RoofUnder Construction27p · 3 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Structural
Use a spider crane during construction
On file for this project
44 documents · 2 drawing sheets
Installation of the Engineered Enclosure System in conjunction with Demolition application #M00976164
On file for this project
2 documents
Use of a small crane during demolition
On file for this project
2 documents
Floor 81 filing · 2 docs
Issued Permit Scope
Protection and Mechanical Methods
Use of a small crane during demolition
On file for this project
2 documents
Floor 71 filing · 2 docs
Issued Permit Scope
Protection and Mechanical Methods
Use of a small crane during demolition
On file for this project
2 documents
Floor 6Under Construction25p · 2 filings · 20 docs
Structural
Issued Permit Scope
Protection and Mechanical Methods · Structural
Use a spider crane during construction
On file for this project
44 documents
Use of a small crane during demolition
On file for this project
2 documents
Floor 5Under Construction53p · 2 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods · Structural
Use a spider crane during construction
On file for this project
44 documents
Use of a small crane during demolition
On file for this project
2 documents
Floor 4Under Construction54p · 3 filings · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods · Structural
Use a spider crane during construction
On file for this project
44 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY SHALL COMPLY WITH CHAPTER#33 OF 2022 THE NY BUILDING CODE.
On file for this project
6 documents
Use of a small crane during demolition
On file for this project
2 documents
Floor 3Under Construction56p · 3 filings · 20 docs
ArchitectureMechanicalStructuralZ
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods · Structural
Use a spider crane during construction
On file for this project
44 documents · 3 drawing sheets
Installation of the Engineered Enclosure System in conjunction with Demolition application #M00976164
On file for this project
2 documents
Use of a small crane during demolition
On file for this project
2 documents
Floor 2Under Construction38p · 4 filings · 20 docs
ArchitectureDMElectricalMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods
Use a spider crane during construction
On file for this project
44 documents · 2 drawing sheets
Full demolition of the 3 story building
On file for this project
14 documents · 1 drawing sheet
Installation of the Engineered Enclosure System in conjunction with Demolition application #M00976164
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 1Under Construction35p · 3 filings · 20 docs
ArchitectureMechanical
Issued Permit Scope
General Construction · Mechanical Systems · Protection and Mechanical Methods
Use a spider crane during construction
On file for this project
44 documents
Installation of the Engineered Enclosure System in conjunction with Demolition application #M00976164
On file for this project
2 documents
Use of a small crane during demolition
On file for this project
2 documents
CellarUnder Construction41p · 2 filings · 20 docs
ArchitectureCivilMechanicalStructural
Issued Permit Scope
Earth Work · General Construction · Mechanical Systems · Support of Excavation
Use a spider crane during construction
On file for this project
44 documents · 3 drawing sheets
PROPOSED TO KEEP SUPPORTS INSTALLED DURING DEMOLITION JOB M00976164 TO SUPPORT FOUNDATION WALLS IN THE CELLAR AFTER 1ST FLOOR STRUCTURE IS REMOVED. THE FOUNDATION WALLS WILL REMAIN UNTIL A CONSTRUCTION OF THE NEW BUILDING WILL START.
On file for this project
3 documents