💬 Discuss this project
2004Year Built
2Stories
B2Building Class
R3XZoning
1,584 sfGross Floor Area
2Units
Two family frame · 5,819 sf lot · 0.27 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalLandscapeGeneral
Roof2p · 1 filing · 8 docs
Filed — no permit issued5p · 1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PARKER AND WEST ENGINEERING, PLLC101/28/2025
ACCENT ARCHITECTURE PLLC108/30/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUNRUN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SUNRUN SOLAR ELECTL CORPElectrical103/22/2026
SUNRUN INSTALLATION SVCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PARKER AND WEST ENGINEERI5272101/28/2025
Building Lifecycle
All (27)Filed (2)Permit Issued (1)Signed Off (1)Objection (2)Special Inspection (21)
08/05/2025
Signed off — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01172158-I1
02/03/2025
Permit issued — Solar
S01172158-I1-SL
01/28/2025
Filed — Alteration
FILING HEREWITH TAX ABATEMENT APPLICATION FOR INSTALLATION OF ROOF MOUNTED SOLAR PANELS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
S01172158-I1
01/27/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Walid Abdulla
01/27/2025
Special inspection requirement — Final
Walid Abdulla
01/27/2025
Special inspection requirement — Air barrier - visual inspection
Walid Abdulla
01/27/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Walid Abdulla
01/27/2025
Special inspection requirement — Energy Code Compliance Inspections
Walid Abdulla
10/05/2023
Objection raised — Zoning
10/05/2023
Objection raised — Other
08/30/2023
Filed — Alteration CO
NEW TWO STORY EXTENSION
S00529893-I1
05/30/2023
Special inspection requirement — Structural Steel - Details
02/13/2023
Special inspection requirement — Construction Operations Influencing Adjacent Structures
05/27/2021
Special inspection requirement — Structural Wood Frame
05/27/2021
Special inspection requirement — Mechanical Systems
05/27/2021
Special inspection requirement — Insulation placement and R values
05/27/2021
Special inspection requirement — Fenestration air leakage
05/27/2021
Special inspection requirement — Air barrier - visual inspection
05/27/2021
Special inspection requirement — Lighting in dwelling units
05/27/2021
Special inspection requirement — Interior lighting power
05/27/2021
Special inspection requirement — Fire-Resistance Rated Construction
05/27/2021
Special inspection requirement — Concrete - Cast-In-Place
05/27/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/27/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
05/27/2021
Special inspection requirement — Final
05/27/2021
Special inspection requirement — Footing and Foundation
05/27/2021
Special inspection requirement — Energy Code Compliance Inspections
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSUNRUN INSTALLATION SVC02/03/2025
BIS—ISSUEDHONESTY HOMES INC07/16/2003
1 project · most recent 08/30/2023
Air Conditioning Systems Generators Heating and Air Conditioning Systems Heating Systems
FiledStatusContractorScope
08/30/2023——Air Conditioning Systems, Generators, Heating and Air Conditioning Systems, Heating Systems
1 project · most recent 01/28/2025
FiledStatusContractorScope
01/28/2025CompleteSUNRUN SOLAR ELECTL CORP—
1 project · most recent 08/30/2023
Steel Concrete Wood
FiledStatusContractorScope
08/30/2023——Steel, Concrete, Wood
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
01/27/2025Structural Stability – Alterations of existing buildingsWalid Abdullaspecial
01/27/2025FinalWalid Abdullaprogress
01/27/2025Air barrier - visual inspectionWalid Abdullaenergy_progress
01/27/2025Fire-Resistant Penetrations and JointsWalid Abdullaspecial
01/27/2025Energy Code Compliance InspectionsWalid Abdullaprogress
05/30/2023Structural Steel - Details—special
02/13/2023Construction Operations Influencing Adjacent Structures—special
05/27/2021Structural Wood Frame—progress
05/27/2021Mechanical Systems—special
05/27/2021Insulation placement and R values—energy_progress
05/27/2021Fenestration air leakage—energy_progress
05/27/2021Air barrier - visual inspection—energy_progress
05/27/2021Lighting in dwelling units—energy_progress
05/27/2021Interior lighting power—energy_progress
05/27/2021Fire-Resistance Rated Construction—progress
05/27/2021Concrete - Cast-In-Place—special
05/27/2021Fire-Resistant Penetrations and Joints—special
05/27/2021Structural Stability – Alterations of existing buildings—special
05/27/2021Final—progress
05/27/2021Footing and Foundation—progress
05/27/2021Energy Code Compliance Inspections—progress
▾Documents — 14 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026S01172158-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026S00529893-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026S00529893-I1Open ↗
▸DOB NOWRestrictive Declaration/Easement 11
08/13/2026S00529893-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026S00529893-I1Open ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/26/2026S01172158-I1Open ↗
08/26/2026S01172158-I1Open ↗
08/26/2026S01172158-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026S01172158-I1Open ↗
08/26/2026S01172158-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/20/2026S01172158-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026S01172158-I1Open ↗
▸Other Documents2
▸DOB NOWFinal Survey1
08/13/2026S00529893-I1Open ↗
▸DOB NOWPlot Diagram1
08/13/2026S00529893-I1Open ↗