03/2026
Violation issued (HPD, open)
B
08/31/2026
Violation issued (HPD, open)
C
08/31/2026
Violation issued (HPD, open)
A
08/31/2026
Violation issued (HPD, open)
C
08/31/2026
Violation issued (HPD, open)
A
05/31/2026
Violation issued (HPD, closed)
B
05/31/2026
Violation issued (HPD, closed)
B
05/18/2026
Violation issued (HPD, open)
C
05/18/2026
Violation issued (HPD, open)
B
05/18/2026
Violation issued (HPD, open)
B
05/04/2026
Permit issued — Antenna
B00792728-I1-AN
05/02/2026
Permit issued — General Construction
B00792728-S1-GC
04/08/2026
Violation issued (HPD, closed)
A
04/08/2026
Violation issued (HPD, closed)
A
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, closed)
C
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, open)
C
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, open)
B
02/04/2026
Violation issued (HPD, closed)
A
02/04/2026
Violation issued (HPD, closed)
C
11/12/2025
Objection resolved — Addressed
11/12/2025
Objection resolved — Addressed
11/10/2025
Objection raised — Scope
11/10/2025
Objection raised — Scope
10/22/2025
Filed — Alteration
Installation of safety railing and skylight guard. Repair parapets as per plans. No change in use, egress, or occupancy.
B00792728-P1
10/17/2025
Violation issued (HPD, open)
B
10/17/2025
Violation issued (HPD, open)
C
10/17/2025
Violation issued (HPD, closed)
C
10/17/2025
Violation issued (HPD, open)
B
10/17/2025
Violation issued (HPD, open)
B
10/17/2025
Violation issued (HPD, open)
B
10/14/2025
Filed — Alteration
Installation of safety railing and skylight guard. Repair parapets as per plans. No change in use, egress, or occupancy.
B00792728-S1
10/12/2025
Violation issued (HPD, open)
A
10/12/2025
Violation issued (HPD, open)
C
Latest 60 of 73 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWAntennaPermit IssuedRC3 ELECTRIC, LLC05/04/2026
DOB NOWGeneral ConstructionPermit IssuedRC3 ELECTRIC, LLC05/02/2026
DOB NOWGeneral ConstructionSigned-offBUDO MAINTENANCE CORP04/12/2022
DOB NOWGeneral ConstructionSigned-offBUDO MAINTENANCE CORP03/31/2022
BISPLISSUEDCLEAN TECH MECHANICAL INC02/05/2021
BISOTISSUEDKG MANAGEMENT CNSLTNG INC01/21/2021
BISOTISSUEDINNOVATIVE VENTURES TEAM09/29/2020
BISPLISSUEDEH PLUMBING & HEATING COR07/20/2020
BISOTISSUEDINNOVATIVE VENTURES TEAM02/14/2020
BISPLISSUEDS & L PLUMBING INC10/04/2019
BISOTISSUEDKTC DESIGN GROUP INC10/04/2019
BISOTISSUEDRC3 ELECTRIC, LLC07/27/2017
BISOTISSUEDRC3 ELECTRIC, LLC07/27/2017
4 projects · most recent 04/05/2022
General Wiring
FiledStatusContractorScope
04/05/2022CompleteACCURATE ELEC'L CORP.General Wiring
01/20/2021Permit IssuedE & M ELECTRICAL NY CORPGeneral Wiring
06/18/2020CompleteNEKA ELECTRIC INCGeneral Wiring
06/11/2020Permit IssuedWCK ELECTRIC CORP.General Wiring
Nothing on file for this building.
▾Documents — 91 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/31/2026B00673710-I1Request digital key ↗
08/27/2026B00792728-I1Request digital key ↗
08/27/2026B00792728-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits20
▸BISPLAN / WORK APPROVAL APPLICATION10
07/16/2021321950126Open ↗
11/09/2020321401041Open ↗
11/09/2020321401050Open ↗
Showing 3 of 10 on file for this type
▸BISWORK PERMIT APPLICATION8
03/03/2021321950126Open ↗
01/22/2021321950126Open ↗
07/24/2020321950126Open ↗
Showing 3 of 8 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
12/28/2020321401041Open ↗
04/13/2017321401050Open ↗
▸Seals & Professional Certifications13
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
10/08/2019321950126Open ↗
05/23/2019321950126Open ↗
07/28/2017321401041Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/31/2026B00673710-I1Open ↗
08/27/2026B00792728-I1Open ↗
08/13/2026B00792728-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/23/2026B00792728-S1Open ↗
08/23/2026B00792728-S1Open ↗
08/23/2026B00792728-S1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/23/2026B00792728-S1Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
05/31/2019321950126Open ↗
05/31/2019321950126Open ↗
05/23/2019321950126Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes3
07/28/2017321401050Open ↗
04/19/2017321401041Open ↗
07/29/2021321950126Open ↗
▸BISTPP1 AND TENANT PROTECTION NOTES PRIOR TO THE PERMIT IS REQUIRED1
01/06/2021321401050Open ↗
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/31/2026B00673710-I1Open ↗
08/27/2026B00792728-I1Open ↗
08/13/2026B00792728-P1Open ↗
Showing 3 of 4 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
05/23/2019321950126Open ↗
06/29/2016321401050Open ↗
06/29/2016321401041Open ↗
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
05/31/2019321950126Open ↗
05/23/2019321950126Open ↗
07/28/2017321401041Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
02/07/2022321950126Open ↗
01/06/2021321401050Open ↗
12/18/2020321401041Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
02/07/2022321950126Open ↗
01/06/2021321401050Open ↗
12/18/2020321401041Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026B00673710-I1Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
02/07/2022321950126Open ↗
01/06/2021321401050Open ↗
12/18/2020321401041Open ↗
▸Approvals, Objections & Sign-offs6
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
02/08/2022321950126Open ↗
01/06/2021321401050Open ↗
12/28/2020321401041Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
03/03/2021321950126Open ↗
01/22/2021321950126Open ↗
▸BISSUPERSEDING LETTER1
07/24/2020321950126Open ↗
▸Cost, Insurance & Ownership5
▸BISCOST AFFIDAVIT5
02/07/2022321950126Open ↗
05/31/2019321950126Open ↗
05/23/2019321950126Open ↗
Showing 3 of 5 on file for this type
▸Filing & Intake Forms8
▸BISEFILING COVER SHEET4
05/31/2019321950126Open ↗
05/23/2019321950126Open ↗
06/29/2016321401050Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION3
01/22/2021321401050Open ↗
12/10/2020321401041Open ↗
05/23/2017321401050Open ↗
▸BISBOROUGH INTAKE FORM1
03/03/2021321950126Open ↗
▸Other Documents6
▸DOB NOWHPD4: CONH Pilot Program3
08/27/2026B00792728-I1Open ↗
08/13/2026B00792728-P1Open ↗
08/13/2026B00792728-S1Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
05/05/2017321401041Open ↗
▸BISAS PER DOC 1 SECTION 26 OWNERS CERTIFICATIO BUILDINGS MARKED FOR YES AS OCCUPIED1
01/06/2021321401050Open ↗
▸BISTEMPORARY FLOOD SHIELDS: EMERGENCY FLOOD PLAN1
05/23/2019321950126Open ↗