| Owner | Filings | Most Recent |
|---|---|---|
| UNITED ASSETS CORPORATION USA | 3 | 03/22/2026 |
| RIZE CONSTRUCTION | 4 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/25/2025 | $775K | — | PRIME NOTES INC. → LINDEN LANE OWB LLC | $465/sf building |
| 11/10/2025 | $400K | — | UNITED ASSETS CORPORATION USA → PRIME NOTES INC | $240/sf building |
| 01/23/2019 | $715K | — | Private party → UNITED ASSETS CORPORATION USA | $429/sf building |
| 08/17/2017 | $475K | — | Private party → Private party | $285/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BARRY J. BANK, P.E., CONSULTING ENG | 2 | 06/24/2022 |
| CARUSONE & CHERRES ARCHITECTS, LLC | 1 | 11/16/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| AB WORKS PROCESSING | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RIZE CONSTRUCTION LLC | General Contractor | 7 | 07/08/2026 |
| KEITH EDWARDS | General Contractor | 1 | 07/08/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BARRY J. BANK, P.E. | 1868 | 2 | 06/24/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | KEITH EDWARDS | 05/07/2026 |
| DOB NOW | Plumbing | Permit Issued | JOHN FITZGERALD PLBG &HTG | 08/09/2022 |
| DOB NOW | Construction Fence | Permit Issued | RIZE CONSTRUCTION LLC | 04/14/2022 |
| DOB NOW | General Construction | Permit Issued | RIZE CONSTRUCTION LLC | 01/24/2022 |
| DOB NOW | Construction Fence | Permit Issued | RIZE CONSTRUCTION LLC | 11/18/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2022 | Permit Issued | JOHN FITZGERALD PLBG &HTG | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2022 | Permit Issued | Y.S ELECTRIC | General Wiring, Lighting |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/22/2022 | Fire-Resistant Penetrations and Joints | Barry Bank, P.E. | special |
| 06/22/2022 | Energy Code Compliance Inspections | Barry Bank, P.E. | progress |
| 06/22/2022 | HVAC and service water heating system controls | Barry Bank, P.E. | energy_progress |
| 06/22/2022 | HVAC and service water heating equipment | Barry Bank, P.E. | energy_progress |
| 06/22/2022 | Maintenance information | Barry Bank, P.E. | energy_progress |
| 06/22/2022 | HVAC insulation and sealing | Barry Bank, P.E. | energy_progress |
| 02/26/2021 | Subgrade Inspections | Barry Bank, P.E. | special |
| 01/19/2021 | Concrete - Cast-In-Place | Barry Bank, P.E. | special |
| 01/19/2021 | Fire-Resistant Penetrations and Joints | Barry Bank, P.E. | special |
| 01/19/2021 | Structural Stability – Alterations of existing buildings | Barry Bank, P.E. | special |
| 01/19/2021 | Energy Code Compliance | Barry Bank, P.E. | progress |
| 01/19/2021 | Energy Code Compliance Inspections | Barry Bank, P.E. | progress |
| 01/19/2021 | Fire-Resistance Rated Construction | Barry Bank, P.E. | progress |
| 01/19/2021 | Air barrier - visual inspection | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Maintenance information | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Insulation placement and R values | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Fenestration and door U-factor and product ratings | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Air barrier continuity plan testing | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Metering | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Fenestration areas | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Interior lighting power | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Permanent certificate | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | HVAC-R and service water piping design and insulation | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Fenestration air leakage | Barry Bank, P.E. | energy_progress |
| 01/19/2021 | Lighting in dwelling units | Barry Bank, P.E. | energy_progress |